NOPSEMA briefing and MODU mooring systems in cyclonic conditions - - PowerPoint PPT Presentation

nopsema briefing
SMART_READER_LITE
LIVE PREVIEW

NOPSEMA briefing and MODU mooring systems in cyclonic conditions - - PowerPoint PPT Presentation

NOPSEMA briefing and MODU mooring systems in cyclonic conditions Kerry Gordon Manager Assessment & Inspection 10 Sept 2015 1 Selected topical issues Triennial independent review of NOPSEMA Stakeholder engagement continues to


slide-1
SLIDE 1

1

NOPSEMA briefing

and MODU mooring systems in cyclonic conditions

Kerry Gordon

Manager – Assessment & Inspection 10 Sept 2015

slide-2
SLIDE 2

Selected topical issues

  • Triennial independent review of NOPSEMA

– Stakeholder engagement continues to be a focus

  • Legislative change

– Amended Wells Regulations commence 1 Jan 2016

  • NOPSEMA focused topic inspection program

2

slide-3
SLIDE 3

Focus topics 2015

Maintenance management

  • management of deferral of work
  • equipment strategies - inspection and monitoring
  • structural integrity - inspection and monitoring
  • safety-critical equipment meeting performance standards.

3

slide-4
SLIDE 4

Focus topics 2015

Contractor management

  • Contractor agreements and performance governance by the
  • perator in relation to:

– how the operator of a diving project effectively ensures diving contractors are complying with their DSMS/DPP – third party contractors & equipment management – asset integrity monitoring programs conducted by third parties.

  • Contractor selection and competency
  • Operator and contractor interface management e.g. SIMOPS.

4

slide-5
SLIDE 5

Focus topics 2015

Blowout source control contingency planning

  • Currently the degree of contingency planning for a well

blowout (relief well, cap and contain etc) varies between

  • titleholders. NOPSEMA will inspect titleholders

arrangements for compliance with the legislation.

– Note: new well regulation RMAR Part 5, Reg. 5.09(k) now specifically addresses the matter.

5

slide-6
SLIDE 6

Focus topics 2015

Position keeping systems

  • Stability management including Ballast & Bilge Systems.
  • Dynamic positioning systems
  • Pre-lay mooring design
  • Inspection testing and maintenance including software

updates

  • Integrity of safety critical elements
  • Competence (operators and maintainers of position keeping

systems).

6

slide-7
SLIDE 7

7

MODU mooring systems in cyclonic conditions

slide-8
SLIDE 8

Background

  • The Atwood Osprey experienced a mooring failure

during cyclone Olwyn and was blown some three nautical miles off location in the vicinity of subsea and surface infrastructure and environmentally sensitive shorelines

  • Investigations have been conducted by NOPSEMA

and Atwood who have both committed to sharing lessons learned from this incident with industry.

8

slide-9
SLIDE 9

Sequence of events - Cyclone Olwyn

  • 9 March – Commence well suspension in preparation for rig evacuation
  • 10-11 March – Osprey completes well suspension, power- down and

evacuation

  • 12 March – TC Olwyn strikes Atwood Osprey
  • 12-13 March – AHTSV reports rig off location ~3nm

13-man team arrives on board to take the rig in tow by the AHTSV and holds station; team departs rig

  • 14 March - Commence ROV operations to assess seabed and condition of

infrastructure.

9

slide-10
SLIDE 10

10

slide-11
SLIDE 11

Regulatory perspective

Four known Incidents of MODU loss of position due to Cyclone activity

  • Mar 2004 – MODU dragged anchors

Cat-3

  • Dec 2008 – MODU dragged anchors

Cat -2

  • Feb 2011 – MODU dragged anchors

Cat -3

  • Mar 2015 – MODU snapped anchor wire

Cat -3

11

slide-12
SLIDE 12

Regulatory perspective

Six documented instances where MODUs have failed to down- man in the face of impending cyclones.

