Pontiac Tr and 7 Mile Rd Virtual Public Information Meeting May 20, 2020 @Washtenawroads Agenda I. Housekeeping II. Presentation III. Q and A Todays Presenter Mark McCulloch Senior Project Manager - Permits (734) 327-6679


slide-1
SLIDE 1

@Washtenawroads

Pontiac Tr and 7 Mile Rd

Virtual Public Information Meeting May 20, 2020

slide-2
SLIDE 2

I. Housekeeping

  • II. Presentation
  • III. Q and A

Agenda

slide-3
SLIDE 3
  • Mark McCulloch

– Senior Project Manager - Permits – (734) 327-6679 – mccullochm@wcroads.org

Today’s Presenter

slide-4
SLIDE 4
  • Meeting audio and video is being recorded

and will be posted to wcroads.org

  • You will be asked to virtually “raise your

hand” during Q and A

  • Chat is enabled

Housekeeping

slide-5
SLIDE 5

Pontiac Trail @ 7 Mile Road Roundabout

slide-6
SLIDE 6
  • Road construction has been deemed

“essential” by state and federal officials

  • Precautions will be taken to protect

employee safety

  • Please do not approach employees

Construction During COVID-19

slide-7
SLIDE 7
  • 2014 roundabout project

– ROW issues – Grant money returned

  • 2020 project using federal aid (rural funds)

– 80/20 match – $880,000 bid (Cadillac Asphalt)

Background

slide-8
SLIDE 8
  • Roundabouts slow down traffic and reduce

the severity of crashes

  • Roundabouts move traffic more efficiently

and reduce congestion

  • Reduces impacts to neighboring parcels

Why a Roundabout?

slide-9
SLIDE 9
  • Safety
  • Congestion mitigation
  • New pavement

Benefits

slide-10
SLIDE 10
  • Spring 2020; utilities being relocated
  • In summer 2020, we will…

– Install single-lane roundabout – Construct curb and gutter – Install enclosed storm sewer – Build crosswalk for east leg crossing – Install street lighting at intersection

Project Overview

slide-11
SLIDE 11

Design

Pontiac Trail

slide-12
SLIDE 12

Pulverize (Crush) Current Roadway

slide-13
SLIDE 13

Prepare for Curb

slide-14
SLIDE 14

Install Curb and Splitter Islands

slide-15
SLIDE 15

Install Central Island

slide-16
SLIDE 16

Paving

slide-17
SLIDE 17

Pavement Markings

slide-18
SLIDE 18
  • Starting in June
  • Plan to be completed by middle of August
  • Contractor will work…

– Monday – Saturday, 7 a.m. – 7 p.m.

Timeline

slide-19
SLIDE 19
  • Except for access to the Corner General

Store, the intersection will be closed to all traffic for approximately 8 weeks

– Property access to be provided by the east leg of the intersection.

Impact to Traffic

slide-20
SLIDE 20
  • 6 Mile Rd to

Dixboro Rd to 8 Mile Rd

  • Dixboro Rd to

6 Mile Rd to Angle Rd

Detour

slide-21
SLIDE 21
  • Mail delivery
  • Trash pickup
  • Interaction as a pedestrian
  • Yard restoration

Construction Details

slide-22
SLIDE 22

Roundabout Reminders...

  • Slow down on approach
  • Look to your left
  • When no traffic is present

proceed slowly

  • When traffic is present YIELD
slide-23
SLIDE 23
  • Visit project page @ wcroads.org

– Subscribe to receive project update emails

  • Contact Project Manager

– Mark McCulloch, (734) 327-6679, mccullochm@wcroads.org

Find Out More

slide-24
SLIDE 24

Q AND A

slide-25
SLIDE 25
  • On your computer or smart phone:

– Join audio then click “participants” at the bottom of screen and select “raise hand”

  • On your touchtone phone: Dial *9

To Ask a Question

slide-26
SLIDE 26
  • Visit project page @ wcroads.org

– Subscribe to receive project update emails

  • Contact Project Manager

– Mark McCulloch, (734) 327-6679, mccullochm@wcroads.org

Find Out More