PRESENTATION TO PRESENTATION TO THE THE INTERNATIONAL ASSOCIATION - - PowerPoint PPT Presentation

presentation to presentation to the the international
SMART_READER_LITE
LIVE PREVIEW

PRESENTATION TO PRESENTATION TO THE THE INTERNATIONAL ASSOCIATION - - PowerPoint PPT Presentation

PRESENTATION TO PRESENTATION TO THE THE INTERNATIONAL ASSOCIATION OF SCHOOL INTERNATIONAL ASSOCIATION OF SCHOOL LIBRARIANSHIP LIBRARIANSHIP PRE PRE- PRE PRE- -CONFERENCE MEETING -CONFERENCE MEETING CONFERENCE MEETING CONFERENCE


slide-1
SLIDE 1

PRESENTATION TO PRESENTATION TO THE THE INTERNATIONAL ASSOCIATION OF SCHOOL INTERNATIONAL ASSOCIATION OF SCHOOL LIBRARIANSHIP LIBRARIANSHIP PRE PRE-

  • CONFERENCE MEETING

CONFERENCE MEETING PRE PRE-

  • CONFERENCE MEETING

CONFERENCE MEETING Hosted by Hosted by THE THE LIBRARY AND INFORMATION ASSOCIATION LIBRARY AND INFORMATION ASSOCIATION OF JAMAICA OF JAMAICA AUGUST 5 2011 AUGUST 5 2011

slide-2
SLIDE 2
  • Overview of Project

Overview of Project

  • Project Achievements to Date

Project Achievements to Date, , Challenges, Mitigation Challenges, Mitigation Strategies Strategies

  • Strategies

Strategies

  • Plans to Project Completion

Plans to Project Completion

  • Impact of the Project on the Education System, the

Impact of the Project on the Education System, the Community and National Development Community and National Development

slide-3
SLIDE 3
  • In early 2004, in considering its goal for universal access,

In early 2004, in considering its goal for universal access, the Ministry with responsibility for telecommunications the Ministry with responsibility for telecommunications determined that an educated knowledge determined that an educated knowledge-

  • based society

based society would spur demand for Internet Services would spur demand for Internet Services

  • ITU fully endorsed and sponsored the design of an e

ITU fully endorsed and sponsored the design of an e-

  • ITU fully endorsed and sponsored the design of an e

ITU fully endorsed and sponsored the design of an e-

  • learning project, utilizing the technology to impact the

learning project, utilizing the technology to impact the education levels of Jamaica’s citizenry education levels of Jamaica’s citizenry

  • Preliminary Feasibility Study developed by Joint

Preliminary Feasibility Study developed by Joint Committee chaired by MOE Junior Minister Committee chaired by MOE Junior Minister

  • Consulting firm hired to finalize study in late 2004

Consulting firm hired to finalize study in late 2004

  • Cabinet approved 1

Cabinet approved 1st

st e-

  • Learning Jamaica project in March

Learning Jamaica project in March 2005 2005

slide-4
SLIDE 4

In 2005, In 2005, Govn

  • Govn. established two Agencies

. established two Agencies

  • The Universal Access Fund Company Limited

The Universal Access Fund Company Limited

  • to collect and manage a

to collect and manage a cess cess on calls terminating in Ja,

  • n calls terminating in Ja,

establish a broad band network to facilitate universal establish a broad band network to facilitate universal

  • establish a broad band network to facilitate universal

establish a broad band network to facilitate universal access, and fund ICT projects that will stimulate internet access, and fund ICT projects that will stimulate internet connectivity connectivity

  • The e

The e-

  • Learning Jamaica Company Limited

Learning Jamaica Company Limited

  • to develop and implement projects that will contribute

to develop and implement projects that will contribute to Universal Access to Universal Access

slide-5
SLIDE 5
  • Board of

Board of e-

  • Ljam

Ljam appointed July 2005 appointed July 2005

  • CEO hired Nov 2005

CEO hired Nov 2005

  • Project

Project launched in February 2006 launched in February 2006

  • Period to September 2006 used to staff and equip

Period to September 2006 used to staff and equip

  • Period to September 2006 used to staff and equip

Period to September 2006 used to staff and equip company and establish systems and procedures company and establish systems and procedures

  • Project started in September 2006

Project started in September 2006

  • 3 phased implementation planned

3 phased implementation planned

slide-6
SLIDE 6
  • Phase 1

Phase 1 -

  • pilot project

pilot project in 30 schools Sept 2006 in 30 schools Sept 2006 to Aug 2007 to Aug 2007

