Radiation Protection at the LHC Lessons Learned
- D. Forkel-Wirth, D. Perrin, S. Roesler, C. Theis,
Heinz Vincke, Helmut Vincke, J. Vollaire CERN-SC-RP-SL
13 October 2006, ILC and LHC Forum
Radiation Protection at the LHC Lessons Learned D. Forkel-Wirth, D. - - PowerPoint PPT Presentation
Radiation Protection at the LHC Lessons Learned D. Forkel-Wirth, D. Perrin, S. Roesler, C. Theis, Heinz Vincke, Helmut Vincke, J. Vollaire CERN-SC-RP-SL 13 October 2006, ILC and LHC Forum Lessons learnt about RP involvement into a project
13 October 2006, ILC and LHC Forum
Conclusion:
costs during the construction phase
during operation
and to be treated like all other sub-project groups with respect to staffing and budgeting – from the design phase onwards
Total beam loss “Normal” beam loss Ambient Dose Equivalent in mSv Ambient Dose Equivalent Rate in uSv/h Simple Controlled Area 50 10 Supervised Area 2.5 1 Non-designated Area 0.3 0.1
Fortunately very conservative parameters were chosen in 1995 but still problems in 2006: Consequence: in some cases we had to abandon all safety margins with respect to calculations (a safety factor of two to three is normally applied)
1 mSv 2.5 mSv 20 mSv 50 mSv 3 uSv/h 10 uSv/h 2006 1995 Internal exposure of the public: < 10 uSv per year to the critical group (> 2003)
Consignes à appliquer lors des activités de maintenance en fonction des débits de doses ambiants. Niveau de référence du débit de doses ambiant Consignes à appliquer lors des activités de maintenance > 100 µSv/h Tous les travaux doivent être soigneusement planifiés et optimisés. > 2 mSv/h Tous les travaux doivent être soigneusement planifiés ; la durée de l’intervention dans la zone doit être strictement limitée ; la télémanipulation des composants est à envisager sérieusement. > 20 mSv/h Aucun travail n’est autorisé dans les endroits où les débits de doses sont supérieurs à cette valeur, car les limites de dose seraient trop facilement atteintes voir dépassées. La télémanipulation des objets est essentielle.
maps – only dose rates on “infinite” surfaces were available -> dose estimates would have resulted in unrealistic high numbers
Location of Samples: Behind a 50 cm long, 7 cm diameter copper target, centered with the beam axis
the LHC
for a large number of cooling times
found between the simulation and the experiment (disagreements less than 20 %)
121.6 cm
12.0 cm 26.0 cm
Graphite Cu (reduced density) Steel 8.0 cm 9.2 cm 8.2 cm
the SPS-LHC transfer line (TT40)
at two different cooling times of one week and one month
within 10%
approach
* H. * H. Vincke Vincke
1st Measurement after two weeks of cooling Measured dose rate: 0.95 mSv/h Simulated dose rate: ~1.1 mSv/h 2nd Measurement after one month of cooling Measured dose rate: 0.4 mSv/h Simulated dose rate: ~0.4 mSv/h
* H. * H. Vincke Vincke
at their less-radioactive end.
resistant cables in high-loss areas.
with the highest expected losses.
mixed radiation fields
(RAMSES):
with location ID Radiation Display Display Control box Radiation Monitor
Monitor
Controller Direct hardware connection Tap box
Basic Area Controller
with ID + local database RP Data Base long term storage RP User Interface Remote User Interface
Internet LHC point (local Network) CERN Networks (Ethernet)
RP User Interface Configuration and Supervision Manager
1.E-08 1.E-07 1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01 1.E-09 1.E-08 1.E-07 1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01 1.E+00 1.E+01
Energy [GeV] d Φ / d ln(E) [1/cm2]
kaons pion+ pion- neutrons protons photons electrons 1.E-10 1.E-09 1.E-08 1.E-07 1.E-06 1.E-05 1.E-04 1.E-09 1.E-08 1.E-07 1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01 1.E+00 1.E+01
Energy [GeV] d Φ / d ln(E) [1/cm2]
kaons pion+ pion- neutrons protons photons
Air filled ionisation chamber (PMI) wall: C-H2 volume: 3 l gas: air, 1 atm voltage: 400 V High-pressure ionisation chamber (IG5) volume: 5,2 l active gas: Ar or H (20 bar) high-voltage: 1200 V
SPS secondary hadron beam is hitting a copper target irradiation of the PMI chambers with different radiation fields at various positions.
Pos 1 Pos 2 Pos 3 Pos 4 Pos 5 Pos 6
Hadron beam
Cu target Beam parameters:
120 GeV/c
9*107 hadrons/ SPS cycle (16.8 s with 4.8 s continuous beam)
60.7% π+ 34.8% p 4.5% K+
air filled plastic chambers
1E-4 1E-3 0.01 0.1 1 10 100 1E-9 1E-8 1E-7 1E-6 1E-5 1E-4 1E-3 0.01 0.1
Position 2
neutrons photons
e
+/e
Energy (GeV)
Pos 6 Pos 5 Pos 4 Pos 3 Pos 2 Pos 1 beam
Pos 6 Pos 5 Pos 4 Pos 3 Pos 2 Pos 1 beam
1E-4 1E-3 0.01 0.1 1 10 100 1E-9 1E-8 1E-7 1E-6 1E-5 1E-4 1E-3 0.01 0.1
Position 4
neutrons photons
e
+/e
Energy (GeV)
1E-4 1E-3 0.01 0.1 1 10 100 1E-9 1E-8 1E-7 1E-6 1E-5 1E-4 1E-3 0.01 0.1
Position 6
neutrons photons
e
+/e
Energy (GeV)
Pos 6 Pos 5 Pos 4 Pos 3 Pos 2 Pos 1 beam
± 0.146 0.936
± 17,99 115,74 ± 0,82 108,31
Pos 6 ± 0.115 1.076
± 9,47 89,39 ± 1,26 96,20
Pos 5 ± 0.119 1.080
± 8,67 79,00 ± 0,64 85,33
Pos 4 ± 0.104 1.003
± 6,93 67,25 ± 0,73 67,46
Pos 3 ± 0.107 1.031
± 1,56 15,58 ± 0,44 16,06
Pos 2 ± 0.102 0.998
± 0,56 5,64 ± 0,12 5,63
Pos 1 Error Simulation/ Measurement Measurement error *10-6 Measurement Counts/
Simulation error *10-6 Simulation Counts/
*10-6
PS super-cycle
1 4 .4 s
BOOSTER
1 .2 s SPS
FI X TARGETS North & W est areas
East area AD East area SPP SPN SPS ( Machine Developm ent)
I ntegrator Comparator Threshold Control circuitry Charge pump I nput (charge) charge buffer Output signal (frequency) Integrator Input (charge) Output signal (fieldbus) Processor Low charge injection switch Adaptive digitizer
For pulsed fields the read-out electronics has to be based on charge digitizers Range to be covered: 10-14 A (background level) - 10-5 A Switching not permitted! Present CERN electronics covers 5 – 6 decades Newly developed: 9 – 10 decades First tests: electronics measures reliably up to 300 nC/pulse ~ 50 mGy/hour (LHC injection)