North Carolina Piedmont Nutrient Load Reducing Measures Technical - - PowerPoint PPT Presentation

north carolina piedmont nutrient load
SMART_READER_LITE
LIVE PREVIEW

North Carolina Piedmont Nutrient Load Reducing Measures Technical - - PowerPoint PPT Presentation

North Carolina Piedmont Nutrient Load Reducing Measures Technical Report Project Update Victor DAmato Jonathan Smith Andrew Anderson and Natalie Carmen Project Approach - Schedule Activity May June July August September Task 1 Selection of


slide-1
SLIDE 1

North Carolina Piedmont Nutrient Load Reducing Measures Technical Report Project Update

Victor D’Amato Jonathan Smith Andrew Anderson and Natalie Carmen

slide-2
SLIDE 2

Project Approach - Schedule

Activity May June July August September Task 1 Selection of Measures

  • Kick off and NSAB meeting

Task 2 Data Sources

  • Data protocol
  • Data collection
  • Data assessment
  • Data summary

Task 3 Technical Report

  • Method/tool development
  • Draft report
  • NSAB presentation
  • Final report
slide-3
SLIDE 3

Project Approach – Tasks

  • Task 1. Selection of Measures
  • May 13th NSAB meeting: kick off/presentation attended by Vic, Jonathan
  • Will begin putting together data protocol (Task 2) in preparation
  • Prepared to discuss key questions to be addressed prior to data collection
  • Coordination with PTRC/DWQ
  • Task 2. Data Sources
  • Data protocol technical memo (by May 20th) – criteria for accepting data

– NC Piedmont applicability – Data QA/QC and other characteristics

  • Data collection – collect data sources/references
  • Data assessment – assess sources versus acceptance criteria
  • Data summary (by June 14th) – summarize assessment and recommend data

sources to use

slide-4
SLIDE 4

Project Approach – Tasks

  • Task 3. Technical Report
  • Method/tool development – data processing and

analysis

  • Draft report (by August 9th)
  • NSAB presentation (September 6th)

– Summarize draft report, comments received and proposed revisions and other actions to be taken

  • Final report (by September 20th)
slide-5
SLIDE 5

Today’s Presentation

  • For each measure:
  • Orientation to and

summary of content in draft report

  • Major issues

identified

  • Remaining work to

finalize report

  • Question/answer
  • Executive Summary
  • Background and Introduction
  • Project Parties and Roles
  • Project Overview
  • Data Sources and Assessment
  • (Load Reducing Measure)
  • (Load Reducing Measure)
  • Background
  • Baseline Load Characterization
  • Potential Management Practices
  • Management Practice Performance

Summary and Validation

  • Other Recommendations
  • Program Implementation

Recommendations

  • References
slide-6
SLIDE 6

Remedy Malfunctioning Septic System – Background

  • “Malfunctions” and load delivery characteristics vary spatially and

temporally

  • New malfunctions occurs as old malfunctions are remedied
  • Malfunction types
  • Illicit septic tank effluent discharge
  • Illicit graywater (e.g., from laundry) discharge
  • Demonstrated drainfield malfunction
  • Remedy types
  • Repair to properly functioning septic system
  • Repair with properly functioning TS-II (nitrogen-reducing) onsite system
  • Connection to permitted major NPDES system
  • Replacement with a discharging TS-II system
  • Credits awarded based on rates of different types of malfunctions and

remedies implemented

slide-7
SLIDE 7

Remedy Malfunctioning Septic System – Program Elements

  • New “survey program” for jurisdictions to establish

malfunction rates and accounting for malfunctions and remedies

  • 20% of systems inspected per year
  • Normalize seasonal differences
  • Apply malfunction rate improvement to all systems in jurisdiction
  • Remedies resulting from malfunctions identified via

traditional methods (complaints, required inspections, home transfers)

  • Systems (functioning and malfunctioning) otherwise

eliminated by connection to sewer

  • Averaging across multiple systems captures expected range

in malfunction intensity and remedy performance

slide-8
SLIDE 8

Remedy Malfunctioning Septic System – Malfunction Types

  • Illicit septic tank effluent discharge
  • TN load of 11 lb/yr-person (assumes no reduction in septic tank)
  • TP load of 1.8 lb/yr-person
  • Illicit graywater (e.g., from laundry) discharge
  • TN load of 0.70 lb/yr-person
  • TP load of 0.98 lb/yr-person
  • Based on published data post detergent phosphate reduction
  • Demonstrated drainfield malfunction
  • TN load of 1.1 lb/yr-person
  • TP load of 0.036 lb/yr-person
  • Based on combination of Piedmont water quality data and malfunction