Phase 2 Phase 2 -

  • roll

roll-

  • out to 75
  • ut to 75
  • Phase 2

Phase 2 -

  • roll

roll-

  • out to 75
  • ut to 75

schools Sept 2007 to schools Sept 2007 to Aug 2008 Aug 2008

Phase 3 Phase 3 – roll

roll-

  • out to 75
  • ut to 75

schools Sept 2008 to schools Sept 2008 to Aug 2009 Aug 2009

slide-7
SLIDE 7

MOE asked that the first project be in the high schools, MOE asked that the first project be in the high schools, grade 7 to 11 grade 7 to 11

  • To utilize current state

To utilize current state-

  • of
  • f-
  • the

the-

  • art ICTs

art ICTs to to

  • Improve the quality of education

Improve the quality of education

  • Enhance the learning experience

Enhance the learning experience

  • Improve the level of passes in the CXC CSEC

Improve the level of passes in the CXC CSEC exam exam

slide-8
SLIDE 8
  • 180 institutions

166 Public High Scchools 6 Public Special

  • 6 Public Special

Scools 8 Colleges that train teachers for the High Schools

slide-9
SLIDE 9
slide-10
SLIDE 10
  • 11 subjects

11 subjects – 1 1st

st 5 in pilot

5 in pilot

  • English

English

  • Mathematics

Mathematics

  • Biology

Biology

  • Chemistry

Chemistry

  • Chemistry

Chemistry

  • Information Technology

Information Technology

  • Physics

Physics

  • Geography

Geography

  • Building technology

Building technology

  • Integrated Science

Integrated Science

  • Spanish

Spanish

  • Social Studies

Social Studies

slide-11
SLIDE 11

Instructional Materials Technology Infrastructure

  • !!

!!

  • Teacher Training

Continuous Assessment Remedial

slide-12
SLIDE 12

"#$ "#$% % & & & &

Acquisition / Acquisition / Development of a Development of a comprehensive set comprehensive set

  • f standard ICT
  • f standard ICT-
  • Teachers

Teachers Instructional Instructional Materials (TIMs) Materials (TIMs) Student’s Student’s Instructiona Instructiona l Materials l Materials (SIMs) (SIMs) Video Video-

  • taped

taped Lecture Lecture Series ( for Series ( for ‘challenging’ ‘challenging’

  • f standard ICT
  • f standard ICT-
  • based

based instructional instructional materials for materials for teachers and teachers and students in 11 students in 11 subject areas subject areas l Materials l Materials (SIMs) (SIMs) Interactive Interactive Educational Educational Software Software Item Bank Item Bank ‘challenging’ ‘challenging’ topics topics) )

slide-13
SLIDE 13

"# "#% % '&() '&() (*+*,# (*+*,#

Provision of ICT Provision of ICT equipment and related equipment and related software to Schools and software to Schools and Colleges Colleges Establishment of a Central Establishment of a Central Repository for Educational Repository for Educational Materials (CREM) at MOE Materials (CREM) at MOE to store, reproduce, to store, reproduce, continuously update, and continuously update, and distribute materials distribute materials

  • distribute materials

distribute materials Upgrade of the EMIS at Upgrade of the EMIS at the MOE to enhance the MOE to enhance management and management and administrative administrative capability capability Broad Band Internet Broad Band Internet Access (to be provided Access (to be provided by by UAF UAF) )

slide-14
SLIDE 14

"#- "#-% % '( '(

Training of Training of all school all school ICT skills ICT skills (NCTVET NVQJ (NCTVET NVQJ standards) standards) Integration Integration Training of 2 Training of 2 Systems Systems Administrators Administrators from each from each institution institution Training of 2 Training of 2 Trainers from Trainers from each institution each institution for both ICT for both ICT skills and skills and Technology Technology Integration Integration

  • all school

all school teachers and teachers and College tutors College tutors Utilization Utilization

  • f the new
  • f the new

instruction instruction al materials al materials Integration Integration into the into the teaching teaching /learning /learning process process (ISTE (ISTE standards) standards) Integration Integration Training of 2 Lecturers from each Training of 2 Lecturers from each College to Masters degree level in College to Masters degree level in Technology in Technology in Education Education

slide-15
SLIDE 15

"#. "#.% % #/& #/& Collaborating with existing Collaborating with existing remedial interventions remedial interventions providing ICT providing ICT-

  • based materials

based materials and equipment and training of and equipment and training of tutors and support personnel tutors and support personnel

  • Special equipment and

Special equipment and software for Special software for Special Schools Schools tutors and support personnel tutors and support personnel

slide-16
SLIDE 16

"#0 "#0% % +# +#

Introduction of standard Introduction of standard examinations across the examinations across the

  • examinations across the

examinations across the system at grades 7, 8 & 9 system at grades 7, 8 & 9

(Grade 11 CSEC and Grade 10 CCSC (Grade 11 CSEC and Grade 10 CCSC already in already in place place)

