National Grid Presentation 5 July Ofgem Workshop Agenda Opex - - PowerPoint PPT Presentation

national grid presentation 5 july ofgem workshop agenda
SMART_READER_LITE
LIVE PREVIEW

National Grid Presentation 5 July Ofgem Workshop Agenda Opex - - PowerPoint PPT Presentation

National Grid Presentation 5 July Ofgem Workshop Agenda Opex Capex Load-related and adjustment and incentive mechanisms Non-load Financial Issues Overall impact on consumers 2 Opex Electricity and Gas Opex Ofgems


slide-1
SLIDE 1

National Grid Presentation 5 July Ofgem Workshop

slide-2
SLIDE 2

2

Agenda

Opex Capex

Load-related and adjustment and incentive mechanisms Non-load

Financial Issues Overall impact on consumers

slide-3
SLIDE 3

Opex

slide-4
SLIDE 4

4

Electricity and Gas Opex Ofgem’s Initial Proposals

NGET

2004/05

16% “Normalisation” reduction

From this revised 2004/05 base Ofgem then factor in

A further 9% reduction from 2007/08 Increasing to 17% by 2011/12

NGGT

2004/05

6% “Normalisation” reduction

From this revised 2004/05 base Ofgem then factor in

A further 8% reduction from 2007/08 Increasing to 16% by 2011/12

slide-5
SLIDE 5

5

Electricity TO Opex The Gap Between Us

50 100 150 200 250 300 350 400 450 500 550 600

1 9 9 1 / 9 2 1 9 9 2 / 9 3 1 9 9 3 / 9 4 1 9 9 4 / 9 5 1 9 9 5 / 9 6 1 9 9 6 / 9 7 1 9 9 7 / 9 8 1 9 9 8 / 9 9 1 9 9 9 / 2 / 1 2 1 / 2 2 2 / 3 2 3 / 4 2 4 / 5 2 5 / 6 2 6 / 7 2 7 / 8 2 8 / 9 2 9 / 1 2 1 / 1 1 2 1 1 / 1 2

TO + SO TO SO Ofgem TO Proposals

slide-6
SLIDE 6

6

Why The Gap?

“Normalisation” of 2004/05 is flawed

Normal costs deducted as if they were “abnormal”

Projecting forward from 2004/05

Only partial recognition of “quasi capex” No recognition of system expansion and asset condition

upward drivers

No recognition of real pay growth in the economy Future efficiencies contain overlap, error and arbitrary

exclusions

Reducing activity levels to align with Ofgem’s

targets would lead to reduced network reliability

slide-7
SLIDE 7

Load-related capex

slide-8
SLIDE 8

8

Load-related capex in the round

We agree on the desirability of using revenue

drivers/adjustment mechanisms for ‘uncertain’ spend

However, still need a baseline projection for load-

related capex for

Financial modelling As a baseline for adjustment

Deal first with baselines and then with the

adjustment/incentivisation mechanisms

slide-9
SLIDE 9

9

Ofgem’s proposals - electricity

2000/1-2004/5

Deemed efficient

Deductions from our 2007/8-2011/12 plan

13%

“entry volume adjustment”

2%

“avoidable early replacement”

4%

“double counting”

6%

“scope for improved procurement” / above inflation unit cost increases for further review” 2005/6 and 2006/7

Treated as forecast years, thus deductions broadly consistent with

Ofgem’s treatment of our 2007/8-2011/12 plan

slide-10
SLIDE 10

10

Ofgem’s proposals - gas

2001/2-2005/6

£75m of investment re increased entry capacity at St

Fergus deemed inefficient

Deductions from our 2007/8-2011/12 plan

58%

“entry volume adjustment”

8%

“scope for improved procurement” / above inflation unit cost increases for further review”

2005/6 and 2006/7

Treated as forecast years, thus deductions broadly

consistent with Ofgem’s treatment of our 2007/8-2011/12 plan

slide-11
SLIDE 11

11

Our initial response (1)

We need detailed feedback from Ofgem to comment on

their assumptions

2005/6 and 2006/7 are completed/contractually committed

and so PCR should update for this information

Ofgem’s treatment of our procurement costs is hard to

justify in the face of an inflationary market place

Steel costs Pipeline build programme Utility investment programmes

As with non-load investment, need to reach agreement on

likely future trend of unit costs

slide-12
SLIDE 12

12

Our Initial response (2)

We expect revenue drivers to deal with

uncertainties but large proportion of load related investment is “validated”:

Capacity rights purchases through gas entry auctions Agreement of ARCA for gas exit Bilateral agreements and commitment to Final Sums for

electricity entry and exit

slide-13
SLIDE 13

Adjustment mechanisms and incentives

slide-14
SLIDE 14

14

Ofgem’s proposals

Increased used of revenue drivers to deal with uncertainty Baselines set on the basis of actual system capability Simple or sophisticated UCAs Five year rolling incentives Assumption of interruption or capacity swap before

investment

Increased use of penal-only incentive schemes

Implicitly for new investment Explicitly for electricity network reliability

Question mark over extent to which investment purely and

mechanically driven by user commitment

slide-15
SLIDE 15

15

Our initial response

Supportive of overall approach but current package

not acceptable, not least because

Gas baselines above actual system capability UCAs lower than likely investment costs plus exposed to

these for up to two price control periods

Proposed timing of incentive-driven cash flows could

exacerbate financeability issues

Potentially huge downside on proposed gas investment

incentive

Overall

Proposals align poorly with our overall licence obligations Downside dominates

slide-16
SLIDE 16

Non-load related capex

slide-17
SLIDE 17

17

Ofgem’s proposals - electricity

2000/1-2004/5

Deemed efficient

Deductions from our 2007/8-2011/12 plan

26%

“lower level of asset replacement and refurbishment is required with more efficient unit costs”

