ORC Power Plant Neustadt - Glewe Operational Experience Since 2004 - - PowerPoint PPT Presentation

orc power plant neustadt glewe operational experience
SMART_READER_LITE
LIVE PREVIEW

ORC Power Plant Neustadt - Glewe Operational Experience Since 2004 - - PowerPoint PPT Presentation

ORC Power Plant Neustadt - Glewe Operational Experience Since 2004 Electricity generation, combined heat and power Strasbourg, September, 15 th - 2006 Thomas Funke Erdwrme Kraft GbR - Berlin Dr. Silke Khler Geoforschungszentrum - Potsdam


slide-1
SLIDE 1

ORC Power Plant Neustadt - Glewe Operational Experience Since 2004

Electricity generation, combined heat and power Strasbourg, September, 15th - 2006

Thomas Funke Erdwärme Kraft GbR - Berlin

  • Dr. Silke Köhler

Geoforschungszentrum - Potsdam

slide-2
SLIDE 2

15.09.2006

2

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

Location of Neustadt - Glewe

Neustadt – Glewe is located in the Northeast of Germany (North German Basin) Land Mecklenburg-Vorpommern The existing heating station is in

  • peration since 1994

Less demand of heat during the summer gives the chance to produce electricity The complete plant is a combination of heat and electricity production - CHP

Neustadt - Glewe

slide-3
SLIDE 3

15.09.2006

3

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

Heating Station since 1994

Two Wells (production & reinjection) ~ 2250 m deep

  • ca. 1400 customers

Installed capacity: 16.4 MWth geothermal part : 6.5 MWth Geothermal supplies 95 % of the total produced heat Very little heat demand during the summer months

slide-4
SLIDE 4

15.09.2006

4

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

Geothermal Power Plant since 2003

First geothermal power plant in Germany Geothermal facility with very low brine temperature (~97° C) for an electric power station Gross capacity of 200 kW

slide-5
SLIDE 5

15.09.2006

5

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

Thermal water (brine) circuit

Overall mass flow rate of brine 110 m³/h, divided in two streams, one for the heating station and one for the power plant The partial flow to the power plant is cooled down in a heat exchanger (evaporator) to a temperature of ~70° C Afterwards the cooled brine is mixed with the main brine stream and is transported to the heating station (500m) For the production of district heating the brine is finally cooled down to ~50° C Production of heat has the priority. Only the heat not needed by the heating station can be used in the power plant.

  • full load during summertime
  • ut of service during wintertime

brine 98° C 110 m³/h power plant gross capacity 200 kWel

T s

heating station 6 MW geothermal

th

11 MW total

th

heat to district heating system net capacity to grid 70° C ~ 50° C

slide-6
SLIDE 6

15.09.2006

6

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

ORC - Process (Organic Rankine Cycle)

Synthetic organic fluid (Perfluoropentane, C5F12) with a boiling point of ~30° C This fluid is preheated and evaporated before the steam expands in the turbine After the turbine the steam is condensed in the condenser. The condenser is fed by cooling water which is cooled down in two cooling towers. To close the cycle the working fluid is pumped back to the boiler and evaporates again like in any other common power plant process.

Turbine Generator Fluid Pump Evaporator Superheater

Production Injection

Condenser / Cooling Tower

slide-7
SLIDE 7

15.09.2006

7

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

Geothermal power plant Neustadt-Glewe

The unit is installed in a 12 m container close to the production well The electric switching station is installed on the same site. It connects the plant to the 20 kV grid. The power plant runs automatically with checks every three days. Starts and unplanned stops were supported manually.

ORC-Container Cooling towers Chemical Water treatment

slide-8
SLIDE 8

15.09.2006

8

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

Technical data ORC - Thermal Heat Power Plant

Electrical output 200 kW (installed) Electrical production 1.400 – 1.600 MWh/a max. theoretical (annual demand of ~ 500 households) ORC-Turbine axial inflow, single stage with three nozzles Turbine efficiency, 70 % Preheater and evaporator made out of titanium Live steam temperature ~ 75 ° C, pressure ~ 4 bar Pressure condenser ca. 1 bar Total efficiency ~ 7.4 % Total investment costs ~ 950,000 €

slide-9
SLIDE 9

15.09.2006

9

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

The Story of Neustadt - Glewe

1. Technical and organizational preparations 2002 – 2003 2. Start up Nov 2003 3. First modifications Mar 2004 4. Start continuous production Aug 2004 5. First winter shut down Nov 2004 – Mar 2005 6. Bearing damage – generator Apr – May 2005 7. Leakage – ORC valves Jun – Aug 2005 8. Damage brine pump Oct – Nov 2005 9. In operation with unsatisfying load since Apr 2006

01.01.2003 01.01.2004 01.01.2005 01.01.2006 100 200 generator capacity (kW) time

1 2 3 4 5 6 7 8 9

slide-10
SLIDE 10

15.09.2006

10

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

Problems to Solve

Since the first start up the plant doesn’t reach the full load Investigations were started – in close cooperation with GFZ Possible reasons are numerous (heat exchange – feed pump – turbine) We expect first results and improvements this autumn Depending on the investment costs we will try to modify some components Less output affects also the economics. The revenues are much smaller than planned Although the price of the produced electricity is government-funded under the so-called Renewable Energies Act the situation is unsatisfying: Only the combined production of heat and electricity will allow successful

  • peration!
slide-11
SLIDE 11

15.09.2006

11

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

Summary

The geothermal power plant of Neustadt – Glewe is an important project to gain experiences under the special geologic conditions of Germany (low temperatures). It supports the next project of GFZ-Potsdam and Vattenfall in Groß Schönebeck. The technique on the surface is not so easy as it might look like although we’ve heard different things yesterday More experiences in low-temperature power plant operation are necessary. With better thermal conditions the efficiency of new projects will increase – but: Without the combination of heat production (CHP process) it would be difficult to operate a power plant for electricity production with success.

slide-12
SLIDE 12

15.09.2006

12

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

Thank you for your attention

slide-13
SLIDE 13

15.09.2006

13

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

Pictures

Valve with damaged rubber lining Pieces of rubber found in turbine

slide-14
SLIDE 14

15.09.2006

14

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

Charts I

Electricitiy Generation (MWh) 2004 - 2006

10 20 30 40 50 60 70 80 90 Jan 04 Apr 04 Jul 04 Okt 04 Jan 05 Apr 05 Jul 05 Okt 05 Jan 06 Apr 06 Jul 06 Okt 06

slide-15
SLIDE 15

15.09.2006

15

Erdwärme Kraft GbR, Hr. Funke GFZ, Dr. Köhler

Electric Output / Brine

0,0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9 1,0 0,0 0,2 0,4 0,6 0,8 1,0 VBrine/VBrine,max PGen/PGen,max 2004 2005 2006

Charts II

Electric generation decreased within the last years