)

slide-17
SLIDE 17
  • Time frame
  • 1-year pilot September 2006 – August 2007
  • Purpose
  • To test procedures and methodologies, identify bet

practices and support systems

'&

  • Inform roll-out
  • Scope (decided by MOE)
  • 5 subjects (English, Maths, Biology, Chemistry, IT)
  • Grades 10 & 11
  • 28 high schools
  • 3 teachers colleges (that train 80% of the teachers in the high

schools)

slide-18
SLIDE 18

Technology Deployment Strategy

Impact Required

Teacher Planning and

Organization Capability/Research Capability

Subject Matter Delivery to

include student interaction,

Deployment Strategy

Remedial type lab (approx 25

computers

Group type lab (10 desktops or

laptops)

Computers for library, resource

include student interaction, group work, individual work

Student Assessment /

Immediate feedback

Student Self-help School Administration Individual interactive learning -

Remedial

Computers for library, resource

room

Computers for staff room (desk

tops/laptops)

Network connectivity and

presentation bundles for grades 10 & 11

Interactive white boards in

group lab and AV room

slide-19
SLIDE 19

Promoting Buy-in/Ownership Ensuring adequate management and control of

#&# (

  • Ensuring adequate management and control of

implementation processes

Handholding / Reinforcement Ensuring Sustainability Smooth/effective Handover

slide-20
SLIDE 20

Instruction Improvement Alternate learning Learning

#&#(

  • Quality Instructional

Materials

CREM Tech Infrastructure/ Tools

Remedial

Tech Infrastructure/ Tools

Skills

ICT & Integration Training

Learning Mgt Tools

CREM/Portal

slide-21
SLIDE 21

Sustainability

#&#(

  • Buy-in

Promotion & Planning support

Implementation Management

Quality Assurance, reinforcement, help dsek

Longer term support

Sys Adm training & CREM Teachers College intervention Equip. Maintenance and replacement Strategy as well as Funding Recommendations

slide-22
SLIDE 22
  • Pilot phase delayed by 1 year to August 2008

Pilot phase delayed by 1 year to August 2008

  • RFP for network and equipment published June 2006,

RFP for network and equipment published June 2006, protest from unsuccessful bidder delayed the signing protest from unsuccessful bidder delayed the signing

  • f the contracts to May and July 2007, resp.
  • f the contracts to May and July 2007, resp.

'&&( '&&( 1/ 1/

  • f the contracts to May and July 2007, resp.
  • f the contracts to May and July 2007, resp.
  • No Board between September 2007 to January 2008

No Board between September 2007 to January 2008

  • Rollout affected by unavailability of funds in MOE

Rollout affected by unavailability of funds in MOE 2007 2007-

  • 8 budget to fund building infrastructure in

8 budget to fund building infrastructure in remaining 150 schools remaining 150 schools

slide-23
SLIDE 23
  • Early 2008, fast track strategies implemented

Early 2008, fast track strategies implemented including: including:

  • Provision of Audiovisuals to all schools ASAP (not only pilot,

Provision of Audiovisuals to all schools ASAP (not only pilot, since do not require infrastructure) since do not require infrastructure)

((( (((

since do not require infrastructure) since do not require infrastructure)

  • Sourced off

Sourced off-

  • the

the-

  • shelf materials since development timeline

shelf materials since development timeline would be protracted would be protracted

  • Encouraged schools to self

Encouraged schools to self-

  • finance building infrastructure

finance building infrastructure

  • Negotiated with Contractors to increase rate of deployment

Negotiated with Contractors to increase rate of deployment

  • MOE assigned 2 Building Officers directly to project

MOE assigned 2 Building Officers directly to project

  • Project extended to March 2011, new timeline

Project extended to March 2011, new timeline developed for all components developed for all components

slide-24
SLIDE 24
  • In mid 2009, MOE requested inclusion of 16

In mid 2009, MOE requested inclusion of 16 independent high schools whom assist in independent high schools whom assist in placement of students from GSAT and GNA placement of students from GSAT and GNA

  • In April 2010, budget halved by MOFP, project had

In April 2010, budget halved by MOFP, project had

'2(*'&&(3 '2(*'&&(3 $ $

  • In April 2010, budget halved by MOFP, project had

In April 2010, budget halved by MOFP, project had to be extended to March 2012 to be extended to March 2012

  • Decision taken to defer all items for which the

Decision taken to defer all items for which the supplier was not yet contracted to 2011 supplier was not yet contracted to 2011-

  • 12, affecting

12, affecting

  • mobile white boards

mobile white boards

  • equipment and networks for 4 remaining high schools

equipment and networks for 4 remaining high schools and 16 additional independent high schools, and 16 additional independent high schools,

  • content development for next 6 subjects

content development for next 6 subjects

slide-25
SLIDE 25

Re Instructional Materials Re Instructional Materials

  • TIMs and SIMs sourced for English,

TIMs and SIMs sourced for English, Maths Maths, , Biology, Information technology, Building Biology, Information technology, Building Technology and Physics, licenses purchased and Technology and Physics, licenses purchased and

+'#/ +'#/

Technology and Physics, licenses purchased and Technology and Physics, licenses purchased and materials delivered to all relevant schools, materials delivered to all relevant schools,

  • Spanish delivered to pilot schools only

Spanish delivered to pilot schools only -

  • to be

to be evaluated for roll evaluated for roll-

  • out,
  • ut,
  • Geography and Integrated Science to be trialed

Geography and Integrated Science to be trialed in selected schools, nothing found for Social in selected schools, nothing found for Social Studies Studies

slide-26
SLIDE 26
  • Govt.