accounting methodologies used in other watershed studies

slide-9
SLIDE 9

Remedy Malfunctioning Septic System – Remedy Types

  • Repair to properly functioning septic system
  • TN load of 0.55 lb/yr-person (95% reduction of STE load)
  • Zero TP load (100% reduction)
  • Based on combination of Piedmont water quality data, Chesapeake and others
  • Currently conducting additional literature review and review of Piedmont water

quality data to estimate functioning and malfunctioning system loads

  • Repair with properly functioning advanced (TS-II) onsite system
  • TN load of 0.22 lb/yr-person (60% + 95% = 98% reduction of STE load)
  • Zero TP load (100% reduction in soil)
  • Connection to permitted NPDES system
  • Assume all load transferred to point source sector, but awaiting DWQ input
  • Replacement with TS-II equivalent discharging system
  • TN load of 4.4 lb/yr-person
  • TP load of 1.8 lb/yr-person
slide-10
SLIDE 10

Remedy Malfunctioning Septic System – Credit Summary

TN load reduction credits TP load reduction credits

Remedy (R) M alfunctioning System (M) Properly functioning septic system (R1) (lb/cap/year) Properly functioning TS-II system (R2) (lb/cap/year) Connection to major NPDES system (R3)* (lb/cap/year) Connection to a TS- II Discharging System (R4) (lb/cap/year) Direct STE discharge (M1) 10.45 10.78 11.0 6.6 Direct graywater/laundry discharge (M2) 0.15 0.48 0.70

  • Demonstrated drainfield

malfunction (M3) 0.55 0.88 1.1

  • Remedy (R)

M alfunctioning System (M) Properly functioning septic system (R1) (lb/cap/year) Properly functioning TS-II system (R2) (lb/cap/year) Connection to major NPDES system (R3) (lb/cap/year)* Connection to a TS- II Discharging System (R4) (lb/cap/year) Direct STE discharge (M1) 1.8 1.8 1.8

  • Direct graywater/laundry

discharge (M2) 0.98 0.98 0.98

  • Demonstrated drainfield

malfunction (M3) 0.036 0.036 0.036

slide-11
SLIDE 11

Remedy Discharging Sand Filter – Background

  • Describes several different types of systems with varying characteristics
  • Only a portion have actually been identified and permitted
  • Accounting can be done on a system-by-system basis but there are

benefits for jurisdictions to combine program with that for septic systems

  • Discharging system types
  • Gravity-dosed single pass sand filters with regular discharges
  • Gravity-dosed single pass sand filters with no or infrequent discharges
  • Recirculating filters and TS-II equivalent treatment systems
  • Malfunctioning (surface failing) systems
  • Remedy types
  • Upgrade to recirculating filters or TS-II treatment systems
  • Connection to major NPDES system
  • Replacement with properly functioning septic system
  • Replacement with properly functioning TS-II onsite system
slide-12
SLIDE 12

Remedy Discharging Sand Filter – System Types

  • Gravity-dosed single pass sand filters with regular discharges
  • TN load of 7.4 lb/yr-person (33% load reduction)
  • TP load of 1.8 lb/yr-person (no load reduction)
  • Based on Durham/DWQ data and some published data
  • Gravity-dosed single pass sand filters with no or infrequent discharges
  • TN load of 7.4 lb/yr-person (33% load reduction)
  • TP load of 0.9 lb/yr-person (50% load reduction)
  • Recirculating filters and TS-II treatment systems
  • TN load of 4.4 lb/yr-person (60% load reduction)
  • TP load of 1.8 lb/yr-person (no load reduction)
  • Malfunctioning systems
  • TN load of 7.4 lb/yr-person (33% load reduction)
  • TP load of 1.8 lb/yr-person (no load reduction)
slide-13
SLIDE 13

Remedy Malfunctioning Septic System – Remedy Types

  • Upgrade to recirculating filters and TS-II

treatment systems

  • TN load of 4.4 lb/yr-person (60% load

reduction)

  • TP load of 1.8 lb/yr-person (no load

reduction)

  • Connection to major NPDES system
  • Assume all load transferred to point source

sector, but awaiting DWQ input

  • Repair to properly functioning septic

system

  • TN load of 0.55 lb/yr-person
  • Zero TP load
  • Repair with properly functioning advanced

(TS-II) onsite system

  • TN load of 0.22 lb/yr-person
  • Zero TP load
slide-14
SLIDE 14

Remedy Malfunctioning Septic System – Credit Summary

TN load reduction credits

Alternative (A) Discharging System (D) Upgrade to TS-II treatment system (A1) (lb/cap/year) Connection to major NPDES system (A2)* (lb/cap/year) Replacement with properly functioning septic system (A3) (lb/cap/year) Replacement with properly functioning TS-II

