Opportunities for storage National Grid UK and US Electricity and - - PowerPoint PPT Presentation
Opportunities for storage National Grid UK and US Electricity and - - PowerPoint PPT Presentation
Role of System Operator Opportunities for storage National Grid UK and US Electricity and Gas Transmission & Distribution 2 National Grid UK electricity Transmission Owner (England and Wales) System design Project
2
National Grid
UK and US Electricity and Gas Transmission & Distribution
3
National Grid – UK – electricity
Transmission Owner (England and Wales) System design Project management Engineering and maintenance ~7,200km of overhead line; ~675km of underground cable; and 337 substations at 244 sites. System Operator (Great Britain) System Planning System Operation Market Facilitation Energy Trading
- Anglo-French Interconnector (2GW)
- BritNed Interconnector (1GW)
- North & South Irish connection
(1.1GW) + planned new links
2010/2011 GB Demands
15000 20000 25000 30000 35000 40000 45000 50000 55000 60000 30 130 230 330 430 530 630 730 830 930 1030 1130 1230 1330 1430 1530 1630 1730 1830 1930 2030 2130 2230 2330 Time National Grid Demand (MW)
Summer Minimum Typical Summer Typical Winter Winter Maximum
Typical summer and winter GB demand profiles
National Grid Demand (GW) 60 55 50 45 40 35 30 25 20 15
GB Installed Capacity (2103/14)
5
1,467 20,454 31,887 1,122 4,000 9,471 1,123 2,744 3,669 3,368
GB Installed Capacity (2013/14)
Biomass CCS Coal Gas Hydro Interconnector Marine Nuclear Oil Pumped Storage Onshore Wind
GB Installed Capacity (2013/14) Biomass 1,467
1.8%
CCS
0.0%
Coal 20,454
25.8%
Gas 31,887
40.2%
Hydro 1,122
1.4%
Interconnecto 4,000
5.0%
Marine
0.0%
Nuclear 9,471
11.9%
Oil 1,123
1.4%
Pumped Stora 2,744
3.5%
Onshore Win 3,669
4.6%
Offshore Win 3,368
4.2%
Total 79,305
100.0%
Key Market Principles
6
Market Balancing ceases at Gate Closure (rolling 1hr ahead of real time)
Market ceases balancing at Gate Closure (1hr ahead of real time). The System Operator then balances the system (second by second) and is the sole counterparty to any further trades
Imbalance Cashed Out post event
Market participants are incentivised to balance their metered input / output with their contracted position through cashing out their imbalance at a less favourable price
Market Balancing – ‘ Self Dispatch’
Market (generation and supply) is the principle balancing process (by half hour) Participants need to forecast demand and wind power
Economic, Efficient and Secure
The System Operator has a licence condition to operate a secure, economic and co-ordinated system; it has an incentive scheme to reward efficient operation
Post Gate Balancing ( 1 hr ahead)
The System Operator then balances the system (second by second) and is the sole counterparty to any further trades Actions are taken in advance via Commercial Services
Forecasting, Planning & Information
System Operator forecasts demand and wind power Physical information received from market
Market – Primary Balancer System Operator – Residual Balancer
Bilateral trading activities
Meter readings
Gate closure Real time 1 hour
Bid / offer acceptances
Balancing mechanism BM data ~1,500,000 items /day
Bids/Offers Op Data FPNs ~1000 Balancing actions/day
Settlement
CONTRACT VOLUMES BM actions
National Grid Forecasting & ‘Dispatch’
The Balancing Mechanism and information
Market Forecasting & Self Dispatch
~98% of energy balancing done by market (by half hr) ~2% of energy balancing by System Operator (sec by sec)
+ 0.5 GW + 0.5 GW + 1 GW + 1.5 GW + 1 GW
- 2 GW
Temperature (1°C fall in cold conditions) Cloud cover (clear sky to thick cloud) Precipitation (no rain to heavy rain) Temperature (1°C rise in hot conditions) Cooling power (10 mph rise in cold conditions) Embedded Wind Power (Maximum output)
Demand and Wind Forecasting
8
Ofgem FIT Regiser: Link Latest Installed Solar: 1610 MW Latest Installed Wind: 1995 MW
Embedded Generation Estimates
Last run: 15-Apr-2013 12:09:12 14-APR-2013 15-APR-2013 16-APR-2013 05:00 08:00 12:00 17:00 21:00 00:00 05:00 08:00 12:00 17:00 21:00 00:00 05:00 08:00 12:00 17:00 21:00 Solar (MW) 157 1282 558 4 250 1288 919 274 1288 1059 1 Wind (MW) 1377 1501 1562 1489 1298 1277 1245 1241 1344 1168 943 1059 1322 1450 1632 1519 1004 Total (MW) 1377 1658 2844 2047 1302 1277 1245 1491 2632 2087 943 1059 1322 1724 2920 2578 1005 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 14-APR-2013 05:00 08:00 12:00 17:00 21:00 15-APR-2013 05:00 08:00 12:00 17:00 21:00 16-APR-2013 05:00 08:00 12:00 17:00 21:00 Embedded Generation / MW