Govt.-

  • owned materials developed, delivered to
  • wned materials developed, delivered to

schools and available on e schools and available on e-

  • Ljam

Ljam website website

  • TIMS and SIMs for English, Biology and Chemistry

TIMS and SIMs for English, Biology and Chemistry developed by UWI (JBTE) and developed by UWI (JBTE) and Maths Maths developed by developed by UTECH/U. of Plymouth UTECH/U. of Plymouth

+//&+'#/ +//&+'#/

UTECH/U. of Plymouth UTECH/U. of Plymouth

  • Video lectures for 1

Video lectures for 1st

st 5 subjects developed by ZED

5 subjects developed by ZED and CPTC, broadcast on PBCJ, and CPTC, broadcast on PBCJ, Contracts signed and Contracts signed and production in progress for remaining 6 subjects production in progress for remaining 6 subjects

  • Over

Over 11500 Items written and reviewed by teachers, Items written and reviewed by teachers, placed in a placed in a Moodle Moodle database on e database on e-

  • Ljam

Ljam website, website, used by students to study for exams (since 2009) used by students to study for exams (since 2009)

slide-27
SLIDE 27

Re Technology Infrastructure Re Technology Infrastructure

  • Audiovisuals delivered to 185 institutions ,

Audiovisuals delivered to 185 institutions , including the 5 Community Colleges including the 5 Community Colleges

+//&+'#/ +//&+'#/

  • Computer networks in 180 institutions

Computer networks in 180 institutions

  • Grade 10&11 Classrooms

Grade 10&11 Classrooms

  • Library

Library

  • Resource Room

Resource Room

  • Staff rooms

Staff rooms

  • Computer Laboratories

Computer Laboratories

slide-28
SLIDE 28

Re CREM Re CREM

  • Decision re CREM hosting taken by MOE Nov

Decision re CREM hosting taken by MOE Nov 2009, equipment and network delivered since July 2009, equipment and network delivered since July 2010, and training of technical staff completed 2010, and training of technical staff completed (Supplier (Supplier – Dell World Trade) Dell World Trade)

+//&+'#/ +//&+'#/

(Supplier (Supplier – Dell World Trade) Dell World Trade)

  • CREM Coordinator identified early 2011, and

CREM Coordinator identified early 2011, and discussions commenced re establishment of unit discussions commenced re establishment of unit for managing the materials development, update for managing the materials development, update and dissemination/access, and providing 24/7 and dissemination/access, and providing 24/7 support support

slide-29
SLIDE 29

Re Training Re Training

  • Basic ICT skills

Basic ICT skills

  • Over

Over 11,000 11,000 teachers, lecturers and Education Field Officers teachers, lecturers and Education Field Officers nearly 8,000 certified nearly 8,000 certified

  • 454 systems administrators

454 systems administrators

  • Nearly 200 Trainer of trainers

Nearly 200 Trainer of trainers

  • Online application developed

Online application developed

+//&+'#, +//&+'#,

  • Re Technology Integration

Re Technology Integration

  • 3,988 teachers, lecturers and education officers

3,988 teachers, lecturers and education officers

  • Online Application developed

Online Application developed

  • Re Masters degrees in Technology in Education

Re Masters degrees in Technology in Education

  • 15 lecturers granted scholarships British Columbia University,

15 lecturers granted scholarships British Columbia University, J$1mil each J$1mil each

  • 8 graduated in November 2010

8 graduated in November 2010

  • now the Instructional Technology Lecturer at the College,

now the Instructional Technology Lecturer at the College, bonded for 3 years bonded for 3 years

slide-30
SLIDE 30

Re Continuous Assessment Re Continuous Assessment

  • Grade 9 Diagnostic test

Grade 9 Diagnostic test

  • Pilot in 28 schools in 2009 in English,

Pilot in 28 schools in 2009 in English, Maths Maths

  • rolled out to 150 schools in June 2010, adding Integrated Science,

rolled out to 150 schools in June 2010, adding Integrated Science,

  • marked centrally at e

marked centrally at e-

  • Ljam

Ljam using Multiple Choice Marking Software using Multiple Choice Marking Software (Exam View), uses scanners provided by the project (Exam View), uses scanners provided by the project -

