OUTLINE Neighborhood Complete Streets program background What is a - PowerPoint PPT Presentation

OUTLINE Neighborhood Complete Streets program background What is a Complete Street? S Irving St project identification & existing conditions Proposed project concept Public Engagement Neighborhood Context Q


  1. OUTLINE ▪ Neighborhood Complete Streets program background ▪ What is a “Complete Street”? ▪ S Irving St project identification & existing conditions ▪ Proposed project concept ▪ Public Engagement ▪ Neighborhood Context ▪ Q & A with Development Services & APS

  2. WHAT IS A COMPLETE STREET? ▪ Complete Streets are streets designed and operated to allow safe and comfortable use by all users. ▪ People walking, biking, riding transit and driving are all accommodated in the available infrastructure, and the street design is compatible with the surrounding land uses. ▪ County policy since 2007 Master Transportation Plan (MTP) ▪ Streets are public spaces for all people , not for private vehicles alone

  3. PROJECT SELECTION & FEATURES Highly ranked Location: ▪ Incomplete sidewalk ▪ History of Crashes ▪ Volume (1,041 Average Daily Traffic) ▪ Proximity to schools, adjacent bicycle facilities & transit Full rankings with explanation: https://projects.arlingtonva.us/programs/neighborhood- complete-streets/ncs-potential-project-list/

  4. S IRVING ST EXISTING CONDITIONS ▪ No complete sidewalk on either side of the street, ▪ small section of sidewalk on the east side in front of two properties ▪ on-street parking allowed on both sides of the street

  5. PROJECT GOALS: ▪ Safety for all users, with care taken for pedestrian experience ▪ Reduce/eliminate crashes ▪ Least impact to parking and property ▪ Engage with neighbors, community stakeholders, NCSC at INVOLVE levels ▪ Meet engineering best practices ▪ Consistent with County policy

  6. PUBLIC ENGAGEMENT TIMELINE ▪ Spring 2017 - project nomination ▪ September 2019 – NCSC directed staff to begin public engagement on project ▪ November 12, 2019 – Arlington Heights Civic Association meeting ▪ November 12 – December 8, 2019 – Online feedback form ▪ November 19, 2019 – Block meeting ▪ December 5, 2019 – NCS proposed projects meeting ▪ December 16, 2019 – NCS Funding Hearing ▪ February 2020 – Arlington County Board ▪ Project Webpage: https://projects.arlingtonva.us/projects/south-irving-street-ncs-project/

  7. ACTIVE PROJECTS/INVESTIGATIONS FLEET SouthWa Walt lter er Reed ed Driv ive e Streetsca eetscape pe Impr provemen ovements South Irving ng Street et Neighbor ghborhoo ood Compl plete e Street eet Project ject Career eer Legend: Center er APS New or Expanded Schools Arlington Transportation Projects Arlington Safety Reviews Underway

  8. Michelle Stafford NCS Program Manager mstafford@arlingtonva.us

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.