PROGRAMS OVERVIEW February 8, 2018 Presentation Outline Pavement - - PowerPoint PPT Presentation
PROGRAMS OVERVIEW February 8, 2018 Presentation Outline Pavement - - PowerPoint PPT Presentation
FY18 ANNUAL PROGRAMS OVERVIEW February 8, 2018 Presentation Outline Pavement Management Overview 2017 Annual Programs 2018 Concrete Program 2018 Asphalt Program 2018 Crack Seal Program Presentation Outline Pavement
Presentation Outline
Pavement Management Overview 2017 Annual Programs 2018 Concrete Program 2018 Asphalt Program 2018 Crack Seal Program
Presentation Outline
Pavement Management Overview 2017 Annual Programs 2018 Concrete Program 2018 Asphalt Program 2018 Crack Seal Program
Pavement Management
Road network is City’s most valuable resource
Valued at over $400,000,000.00
Data-based decision making and trend analysis
factor heavily into the process, and can improve efficiency and efficacy
3,418 street sections (~650 Lane Miles)
2965 Sections (~580 LM) – Concrete (84%) 453 Sections (~70 LM) – Asphalt (16%)
Pavement Management
100 200 300 400 500 600 700 800 900 0-9 10-14 15-19 20-24 25-29 30-34 35+
Number of Sections Street Age (Yrs.)
O'Fallon Street Age
Asphalt Concrete
Pavement Management
City developed a Strategic Plan in 2017
E.vii. – Raise the Pavement Condition Index (PCI) rating
- f the O’Fallon City streets such that no more than 10%
- f the roadways are rated as less than 75.
Recommend a strategy for upgrading and maintaining the City’s most valuable asset.
E.xi. – Design a program that will replace concrete
slabs on a 30-year rotation (7,000 slabs annually), crack seal on a 5-year cycle (1.2M feet of cracks annually) and overlay asphalt on a 12-year cycle (72,300 square yards annually) by increasing funding.
Pavement Management
City Staff estimate that $5M per year is needed
- ver the next five (5) years to achieve the strategic
goals, with increases in funding in the following years
City Staff have presented several times in regards
to opportunities for increased funding:
Use Tax, ½ cent sales tax, Street Light Fees, Recouping
Property Tax, Etc.
Pavement Management
Presentation Outline
Pavement Management Overview 2017 Annual Programs 2018 Concrete Program 2018 Asphalt Program 2018 Crack Seal Program
2017 Concrete Program
Total Funding - $3.992 M City Council approved three (3) different types of
repairs for concrete streets
Removal of partial-depth asphalt joint replacement
(Mill and Fill)
Clearing the backlog of open Work Orders (WO) Concrete streets that have the lowest PCI ranking in the
City (Low PCI)
2017 Concrete Program
Removal of partial-depth asphalt joint replacement
(Mill and Fill)
Six (6) subdivisions cleared of PDAJ repairs, replaced
with new concrete slabs ($750K)
Clearing the backlog of open Work Orders (WO)
In collaboration with Streets Dept., reduced WOs from
283 to 19 upon completion ($2.25M)
Concrete streets that have the lowest PCI ranking in
the City (Low PCI)
Repaired the 20 lowest rated concrete streets in the
City ($1M)
2017 Concrete Program
Fixed issues on over 350 street sections throughout
the City
Replaced nearly 3,000 concrete slabs (1.4% of
total slabs in the City)
Replaced 62,600 Sq. Yds. Of 7” Concrete Replaced 5,400 Sq. Yds. Of 8” Concrete
Replaced 420 Ft. of Concrete Curb Ramp Installed 970 Ft. of Underdrains Completed ahead of schedule
2017 Asphalt Program
No funding was allotted for this program in 2017. No asphalt streets were repaired.
2017 Crack Seal Program
Sealing 13 Residential Subdivisions (all roads) Sealing 24 Individual Streets Approx. 31 miles of roadway will receive Crack
Sealing
Approx. 162,000 ft. of roadway will receive Crack
Sealing
Anticipated completion of project by end of June
Presentation Outline
Pavement Management Overview 2017 Annual Programs 2018 Concrete Program 2018 Asphalt Program 2018 Crack Seal Program
2018 Concrete Program
Types of Street Repairs
Mill/Fill Segments Low PCI Segments Combination of Repairs
Focused on slab removal Most efficient when doing lots of work in an area
2018 Concrete Program
Scenario #1 – M&F
2018 Concrete Program
Scenario #2 – Low PCI
13% of concrete sections remain rated below 75
2018 Concrete Program
Scenario #3
Combination of M&F and Low PCI $1.5M = ~1100 concrete slabs Staff would need guidance on City Council’s preferred
allocation percentages (i.e. 50% M&F, 50% PCI, etc.)
2018 Concrete Program
Staff Recommendation
Scenario #2 Has more impact in terms of overall street ratings, in
keeping with strategic plan initiatives
Utilize the Streets Dept. to systematically eliminate the
partial-depth asphalt joints (Mill & Fill) over a number
- f years
Presentation Outline
Pavement Management Overview 2017 Annual Programs 2018 Concrete Program 2018 Asphalt Program 2018 Crack Seal Program
2018 Asphalt Program
Types of Street Repairs
Full Depth Repairs (Base Failure) 2” Overlay Rejuvenator / Surface Treatment
Lots of options in this area Most efficient when doing lots of work in an area
2018 Asphalt Program
2018 Concrete Program
Staff Recommendation
90% Funding towards FDR / 2” Overlay 10% Funding towards Rejuvenation/Surface Treatment Allows staff to address the worst roads, while keeping
newly replaced roads in good condition
Most efficient use of funding with regard to asphalt
road repairs, per industry experts
Presentation Outline
Pavement Management Overview 2017 Annual Programs 2018 Concrete Program 2018 Asphalt Program 2018 Crack Seal Program
2018 Crack Seal Program
Working on a definite direction for this program Completing one (1) Ward per year, to comply with the
strategic plan initiative
Ward 1 – 72.5 CLM Ward 2 – 52.2 CLM Ward 3 – 64.5 CLM Ward 4 – 53.6 CLM Ward 5 – 68.7 CLM
Avg. Cost
$3,000/CLM – residential streets $6,000/CLM – collector roads $12,000/CLM – major arterials
Next Steps
Presentation of the 2017 O’Fallon Pavement
Manual to City Council (2/22)
Utilizing PAVER software for project forecasting and
planning
Developing systematic approach for