  • results

results compiled by July 2010 compiled by July 2010

  • administered in 173 schools in June 2011, adding Social Studies,

administered in 173 schools in June 2011, adding Social Studies, being marked by schools who have been trained in Exam view being marked by schools who have been trained in Exam view

+//&+'#, +//&+'#,

  • administered in 173 schools in June 2011, adding Social Studies,

administered in 173 schools in June 2011, adding Social Studies,

  • being marked by schools who have been trained in Exam view

being marked by schools who have been trained in Exam view

  • Grade 7 tests administered in June 2011

Grade 7 tests administered in June 2011

  • Results started coming in 1 week after test administered

Results started coming in 1 week after test administered

  • Analysis and reporting done at e

Analysis and reporting done at e-

  • Ljam

Ljam under the supervision of under the supervision of the CXC Consultant the CXC Consultant

slide-31
SLIDE 31

Re Remedial Component Re Remedial Component

  • Technology Enrichment programme designed for

Technology Enrichment programme designed for 30 low 30 low-

  • performing schools,

performing schools,

  • Selection based on poor performance in English and

Selection based on poor performance in English and +//&+'#, +//&+'#,

  • Selection based on poor performance in English and

Selection based on poor performance in English and Maths Maths, by students entering from GSAT as well as in the , by students entering from GSAT as well as in the CXC and the Grade 9 diagnostic tests CXC and the Grade 9 diagnostic tests

  • Institution of a Volunteer Programme to assist the

Institution of a Volunteer Programme to assist the teachers of these subjects at the grade 7 & 8 levels teachers of these subjects at the grade 7 & 8 levels

  • Provision of Integrated Learning Software in English

Provision of Integrated Learning Software in English and and Maths Maths, as well as other resources , as well as other resources

slide-32
SLIDE 32

Re Remedial Component Continued Re Remedial Component Continued

  • Grade 7 diagnostic tests in English and

Grade 7 diagnostic tests in English and Maths Maths, , pre and post tests pre and post tests

  • Technology Planning Workshops

Technology Planning Workshops

+//&+'#, +//&+'#,

  • Technology Planning Workshops

Technology Planning Workshops

  • Closer monitoring and support

Closer monitoring and support – increased visits increased visits and cluster meetings and cluster meetings

  • Reinforcement teacher training

Reinforcement teacher training

  • More frequent reporting

More frequent reporting

slide-33
SLIDE 33

Re Remedial Component Continued Re Remedial Component Continued

  • Involvement of Parents, Community, School

Involvement of Parents, Community, School Board Board

  • Ensuring that the intervention interfaces

Ensuring that the intervention interfaces

+//&+'#, +//&+'#,

  • Ensuring that the intervention interfaces

Ensuring that the intervention interfaces seamlessly with the school’s remedial seamlessly with the school’s remedial programme and the MOE’s Grade Seven programme and the MOE’s Grade Seven Intervention Programme (GPIS) Intervention Programme (GPIS)

  • Volunteer Operation and Training Manuals

Volunteer Operation and Training Manuals developed, and volunteers identified, and developed, and volunteers identified, and training commenced training commenced

slide-34
SLIDE 34
slide-35
SLIDE 35
  • Exciting Text

Exciting Text

  • CD

CD-

  • ROMs

ROMs

  • Video

Video-

  • taped lectures

taped lectures Database resources Database resources

  • CD

CD-

  • ROMs

ROMs

  • DVDs

DVDs

  • Power Point

Power Point Presentations Presentations Video Video-

  • taped lectures

taped lectures

  • Database resources

Database resources

  • Interactive Software

Interactive Software

  • Item Bank

Item Bank

  • Web

Web-

  • based resources

based resources

slide-36
SLIDE 36

EXAMPLE OF CONTENT RESOURCE PROVIDED PROVIDED

slide-37
SLIDE 37
  • Desk

Desk tops tops

  • Lap

Lap-

  • tops

tops

  • Multimedia Projectors &

Multimedia Projectors &

  • Digital Video Cameras

Digital Video Cameras

  • DVD/CD Players

DVD/CD Players

  • Scanners

Scanners

4# 4#

  • Multimedia Projectors &

Multimedia Projectors & Screens Screens

  • Interactive White

Interactive White Boards Boards

  • Document Cameras

Document Cameras

  • Scanners

Scanners

  • Televisions

Televisions

  • Network connectivity

Network connectivity

slide-38
SLIDE 38

ICT’s in use in project schools

slide-39
SLIDE 39
  • Teachers and lecturers trained

Teachers and lecturers trained

  • to levels 1 and 2 in ICT skills (NVTVET)

to levels 1 and 2 in ICT skills (NVTVET)

  • in Technology Integration (ISTE)

in Technology Integration (ISTE) – how to use the how to use the technology in instructional delivery technology in instructional delivery