  • nsite system (A4)

(lb/cap/year) Single-pass filter with regular discharges (D1) 3.0 7.4 6.9 7.2 Single-pass filter with no or infrequent discharges (D2) 3.0 7.4 6.9 7.2 TS-II or equivalent treatment system (D3)

  • 4.4

3.9 4.2 Malfunctioning discharging systems (D4) 3.0 7.4 6.9 7.2

slide-15
SLIDE 15

Remedy Malfunctioning Septic System – Credit Summary

TP load reduction credits

Alternative (A) Discharging System (D) Upgrade to TS-II discharging treatment system (A1) (lb/cap/year) Connection to major NPDES system (A2)* (lb/cap/year) Replacement with properly functioning septic system (A3) (lb/cap/year) Replacement with properly functioning TS-II

  • nsite system (A4)

(lb/cap/year) Single-pass filter with regular discharges (D1)

  • 1.8

1.8 1.8 Single-pass filter with no or infrequent discharges (D2)

  • 0.9

0.9 0.9 TS-II or equivalent treatment system (D3)

  • 1.8

1.8 1.8 Malfunctioning discharging systems (D4)

  • 1.8

1.8 1.8

slide-16
SLIDE 16

Stormwater Measures – Improved Street Sweeping

Chesapeake Bay Expert Panel Recommendation Summary

  • Credit approved in March 2011
  • Primarily based on Law, 2008
  • Two credit methods:
  • Mass loading approach
  • Qualifying street lanes approach
  • *CBP reconvening in August 2013 to update protocol
  • Updated performance
  • Expanded credit for less frequent sweeping
slide-17
SLIDE 17

Stormwater Measures – Improved Street Sweeping

Street Sweeping Pollutant Removal Performance Background

  • First studies in 70’s -80’s
  • Technology of the time limited to mechanical broom
  • Initial research indicated no impact (NURP, 83)
  • Poor pick-up performance of small particulates
  • Improvements to sweeper design in last 30 years have resulted

in significantly increased performance

  • Many studies on pick-up performance, few on impact of

sweeping to downstream WQ

slide-18
SLIDE 18

Stormwater Measures – Improved Street Sweeping

Credit Protocol: Direct Measurement

  • Maintain records of collected “sweepings” mass
  • Conduct analysis of N and P content of collected materials
  • Alternative: Apply standard rates

Lbs of TN = 0.0025 pounds of dry weight sweeping solids Lbs of TP = 0.001 pounds of dry weight sweeping solids

  • Concerns:
  • Little research supporting impact of street sweeping on

downstream water quality

  • Nitrogen processing prior to discharge
slide-19
SLIDE 19

Stormwater Measures – Improved Street Sweeping

Credit Protocol: Miles swept method

  • Estimate annual Nutrient load to road surface
  • Apply removal performance per frequency and type of sweeper

technology

Frequency TP TN Monthly 4% 4% Biweekly 5% 6% Weekly 5% 6%

slide-20
SLIDE 20

Stormwater Measures – Improved Street Sweeping

Credit Protocol: Miles swept method

  • Concerns
  • Road dirt load and constituents highly variable
  • Age/type of roadway surface
  • Traffic load/type
  • vegetation/seasonal effects
  • Climate
  • Sweeping obstructions
slide-21
SLIDE 21

Stormwater Measures – Improved Street Sweeping

Credit Protocol: Miles swept method

  • Sweeping program criteria
  • No parking or other obstructions
  • Sweeper type: regen/vac
  • Primary and secondary roads only
slide-22
SLIDE 22

Stormwater Measures – Stream Restoration/Enhancements

  • Stream Restoration Credit Protocols
  • Prevented sediment
  • In-stream nutrient processing
  • Floodplain reconnection
  • Regenerative Stormwater Conveyance (RSC)
slide-23
SLIDE 23

Stormwater Measures – Stream Restoration/Enhancements

“Prevented Sediment” Protocol

  • Evaluates the reduction in nutrients delivered to receiving waters associated

with the reduction in streambank erosion and relies on computation of three factors:

  • Pre-project annual sediment load
  • Nutrient content (N and P) of streambank soil
  • Net efficiency (%) of restoration in reducing bank erosion
slide-24
SLIDE 24

Stormwater Measures – Stream Restoration/Enhancements

Prevented Sediment: Pre-Project Annual Sediment Load

  • Option 1: Estimate sediment loss rate based on pre-project monitoring of

streambank erosion rates via cross-section surveys and bank pins.