  • Semi-Sub MODU 2004
  • Jack-Up MODU

2006

  • Semi-Sub MODU 2007
  • Semi-Sub MODU 2009
  • Semi-Sub MODU 2011
  • Semi-Sub MODU 2015

12

slide-13
SLIDE 13

Regulatory perspective continued

Inconsistency in safety case design and performance standards utilised in mooring design and analysis.

  • “50 year return period”
  • 1 case
  • “API RP 2SK using 20 year return period”
  • 2 cases
  • “API RP 2SK using 10 year return period”
  • 1 case
  • “specification to ABS rules and MODU code”
  • 1 case
  • completely silent on design and performance

standards for mooring systems.

  • 3 cases

13

slide-14
SLIDE 14

Investigation overview

  • Hind-cast computer modelling
  • ROV survey of the seabed
  • Review of the mooring system design and its

component parts

  • Inspection of critical components
  • Visual inspection, metallurgical analysis and

destruction testing of the mooring lines

14

slide-15
SLIDE 15

Investigation overview continued

  • Design including pre-laid systems
  • Assurance, installation and managing change
  • Inspection and maintenance.

15

slide-16
SLIDE 16

Findings - Mooring design

  • Return period (20,50,100 year RP environmental

conditions)

  • Component positioning
  • Lack of detailed risk assessment at the mooring

design stage involving all parties

  • Deficiencies in the assurance processes at the

interfaces between the responsible parties.

16

slide-17
SLIDE 17

Mooring installation - Interface

Combination of rig and pre-laid mooring components

  • Pre lay mooring installation procedures
  • Drag anchor pull test tensions
  • Management of change.

17

slide-18
SLIDE 18

Operations, inspection and maintenance

  • Records of inspection history
  • Frequency of inspections
  • Competency assurance system for mooring

equipment/rope inspectors

  • Lack of performance standards and the

necessary associated assurance tasks for the mooring system – ongoing availability and reliability of the SCE

18

slide-19
SLIDE 19

Recovery preparedness

Opportunities for improvement

  • Procedures for managing mooring line tensions

for survival conditions/MODU cyclone evacuation

  • MODU real time position indication - GPS
  • Mooring line tension/weather recording and

UPS

  • MODU recovery – preparedness for towing

19

slide-20
SLIDE 20

Key learnings - Mooring failure

  • Reliability of the mooring system under foreseeable

cyclone conditions

  • Assurance of mooring design, installation and

critical component materials – quality control

  • The interface: SCE - inspection, maintenance, MoC

and operations procedures

  • Recovery preparedness and. response

20

slide-21
SLIDE 21

Regulatory approach and expectations

slide-22
SLIDE 22

MODU mooring workshop

Provided an opportunity for industry and NOPSEMA to collectively examine better ways to manage this significant risk.

  • Provide information about the incident and lessons learned
  • Communicate regulatory requirements and perspective
  • Discuss opportunities for improvement

– identify any actions on which immediate consensus can be reached – identify areas for which there is consensus in direction but require more work to define detail.

22

slide-23
SLIDE 23

Workshop inputs

  • NOPSEMA and Atwood investigation findings
  • Information paper provided for context
  • Consideration of existing standards and practices

from elsewhere

23

slide-24
SLIDE 24

Regulatory expectations

To strengthen requirements with a view to improving the situation:

  • Achieve consensus on what is best practice in relation to

each of these issues;

  • Determine current industry knowledge and approach with

respect to mooring design criteria;

  • Assess and manage the risks arising from these issues with

respect to the impending cyclone season and longer term.

24

slide-25
SLIDE 25

Regulatory expectations

Safety case considerations:

  • rig operators - mooring systems are safety critical

Current considerations:

  • understand the design basis and integrity of current

hardware

25

slide-26
SLIDE 26

Next steps

NOPSEMA will issue regulatory guidance:

  • to address key issues identified and recognized in the

workshop and in the information paper;

  • to raise awareness and prompt a review of arrangements in

place for the immediately forthcoming cyclone season; and

  • to provide guidance on key interface points between

titleholders and operators which should be addressed in the rig safety case

Methodology for topics requiring further work

26

slide-27
SLIDE 27

27

Thankyou