General Characteristics of Technology Tools and their Uses

/2# /2#

General Characteristics of Technology Tools and their Uses Digital Devices Using the Internet for Research and Teaching Creating 2D and 3D Animations Using Internet Communication Tools Digital Stories Web Quests and Treasure Hunts Wikis Blogs Podcasts RSS Feeds

slide-40
SLIDE 40
  • Trainer of trainers for both aspects

Trainer of trainers for both aspects

  • System Administrators trained to manage and maintain

System Administrators trained to manage and maintain the integrity of the network, at least 2 per school the integrity of the network, at least 2 per school

  • System Administration introduction

System Administration introduction

  • Dell Equipment Orientation

Dell Equipment Orientation

/2# /2#

  • Dell Equipment Orientation

Dell Equipment Orientation

  • Network and Server Administration including

Network and Server Administration including Microsoft Server and Active directory Microsoft Server and Active directory

  • School Network build out and Virus Management

School Network build out and Virus Management

  • Advanced Microsoft System utilities

Advanced Microsoft System utilities

  • Advanced Systems Problem Solving

Advanced Systems Problem Solving

  • Web resources and Forum

Web resources and Forum

  • Masters level trained Instructional Technology Lecturers

Masters level trained Instructional Technology Lecturers in the Colleges in the Colleges

slide-41
SLIDE 41

/2# /2#

slide-42
SLIDE 42
  • Virtual Assets that have IP value

Virtual Assets that have IP value

  • Ideas

Ideas

  • Designs

Designs

  • Images

Images

&&&) &&&)

  • Images

Images

  • Instructional Materials

Instructional Materials

  • Lessons

Lessons

  • Vignettes

Vignettes

  • Stories

Stories

  • Theses

Theses

  • Power

Power-

  • points

points

slide-43
SLIDE 43

&&&) &&&)

slide-44
SLIDE 44

Average investment per high school/teachers Average investment per high school/teachers college college

  • Equipment and Networks and related training

Equipment and Networks and related training

# #

  • Equipment and Networks and related training

Equipment and Networks and related training US$142,000 US$142,000

  • Materials and related training

Materials and related training US$9000 US$9000

  • Training (HEART and Mico)

Training (HEART and Mico) US$25,000 US$25,000 Additional Additional US$11,635 per person US$11,635 per person for Masters training for Masters training (15 lecturers) (15 lecturers)

slide-45
SLIDE 45
  • To provide equipment to remaining 4 high schools and

To provide equipment to remaining 4 high schools and additional 16 independent high schools and special additional 16 independent high schools and special equipment to special schools, equipment to special schools,

  • To provide whiteboards and mobile labs to all schools

To provide whiteboards and mobile labs to all schools (5 '$ (5 '$

  • To provide whiteboards and mobile labs to all schools

To provide whiteboards and mobile labs to all schools

  • To complete establishment of the CREM (MOU for

To complete establishment of the CREM (MOU for Broadband signed in May 2011) Broadband signed in May 2011)

slide-46
SLIDE 46
  • To complete training and certification of teachers and

To complete training and certification of teachers and lecturers, using the online application developed for the lecturers, using the online application developed for the project project (5 '$ (5 '$

  • To implement the technology enrichment programme to

To implement the technology enrichment programme to assist the selected schools in improving literacy and assist the selected schools in improving literacy and numeracy numeracy

slide-47
SLIDE 47
  • To roll

To roll-

  • out Chemistry materials to remaining 150 schools
  • ut Chemistry materials to remaining 150 schools
  • To complete sourcing and development of materials for

To complete sourcing and development of materials for additional 6 subjects additional 6 subjects (5 '$ (5 '$

  • To acquire/develop materials for grade 7

To acquire/develop materials for grade 7-

  • 9

9

  • To increase the Item bank for grades 10&11 to 22,000, 2000

To increase the Item bank for grades 10&11 to 22,000, 2000 for each subject, and for grades 7 for each subject, and for grades 7-

  • 9 to

9 to 5,000 5,000, , 1000 for each 1000 for each subject subject

  • To trial various educational software in selected schools

To trial various educational software in selected schools (literacy, numeracy, CAD) (literacy, numeracy, CAD)

slide-48
SLIDE 48
  • To handover elements of the project to MOE for

To handover elements of the project to MOE for institutionalization institutionalization

  • To develop Project #2 for Primary Schools

To develop Project #2 for Primary Schools (5 '$ (5 '$

  • To work with the schools to ensure proper Implementation

To work with the schools to ensure proper Implementation and Resource Management strategies that seek to direct and Resource Management strategies that seek to direct and control the use of resources to produce the best value and control the use of resources to produce the best value from the investment and to ensure sustainability of the from the investment and to ensure sustainability of the project interventions project interventions

slide-49
SLIDE 49
  • School Inventory and Knowledge database being

School Inventory and Knowledge database being maintained, periodic audits conducted maintained, periodic audits conducted Support provided through website, telephone, e Support provided through website, telephone, e-