  • Requires pre-project monitoring
  • Monitoring stations must be representative of reach
slide-25
SLIDE 25

Stormwater Measures – Stream Restoration/Enhancements

Prevented Sediment: Pre-Project Annual Sediment Load

  • Option 2: Estimate sediment loss rate based on the application of the Bank

Assessment for Non-Point Source Consequences of Sediment (BANCS, Rosgen 2001, Doll, 2004) method. The BANCS method relies on two common bank erodibility estimation tools which have seen widespread application in North Carolina

  • Bank Erosion Hazard Index (BEHI)
  • Near Bank Stress (NBS)
  • Concerns:
  • Variation among practitioners
  • Erosion rate curves specific to region
slide-26
SLIDE 26

Stormwater Measures – Stream Restoration/Enhancements

Prevented Sediment: Nutrient content of eroded sediments

  • Option 1: Conduct monitoring of streambank sediment

characteristics within the reach of interest

  • Concerns
  • Sediment monitoring protocol
  • Distribution of sampling locations
slide-27
SLIDE 27

Stormwater Measures – Stream Restoration/Enhancements

Prevented Sediment: Nutrient Content of eroded sediments

  • Option 2: Use default nutrient concentration values

representative of urban streams within the region

  • Concerns
  • Variability between reaches
  • Representative values not published for NC

Source Phosphorus Nitrogen Content (lb/tn) 0.46 1.26

slide-28
SLIDE 28

Stormwater Measures – Stream Restoration/Enhancements

Prevented Sediment: Net efficiency

  • Incorporates the efficiency of the restoration to reduce

streambank erosion

  • Concerns
  • Efficiency may range widely between projects
  • Should also consider delivery of nutrients to

downstream resources Limited data was discovered supporting the selection of a restoration efficiency in NC Net Efficiency= 50%

slide-29
SLIDE 29

Stormwater Measures – Stream Restoration/Enhancements In-stream Nutrient Processing Protocol

  • Applies to projects or components of projects in which in-stream

design features promote nutrient processing specifically de-nitrification within the “Hyporheic” zone

  • Protocol:
  • Determine appropriate reach length for credit
  • Identify “hyporheic box”
  • Apply unit denitrification rate
slide-30
SLIDE 30

Stormwater Measures – Stream Restoration/Enhancements In-stream Nutrient Processing Protocol

  • Concerns
  • Hyporheic box/exchange
  • Bed material/bedrock can limit vertical extent of box
  • Slope
  • Substrate
  • Very limited on headwater streams
  • Denitrification rate
  • No published values for NC
  • Net reduction depends on bulk density of bed material
slide-31
SLIDE 31

Stormwater Measures – Stream Restoration/Enhancements

Floodplain Reconnection

  • Applies to projects in which stream restoration results in

frequent overbank flooding and provides temporary storage and treatment of overflows

.

slide-32
SLIDE 32

Stormwater Measures – Stream Restoration/Enhancements

Floodplain Reconnection Protocol

  • Estimate net storage volume of floodplain reconnection
  • Estimate N and P load/concentration delivered to the

floodplain*

  • Estimate N and P removal performance to floodplain

reconnection

  • Compute Net N and P reduction

*Since this credit applies to N and P contained in stormwater runoff, the load estimation should account for the performance of any upland BMPs.

slide-33
SLIDE 33

Stormwater Measures – Stream Restoration/Enhancements

Floodplain Reconnection

  • Estimate of net volume of floodplain reconnection
  • Survey or computation of floodplain treatment storage

volume

  • Computation of fraction of annual runoff which will be

“captured” by floodplain storage

  • Requires detailed hydrologic and hydraulic analysis
slide-34
SLIDE 34

Stormwater Measures – Stream Restoration/Enhancements

Floodplain Reconnection

  • Estimate of N and P Load delivered to the floodplain
  • Determine total N & P load delivered to watershed
  • < 40 acres JFLSLAT
  • > 40 acres
  • Falls: WARMF model
  • Jordan: Jordan Lake Model Compute net load

delivered to floodplain by multiplying total load by fraction of runoff treated

slide-35
SLIDE 35

Stormwater Measures – Stream Restoration/Enhancements

Floodplain Reconnection

  • Estimate N and P removal performance of floodplain

reconnection

  • Compute load reduction by applying stormwater

wetland effluent values (JFLSLAT) to reconnection volume

slide-36
SLIDE 36

Stormwater Measures – Stream Restoration/Enhancements Regenerative Stormwater Conveyance

  • Dry Channel RSC Protocol
  • Compute treated volume (filtered, infiltrated, retained)
  • Compute N & P load per JFLSLAT
  • Apply effluent values for treated volume per Dr. Hunts
  • ngoing research (use Sand Filter in interim)
  • Concerns
  • Unproven BMP in NC