500 1,000 1,500 2,000 2,500 20110301 20110415 20110530 20110714 20110828 20111012 20111126 20120110 20120224 20120409 20120524 20120708 20120822 20121006 20121120 20130104 20130218 20130404 20130519 20130703 20130817 20131001 20131115 20131230 PV Installed Capacity PV Output @ 1200
Progressive Demand Control Domestic Consumers unlikely to notice if Demand Control by voltage reduction <5% total OK Notice of Insufficient System Margin NISM High Risk of Demand Reduction HRDR Demand Control Imminent DCI Short Term Operating Reserve (STOR) Contingency Reserve Regulating Reserve Low Frequency Response Demand
Reserve requirements
10
10 s 60 s Time 49.5 49.2 Frequency (Hz) 50.0 49.8 50.2 30 s Primary
(10-30s)
Incident (e.g. generation loss) Secondary
(30s - 30min)
Reserve 49.0 48.8 47.0
Lower Statutory Limit
50.5
Upper Statutory Limit
52.0
Managing Frequency
Demand Disconnection Generation Tripping
Upper Operational Limit Lower Operational Limit Lowest ‘Planned’ Limit
30 mins
Ancillary Services
Mandatory Services
Mandatory Capability from ‘Transmission connected’ generators for:
Primary, Secondary and High frequency response (provider specified holding price) Deload cost paid via Balancing Mechanism Reactive range (paid for by a index based price)
Commercial Services
More economic solutions to mandatory services and reserve that comprise one or more of:
Firm contracts (for a committed period of time) Enhanced capability / different technical parameters Services from providers
- ther than
main generators
11
Committed in operational timescales (no availability fee) Committed before or in
- perational timescales
Commercial Services
12 Firm Frequency Response (5s – 30 mins)
- Availability & Utilisation
prices
- Monthly tendered service
- Window of service
- Mostly generation but open
to all
- Automatic service
- Performance monitoring
Firm Reserve STOR (20 mins) and Fast Reserve (2 mins)
- Availability & Utilisation
Prices
- 3 times year / monthly
tenders
- BM and bespoke dispatch
system
- Performance monitoring /
payment penalties Reserve BM Start Up / Energy Trades
- Short term call off
- Utilisation prices – pre
agreed / negotiated short term
- Framework Agreements
Reactive Enhanced reactive power
- Utilisation /
avilability
- Ad hoc / tender
Firm Constraint Management
- Availability &
utilisation
- Ad hoc tender
- Weeks ahead
Intertrips
- Availability /
utilisation
- Bilateral / framework
STOR: BM: OCGTs, Pumped Storage NBM: Diesel, OCGTs, Hydro, Biomass, CCGT. Fast Reserve: Pumped storage, Sync Gas Synchronous generators Demand side in development Coal and Oil, units in cold storage Synchronous generators Synchronous generators, wind, embedded./demand side in development Commercial and operational: interconnectors, wind, some large generator sites
Ancillary Service Breakdown
Typical contracted levels (figures vary with economics of tenders received) 600-1000MW for Firm Frequency Response 300-400MW for Fast Reserve 2200-2500MW for STOR ~50% of these are Non-BM units
13
Balancing Services Costs
£271
- £14
£1 £70 £97 £56 £5 £17 £1 £52 £69 £9 £100 £16
- £100
- £50
£0 £50 £100 £150 £200 £250 £300
Reactive STOR + BM Utilisation Mandatory Frequency Response Commercial Frequency Response Fast Start Black Start BM Start Up Fast Reserve (Tendered) Fast Reserve (Non-Tendered) Constraints and Intertrips SO-SO BM Constraints Trades PGBTs Fees & Liabilities
£m
2013/14
How the System Operator is funded
Balancing Services Use of System (BSUoS) paid by Generators & Demand that use the Transmission System (~£1.50 / MWh) Includes: Internal SO costs ‘External Costs’ : - Balancing Mechanism and Ancillary Services (~£1bn / year) SO incentive scheme to manage external costs (+/-£25m) The Network is paid for separately via Transmission Charges
14
15
Future GB Wind Capacity Scenarios Until 2020
5,000 10,000 15,000 20,000 25,000 30,000 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Year Installed Wind Capacity / MW
Slow Progression Accelerated Growth
16
The changing grid
‘IFA’ France 2GW
existing electricity network potential wind farm sites potential nuclear sites interconnectors
France 2GW ‘Britned’ Netherlands 1.2GW Belgium 1GW Norway 1.4GW ‘East-West’ Ireland 500MW ‘Moyle’ Ireland 500MW* Denmark 1GW
Arrows are illustrative and do not show connection points.