  • 6 !+!*7+!+869

6 !+!*7+!+869 +: +:

  • Support provided through website, telephone, e

Support provided through website, telephone, e-

  • mail, Chat, Blogs, field visits

mail, Chat, Blogs, field visits

  • Service level agreement in place for all equipment

Service level agreement in place for all equipment

  • Technical and operational guidelines / standards

Technical and operational guidelines / standards /best practices provided /best practices provided

slide-50
SLIDE 50

7 +!+: !+: 7 +!+: !+:

slide-51
SLIDE 51
  • Infrastructure Project Manager to assist schools in

Infrastructure Project Manager to assist schools in identifying contractors and liaise between e identifying contractors and liaise between e-

  • Ljam

Ljam and the and the MOE Building Officers MOE Building Officers

  • Framework contract with suppliers to supply goods over

Framework contract with suppliers to supply goods over

6 !+!*7+!+869 6 !+!*7+!+869 +: +:

  • Framework contract with suppliers to supply goods over

Framework contract with suppliers to supply goods over period of time and give latest technology period of time and give latest technology

  • Electrical Consultant to sign

Electrical Consultant to sign-

  • off on building works and
  • ff on building works and

electrical circuitry (paid for by MOE) electrical circuitry (paid for by MOE)

  • Distinctive marking on equipment

Distinctive marking on equipment – logo on BIOS logo on BIOS

  • Training of System Administrators to ensure integrity of the

Training of System Administrators to ensure integrity of the school network school network

slide-52
SLIDE 52
  • Subject Specialists hired to manage the acquisition

Subject Specialists hired to manage the acquisition and development of content and development of content

  • Subject Advisory Groups, led by MOE Officer,

Subject Advisory Groups, led by MOE Officer, established to sign off on standards and ensure established to sign off on standards and ensure quality of materials developed/acquired quality of materials developed/acquired

6 !+!*7+!+869 6 !+!*7+!+869 +: +:

established to sign off on standards and ensure established to sign off on standards and ensure quality of materials developed/acquired quality of materials developed/acquired

  • Cluster workshops on materials provided to ensure

Cluster workshops on materials provided to ensure appropriate and effective usage appropriate and effective usage

  • Teachers Colleges being equipped to ensure on

Teachers Colleges being equipped to ensure on-

  • going professional development of teachers, both

going professional development of teachers, both pre pre-

  • service and in

service and in-

  • service

service

slide-53
SLIDE 53
  • School e

School e-

  • Learning Implementation Committee

Learning Implementation Committee (SEIMC), comprising heads of departments , (SEIMC), comprising heads of departments , established to be responsible for the Steering/ established to be responsible for the Steering/ Monitoring of the implementation of the project Monitoring of the implementation of the project in the school in the school

6 !+!*7+!+869 6 !+!*7+!+869 +: +:

in the school in the school

  • Officers hired to monitor the implementation of

Officers hired to monitor the implementation of the projects in the schools, includes regular visits the projects in the schools, includes regular visits and SEIMC cluster meetings for reinforcement and SEIMC cluster meetings for reinforcement /sharing / problem solving /monitoring, regular /sharing / problem solving /monitoring, regular reporting reporting

  • MOE Officers part of the monitoring process

MOE Officers part of the monitoring process

slide-54
SLIDE 54
  • Brokering adequate insurance coverage for the schools to

Brokering adequate insurance coverage for the schools to participate if desired participate if desired

  • Lobbying for posts of Systems Administrator and

Lobbying for posts of Systems Administrator and

6 !+!*7+!+869 6 !+!*7+!+869 +: +:

  • Lobbying for posts of Systems Administrator and

Lobbying for posts of Systems Administrator and Instructional Technology Lecturer to be added to Instructional Technology Lecturer to be added to school/college establishment school/college establishment

  • Locks being installed to safeguard computers at the schools

Locks being installed to safeguard computers at the schools (incidence of theft reported thirty (30) schools, valued at (incidence of theft reported thirty (30) schools, valued at US $115,289.40) US $115,289.40)

slide-55
SLIDE 55
  • Looking at a workable maintenance strategy,

Looking at a workable maintenance strategy, eg eg use of the use of the HEART Trust and Community College HEART Trust and Community College network to provide network to provide maintenance maintenance services as indicated in MOE draft ICT services as indicated in MOE draft ICT Strategic Plan Strategic Plan

6 !+!*7+!+869 6 !+!*7+!+869 +: +:

