PROGRAMS OVERVIEW February 8, 2018 Presentation Outline Pavement - - PowerPoint PPT Presentation

programs overview
SMART_READER_LITE
LIVE PREVIEW

PROGRAMS OVERVIEW February 8, 2018 Presentation Outline Pavement - - PowerPoint PPT Presentation

FY18 ANNUAL PROGRAMS OVERVIEW February 8, 2018 Presentation Outline Pavement Management Overview 2017 Annual Programs 2018 Concrete Program 2018 Asphalt Program 2018 Crack Seal Program Presentation Outline Pavement


slide-1
SLIDE 1

FY18 ANNUAL PROGRAMS OVERVIEW

February 8, 2018

slide-2
SLIDE 2

Presentation Outline

 Pavement Management Overview  2017 Annual Programs  2018 Concrete Program  2018 Asphalt Program  2018 Crack Seal Program

slide-3
SLIDE 3

Presentation Outline

 Pavement Management Overview  2017 Annual Programs  2018 Concrete Program  2018 Asphalt Program  2018 Crack Seal Program

slide-4
SLIDE 4

Pavement Management

 Road network is City’s most valuable resource

 Valued at over $400,000,000.00

 Data-based decision making and trend analysis

factor heavily into the process, and can improve efficiency and efficacy

 3,418 street sections (~650 Lane Miles)

 2965 Sections (~580 LM) – Concrete (84%)  453 Sections (~70 LM) – Asphalt (16%)

slide-5
SLIDE 5

Pavement Management

100 200 300 400 500 600 700 800 900 0-9 10-14 15-19 20-24 25-29 30-34 35+

Number of Sections Street Age (Yrs.)

O'Fallon Street Age

Asphalt Concrete

slide-6
SLIDE 6

Pavement Management

 City developed a Strategic Plan in 2017

 E.vii. – Raise the Pavement Condition Index (PCI) rating

  • f the O’Fallon City streets such that no more than 10%
  • f the roadways are rated as less than 75.

Recommend a strategy for upgrading and maintaining the City’s most valuable asset.

 E.xi. – Design a program that will replace concrete

slabs on a 30-year rotation (7,000 slabs annually), crack seal on a 5-year cycle (1.2M feet of cracks annually) and overlay asphalt on a 12-year cycle (72,300 square yards annually) by increasing funding.

slide-7
SLIDE 7

Pavement Management

 City Staff estimate that $5M per year is needed

  • ver the next five (5) years to achieve the strategic

goals, with increases in funding in the following years

 City Staff have presented several times in regards

to opportunities for increased funding:

 Use Tax, ½ cent sales tax, Street Light Fees, Recouping

Property Tax, Etc.

slide-8
SLIDE 8

Pavement Management

slide-9
SLIDE 9

Presentation Outline

 Pavement Management Overview  2017 Annual Programs  2018 Concrete Program  2018 Asphalt Program  2018 Crack Seal Program

slide-10
SLIDE 10

2017 Concrete Program

 Total Funding - $3.992 M  City Council approved three (3) different types of

repairs for concrete streets

 Removal of partial-depth asphalt joint replacement

(Mill and Fill)

 Clearing the backlog of open Work Orders (WO)  Concrete streets that have the lowest PCI ranking in the

City (Low PCI)

slide-11
SLIDE 11

2017 Concrete Program

 Removal of partial-depth asphalt joint replacement

(Mill and Fill)

 Six (6) subdivisions cleared of PDAJ repairs, replaced

with new concrete slabs ($750K)

 Clearing the backlog of open Work Orders (WO)

 In collaboration with Streets Dept., reduced WOs from

283 to 19 upon completion ($2.25M)

 Concrete streets that have the lowest PCI ranking in

the City (Low PCI)

 Repaired the 20 lowest rated concrete streets in the

City ($1M)

slide-12
SLIDE 12

2017 Concrete Program

 Fixed issues on over 350 street sections throughout

the City

 Replaced nearly 3,000 concrete slabs (1.4% of

total slabs in the City)