Cumulative contracted generation (GW) 10 20 30 40 50 60 70 80 90 100 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025* Interconnector Renewable Non-renewable
Source: National Grid TNQCU – March 2013. * No new contracted generation after 2025. Renewable fuel types: Biomass, Hydro, Tidal, Wave, Wind
Further Information
High Level Service Guide http://www2.nationalgrid.com/uk/services/balancing- services/service-guides/ Monthly Balancing Services Summary http://www2.nationalgrid.com/UK/Industry- information/Electricity-transmission-operational- data/Report-explorer/Services-Reports/
17
18 18
Generation Demand
Variable generation
200 400 600 800 1,000 1,200 1,400 1,600 200 400 600 800 1,000 1,200 1,400 1,600 01-Jan 05-Jan 10-Jan 15-Jan 20-Jan 25-Jan 30-Jan 01-Jan 05-Jan 10-Jan 15-Jan 20-Jan 25-Jan 30-Jan MWLarge generation Inflexible generation Active distribution networks
Smart(er) grids & meters, energy storage
Active demand
Time of use tariffs
30 35 40 45 50 55 60 00:00 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 Time of Day Electricity Demand (GW) 2020 Demand ~ 15 GWh (daily) - 1.5 million vehicles Typical winter daily demand Peak Commuting Time 12,000 miles p.a. Peak Commuting Time Optimal Charging PeriodDistributed generation Smarter transmission
Smart zones HVDC Series compensation WAM
Balancing supply and demand?
Energy Storage.
Capacitors Flywheels Batteries Diesel Generators Superconducting Magnets Pumped Storage
0.001 0.01 0.1 1 10 100 1000 0.1 1 10 100 1000 0.01 0.001 0.0001
Power, MW Stored Energy, MWh
Applications/Markets Segmentation of the Electrical Energy Storage Market
Uninterruptible Power Supplies Large Arbitrage Reserve Small Arbitrage Power Quality Traction Supplies Electric Vehicles
Technologies
Dinorwig
Interconnectors vs pump storage
1. Costs Storage: DECC pathway model NOAK pump store = £2000k/MW capital cost with ~75% cycle efficiency Assume ~£200k/MW/yr for financing and non-load op costs Interconnection: Western hvdc link £1.1b for a 400km @ 2400MW hvdc link = £1150/MW/km with 2.5% loss Assume ~£115k/MW/1000km/yr for financing and op costs
20
Interconnection vs pump storage (continued)
- 2. Benefits – pump store
Daily charge per MW = (24-t1) * 75% = 6 MWh Arbitrage profit = (£50 * 6 – £15 * 8) = £180/day = £66k/MW/yr Peak security contribution = CONE = £50k/MW/yr Annual revenue = £116k/MW (cf annual cost £200k/MW )
21
£50/MWh £15/MWh t1 = 16h
- Eg. marginal
fossil burn
- Eg. marginal
renewables Daily price curve
Interconnection vs pump storage (continued)
- 2. Benefits – 1000km E-W intercon giving 1hr local time difference
Arbitrage revenue = (£50 * 0.975 – £15) * 2 = £67/day = £25k/MW/yr Peak security contributions = CONE both ends = £100k/MW/yr Annual revenue = £125k/MW (cf annual cost £115k/MW )
22
£50/MWh £15/MWh t = 1h
- Eg. marginal
fossil burn
- Eg. marginal
renewables Daily price curve
Sensitivities
Storage profit (per MW per yr) Intercon profit (per MW per yr) Base case
- £84k
+£10k Low price = £5/MWh +£29k +£7k High price = £100/MWh +£110k +£71k 1 hr more low price / day +£8k £0 50% chance of simultaneous scarcity £0
- £50k
50% less arbitrage revenues in pickup/dropoff £0
- £11k
50% of link on OH lines £0 +£78k
23
Home battery on PV array
Cost $3000 for 7 kWh @ 90% cycle efficiency = £200/yr financing 1kW convertor = 3hrs * 90% = 2.7 kWhr. Full store = 7 kWhr 1kW arbitrage profit = £0.150*2.7 – £0*3 = £0.41/day = £150/yr Full storage arbitrage profit = £0.150*7 - £0*3 = £1.05/day = £380/yr
124
15p/kWh 1.5p/kWh
- Eg. marginal fossil
+ Dx & Cap LRMC
- Eg. marginal