  • Support in planning for technology sustainability

Support in planning for technology sustainability

  • Fully automated help desk system

Fully automated help desk system

slide-56
SLIDE 56

The Network THE e-LEARNING PROJECT

A Joint MITEC/MOEY Project

slide-57
SLIDE 57

Will revolutionize every aspect of the school system

teaching, learning,

#/)#

learning, administration

slide-58
SLIDE 58
  • Teachers

Teachers

  • Greater proficiency in the use of

Greater proficiency in the use of ICTs ICTs by lecturers in the by lecturers in the teachers colleges and high school teachers teachers colleges and high school teachers

  • lesson planning,

lesson planning,

  • lesson delivery,

lesson delivery,

  • student evaluation,

student evaluation,

  • marking,

marking, reporting, reporting,

#/)#

  • reporting,

reporting,

  • video presentations,

video presentations,

  • communication,

communication,

  • research,

research,

  • networking,

networking,

  • accessing web

accessing web-

  • resources, etc

resources, etc

  • Inexperienced teachers will have a pool of standard high

Inexperienced teachers will have a pool of standard high-

  • quality materials to draw from

quality materials to draw from

slide-59
SLIDE 59
  • Teachers

Teachers

  • Better alignment between teacher communication

Better alignment between teacher communication methods and student interactive trends, methods and student interactive trends, eg eg

  • Use of

Use of Webquest Webquest to stimulate inquiry to stimulate inquiry-

  • based learning

based learning

  • Use of interactive whiteboards to stimulate interactivity

Use of interactive whiteboards to stimulate interactivity Use of video Use of video-

  • cameras to stimulate creativity and

cameras to stimulate creativity and #/)#

  • Use of video

Use of video-

  • cameras to stimulate creativity and

cameras to stimulate creativity and innovation innovation

  • Difficult concepts can be dealt with more easily and more

Difficult concepts can be dealt with more easily and more excitingly excitingly

  • Content can be accessed to specifically deal with

Content can be accessed to specifically deal with weaknesses identified from the Diagnostic tests weaknesses identified from the Diagnostic tests

slide-60
SLIDE 60
  • Learners

Learners

  • Quest for knowledge encouraged

Quest for knowledge encouraged

  • Increased interest in education

Increased interest in education

  • Teaching/learning process more exciting, especially for

Teaching/learning process more exciting, especially for students who learn ‘differently’ or are disabled students who learn ‘differently’ or are disabled #/)# students who learn ‘differently’ or are disabled students who learn ‘differently’ or are disabled

  • Improved attendance at school

Improved attendance at school

  • Increased participation of parents thru Cable TV,

Increased participation of parents thru Cable TV, broadcasts, Internet broadcasts, Internet

  • Contribution to improvement in passes at the school

Contribution to improvement in passes at the school-

  • leaving CXC CSEC examinations

leaving CXC CSEC examinations

  • School

School-

  • leavers more equipped for the 21

leavers more equipped for the 21st

st century work

century work – ICT skills, research skills, problem ICT skills, research skills, problem-

  • solving/decision

solving/decision-

  • making skills

making skills

slide-61
SLIDE 61

USING THE INTERACTIVE WHITEBOARD USING THE INTERACTIVE WHITEBOARD

slide-62
SLIDE 62
  • Administration

Administration

  • Modernisation of school development planning

Modernisation of school development planning #/)#

  • Greater efficiency in school operation

Greater efficiency in school operation

  • Improved decision

Improved decision-

  • making since now data

making since now data-

  • driven

driven

  • Increased and more efficient communication with

Increased and more efficient communication with stakeholders stakeholders

slide-63
SLIDE 63
  • Improvement in the quality of education between Grades 7

Improvement in the quality of education between Grades 7-

  • 11

11 (Forms 1 (Forms 1-

  • 5) in 188 high schools island

5) in 188 high schools island-

  • wide

wide

  • School

School-

  • leavers better suited to the 21st century world of work

leavers better suited to the 21st century world of work

  • Creation of local expertise in development of digital material and

Creation of local expertise in development of digital material and

# ##)*!& ,&#

  • Creation of local expertise in development of digital material and

Creation of local expertise in development of digital material and

  • ther technology
  • ther technology-
  • driven industries, with the possibility of

driven industries, with the possibility of exporting these services exporting these services

  • Greater appetite for internet and data

Greater appetite for internet and data-

  • driven services

driven services

  • Increased demand for affordable computers for teachers and

Increased demand for affordable computers for teachers and students students

  • Project can be used as case study for project implementation

Project can be used as case study for project implementation nationally and regionally nationally and regionally

slide-64
SLIDE 64

DISCUSSION

slide-65
SLIDE 65

THANK YOU

Avrill Crawford Avrill Crawford CEO/Project Manager e-Learning Jamaica Company Limited 36 Trafalgar Road, Kingston 10, Jamaica Tel: 876-929-4044, Fax: 876-929-8676 E-mail: info@e-ljam.net Website: www.e-ljam.net.jm