 Replaced 62,600 Sq. Yds. Of 7” Concrete  Replaced 5,400 Sq. Yds. Of 8” Concrete

 Replaced 420 Ft. of Concrete Curb Ramp  Installed 970 Ft. of Underdrains  Completed ahead of schedule

slide-13
SLIDE 13

2017 Asphalt Program

 No funding was allotted for this program in 2017.  No asphalt streets were repaired.

slide-14
SLIDE 14

2017 Crack Seal Program

 Sealing 13 Residential Subdivisions (all roads)  Sealing 24 Individual Streets  Approx. 31 miles of roadway will receive Crack

Sealing

 Approx. 162,000 ft. of roadway will receive Crack

Sealing

 Anticipated completion of project by end of June

slide-15
SLIDE 15

Presentation Outline

 Pavement Management Overview  2017 Annual Programs  2018 Concrete Program  2018 Asphalt Program  2018 Crack Seal Program

slide-16
SLIDE 16

2018 Concrete Program

 Types of Street Repairs

 Mill/Fill Segments  Low PCI Segments  Combination of Repairs

 Focused on slab removal  Most efficient when doing lots of work in an area

slide-17
SLIDE 17

2018 Concrete Program

 Scenario #1 – M&F

slide-18
SLIDE 18

2018 Concrete Program

 Scenario #2 – Low PCI

13% of concrete sections remain rated below 75

slide-19
SLIDE 19

2018 Concrete Program

 Scenario #3

 Combination of M&F and Low PCI  $1.5M = ~1100 concrete slabs  Staff would need guidance on City Council’s preferred

allocation percentages (i.e. 50% M&F, 50% PCI, etc.)

slide-20
SLIDE 20

2018 Concrete Program

 Staff Recommendation

 Scenario #2  Has more impact in terms of overall street ratings, in

keeping with strategic plan initiatives

 Utilize the Streets Dept. to systematically eliminate the

partial-depth asphalt joints (Mill & Fill) over a number

  • f years
slide-21
SLIDE 21

Presentation Outline

 Pavement Management Overview  2017 Annual Programs  2018 Concrete Program  2018 Asphalt Program  2018 Crack Seal Program

slide-22
SLIDE 22

2018 Asphalt Program

 Types of Street Repairs

 Full Depth Repairs (Base Failure)  2” Overlay  Rejuvenator / Surface Treatment

 Lots of options in this area  Most efficient when doing lots of work in an area

slide-23
SLIDE 23

2018 Asphalt Program

slide-24
SLIDE 24

2018 Concrete Program

 Staff Recommendation

 90% Funding towards FDR / 2” Overlay  10% Funding towards Rejuvenation/Surface Treatment  Allows staff to address the worst roads, while keeping

newly replaced roads in good condition

 Most efficient use of funding with regard to asphalt

road repairs, per industry experts

slide-25
SLIDE 25

Presentation Outline

 Pavement Management Overview  2017 Annual Programs  2018 Concrete Program  2018 Asphalt Program  2018 Crack Seal Program

slide-26
SLIDE 26

2018 Crack Seal Program

 Working on a definite direction for this program  Completing one (1) Ward per year, to comply with the

strategic plan initiative

 Ward 1 – 72.5 CLM  Ward 2 – 52.2 CLM  Ward 3 – 64.5 CLM  Ward 4 – 53.6 CLM  Ward 5 – 68.7 CLM

 Avg. Cost

 $3,000/CLM – residential streets  $6,000/CLM – collector roads  $12,000/CLM – major arterials

slide-27
SLIDE 27

Next Steps

 Presentation of the 2017 O’Fallon Pavement

Manual to City Council (2/22)

 Utilizing PAVER software for project forecasting and

planning

 Developing systematic approach for

planning/execution of O’Fallon Annual Programs