Oldfield School Expansion Ann Pfeiffer Educational Objective To - - PowerPoint PPT Presentation

oldfield school expansion
SMART_READER_LITE
LIVE PREVIEW

Oldfield School Expansion Ann Pfeiffer Educational Objective To - - PowerPoint PPT Presentation

Audit and Performance Review Panel 10 December 2015 Oldfield School Expansion Ann Pfeiffer Educational Objective To expand Oldfield Primary School in Maidenhead from 210 pupils to 420 pupils - to accommodate growing numbers in the local area:


slide-1
SLIDE 1

Audit and Performance Review Panel

10 December 2015

Oldfield School Expansion

Ann Pfeiffer

slide-2
SLIDE 2

Educational Objective

To expand Oldfield Primary School in Maidenhead from 210 pupils to 420 pupils - to accommodate growing numbers in the local area:

  • On a new site.
  • Within the existing designated area.
  • Without diminishing the high standards of this

‘Outstanding’ school.

slide-3
SLIDE 3

Construction Objectives

  • On time – by September 2015
  • Within budget – Initially £10,000,000
  • Good quality

– build quality – suitable spaces for teaching and learning

slide-4
SLIDE 4

History - Approvals

Cabinet approval in principle to expand Oldfield Primary School from 210 to 420 pupils from 1st September 2014. Dec 2011 Site options and feasibility studies Bray Rd, Winbury school, Braywick Park. Jan – April 2012 Cabinet approval to build on the Bray Road site from 1st September 2014. May 2012 Formal determination of proposal following publication of statutory notices. July 2012 Purchase of two temporary classrooms. Sept 2012

slide-5
SLIDE 5

History – Planning permission

Detailed design and submission of planning application May 2012 – July 2013 Consideration of planning application by Development Control Panel – Deferred. 18 September 2013 Further investigation into alternative sites, incl Green Lane and planning issues – traffic, flooding, green belt. September – December 2013 Consideration of planning application by Development Control Panel - Approved 11 December 2013

slide-6
SLIDE 6

History – Construction period

Appointment of contractor January 2014 Start on site. Re-location of slow-worms caused 14 week delay March 2014 Start of construction - 50 week construction period June 2014 Snagging period July 2015 School removals from old site 20 July 2015 School opened on new site Sept 2015

slide-7
SLIDE 7

Constraints

  • Need to be open for Sept 2015, with sufficient time

for school to move in.

  • Appropriate time of year for moving slow worms.
  • Planning issues – e.g. designing for flood plain,

environment agency approval, traffic management.

  • Objections from vocal local residents, and risk of

Judicial Review.

  • Waterway adjacent to school site – safety, desire for

turning circle and buffer zone for wildlife.

  • Logistics of moving a whole school within a few

days.

  • Latterly - Forest Bridge School needing to move into
  • ld school site, also for Sept 2015
slide-8
SLIDE 8

The new site

slide-9
SLIDE 9

Day 84

slide-10
SLIDE 10

A day in the life…

slide-11
SLIDE 11

Budget

Original estimated budget £10,000,000 Early site option studies and temporary classrooms expenditure £285,885 Approved Budget following final Member approval – Jan 2014 Cabinet Prioritisation Sub Committee £8,242,371

slide-12
SLIDE 12

How did we do?

Expansion from 210 pupils to 420 pupils? - Yes

  • On a new site? Yes
  • Within the existing designated area? Bray Road
  • Without diminishing the high standards of this

‘Outstanding’ school? Yes

  • Headteacher and school staff maintained a calm

environment for pupils to learn throughout the process.

  • Temporary classrooms added onto Chiltern Road site

for the intervening years.

  • Minimising disruption by moving between academic

years.

slide-13
SLIDE 13

How did we do?

On time? – by September 2015. Yes Within budget? – Initially £10,000,000. Yes Project Budget £8,242,370 Predicted final Cost £8,226,329 Expenditure so far £7,997,329 Predicted outstanding incl retention £229,000 Possible underspend £16,042

slide-14
SLIDE 14

How did we do?

Quality

  • Suitable spaces for teaching and learning
  • Good classrooms and other teaching space
  • Good staff and admin spaces
  • Good outdoor spaces
  • Effective pupil drop-off zone
  • Build quality
  • Good overall design
  • Good structure and materials
  • Good external appearance
  • BREEAM – Very Good
slide-15
SLIDE 15

What went well?

  • Achieved handover in time for moving in and starting

in Sept 2015.

  • The procurement route for this Design and Build

scheme via iESE framework. Leadbitter – Bouygues.

  • Overall design: feasibility scheme developed well

into full design, including for the flood zone.

  • Co-operation between RBWM, school, and design

team.

  • Budget planning - risk allowances built in from the

start.

  • Traffic management and pupil drop-off - even with

Stafferton Way works still taking place.

slide-16
SLIDE 16

What could have been better?

  • Fewer slow-worms! Caused delays and

consequential cost increases.

  • Greater continuity of personnel -

architectural team, construction team and internal building services team.

  • Even tighter set of Employer’s requirements

for Design and Build project, particularly regarding finishes.

  • Closer liaison with school and client on

detailed design and Value Engineering. .

slide-17
SLIDE 17

Cont’d

  • A longer period for the final stage, to reduce

the list of snagging issues

  • Less stressful handover for the school.
  • Playing field drainage
  • Decking surfacing
slide-18
SLIDE 18

View from Braywick Park

slide-19
SLIDE 19

School from the rear

slide-20
SLIDE 20

Internal finishes – the hall

slide-21
SLIDE 21

Drop zone and hall