9%

“scope for improved procurement” / above inflation unit cost increases for further review”

2005/6 and 2006/7

Treated as forecast years, thus % deductions are as for the 2007/8-2011/12

plan

Ofgem’s Initial Proposals (2005/06 – 2011/12):

33% cut in overhead lines investment 27% cut in switchgear investment Further £128m cut in other plant types Further procurement efficiency of £114m

slide-18
SLIDE 18

18

Our initial response

Need detail on the basis for Ofgem’s proposals but

  • ur own view is unchanged

We are a responsible asset manager

Had to overspend to maintain reliability and to operate

efficiently

Risk taking vs benefit of less asset replacement not economic to

UK We have set out what we believe is required to

maintain network performance

Based on robust, extensive asset condition information In context with the scale and age of the network

slide-19
SLIDE 19

19

Asset replacement investment profile

Scale of expenditure forecast is large relative to the recent past…

Asset Replacement expenditure 0.0 100.0 200.0 300.0 400.0 500.0 600.0 2000/01 2001/02 2002/03 2003/04 2004/05 2005/06 2006/07 2007/08 2008/09 2009/10 2010/11 2011/12

slide-20
SLIDE 20

20

Asset replacement investment profile

… but not large in terms of the lifecycle and size of the network

Replacement cost of relevant part of network ≈ £15.5bn Condition-informed weighted asset life of relevant network assets ≈ 46 years Majority of relevant assets installed between 1961 to 1970

Replacement rates

Recent historical replacement rate ≈ £150m p.a. Long-run steady state ≈ £335m p.a. Installation rate ≈ £900m p.a. Our plan ≈ £500m p.a.

slide-21
SLIDE 21

21

Why is our investment plan as it is?

We understand

The condition of our assets and impact of assets failing The drivers and rates of deterioration of those assets

The asset replacement plan is based on assets

being replaced just before the probability of failure becomes unacceptable

Assets replaced on the basis of specific, detailed

condition information

Capital plan kept under constant review to reflect latest

condition information

Replacement plans only identify sufficient replacement to

maintain the existing performance of the network

slide-22
SLIDE 22

22

Short term consequences of spending less

More assets at risk of failure Increased risk of loss of supply

Wide impact on consumers Long time to replace or repair failed assets

Increased risk of safety and environmental

incidents

slide-23
SLIDE 23

23

Long term consequences of spending less

Increased asset failures More unplanned work

Increased opex and

capex costs

Increased outage/

resource constraints

Ultimately, deterioration

  • f network beyond the

point of recovery

slide-24
SLIDE 24

24

Ofgem’s proposals - gas

2001/2-2005/6

Deemed efficient

Deductions from our 2007/8-2011/12 plan

30%

  • f our emission reduction investment plan

33%

less asset replacement

5%

  • verall deduction for “scope for improved procurement”

2005/6 and 2006/7

Treated as forecast years, thus deductions broadly consistent with

2007/8-2011/12 plan

slide-25
SLIDE 25

25

Our initial response

Need detailed feedback but our own view is

unchanged

Our forecast sets out what we believe is required

to

Meet legislative requirements with respect to emissions Maintain the existing assets in serviceable condition to

maintain security of supply

Consequences of spending to Ofgem’s plans

Loss of flexibility in network

slide-26
SLIDE 26

Financial Issues

slide-27
SLIDE 27

27

Rate of return/financeability

Early days on this

Main Ofgem RoR advice due for August

Points to note at this stage

Pleased that Ofgem intend to deal with the NGET depreciation ‘cliff

face’

DPCR4 RoR at top of relevant range because of the investment

focus of the review - not obvious why this should not apply to TPCR

Major proposed break with DPCR4 (and with most other price

reviews of the last ten years) on treatment of financeability – viz. any financeability issues assumed to be dealt with via equity injection

Issue of the implications of this for RoR, both

‘Narrow’ transactional costs raised by Ofgem and Potential wider impact on the nature of the National Grid investor base

slide-28
SLIDE 28

28

Pensions

Proposals on ‘legacy’ pensions inconsistent with

Ofgas encouragement for Centrica divestment Options available at the time on pension splitting Practice at the time on risk sharing

Proposals on ERDCs

Intrinsically unreasonable Inconsistent with both the outcome of DPCR4 and the

reasons given for that outcome

Appear to disincentivise honest and full provision of

information to Ofgem

slide-29
SLIDE 29

Summary

slide-30
SLIDE 30

30

Purpose of our spending plans

Facilitate markets through network reinforcement

and extension

Maintain network reliability Maintain or improve the safety, physical security

and environmental performance of the networks while operating efficiently

slide-31
SLIDE 31

31

Consumer cost and benefits

Incremental price impact of our plan on domestic

consumers

£2.20 p.a. for Gas consumers

Of which increased replacement capex = 10p

£1.25 p.a. for Electricity consumers

Of which increased replacement capex = 25p

Benefits

A network that responds to market developments The reliability that we believe customers expect Responsible safety and environmental performance

slide-32
SLIDE 32

End