multistory stem building
play

MULTISTORY STEM BUILDING August 2019 DSA MILESTONES Submission - PowerPoint PPT Presentation

Los Alamitos High School MULTISTORY STEM BUILDING August 2019 DSA MILESTONES Submission Current Project Status Construction of Phase I in Progress DSA Approval Construction Documents in Review with the Division of the State Architect


  1. Los Alamitos High School MULTISTORY STEM BUILDING August 2019

  2. DSA MILESTONES Submission Current Project Status Construction of Phase I in Progress DSA Approval Construction Documents in Review with the Division of the State Architect Constructability Review Analysis in Progress Phase II Phase I Construction Construction 2

  3. PHASE I Scope of Work Contractor Mobilization Canopy Demolition Parking Lot Reconfiguration Baseball Scoreboard Interim Housing 3

  4. PHASE I Construction Schedule JUL AUG SEP OCT NOV DEC Contractor Mobilization Contractor Mobilization Canopy Demolition Staff Relocation Parking Lot Reconfiguration TBD Baseball Scoreboard Interim Housing 4

  5. DSA REVIEW AND APPROVAL Review Process ▪ Pre-Application Meeting ▪ Primary Areas Reviewed Fire, Life, Safety Structural Access Compliance Review and Approval Milestones ▪ June 10, 2019 - Construction Documents Submitted ▪ September 15, 2019 - Initial Review Comments Anticipated ▪ November 1, 2019 - Response to Comments Anticipated ▪ December 1, 2019 - Approval of Construction Documents Anticipated ▪ January 2020 - Determine and Negotiate 5 Guaranteed Maximum Price

  6. CONSTRUCTABILITY A technique to review construction processes from start to finish during pre-construction phase. It is used to identify obstacles before a project is built to reduce or prevent errors, delays, and cost overruns. Focused Areas Site Verification Manufacturer Details and Input Product Quality and Installation Quality Assurance Measures Value Engineering Project Logistics Design Discipline Congruity Design Feasibility and Corrections 6

  7. CONSTRUCTABILITY Plumbing and Fire Protection Review Categories ▪ Fixtures, Piping Electrical ▪ Fixtures, Conduit, Building Utility Connections Outlets ▪ Plumbing, Storm Drain, Electrical, Data HVAC Equipment, Registers, ▪ Ducting Building Substructure ▪ Soils Remediation, Footings, Foundations Data and Audio/Visual ▪ Equipment, Data Drops, Projectors, Displays Vertical Building Shell ▪ Exterior and Interior Walls, Metal Panels, Brick Veneer, Windows Horizontal Building Shell 7 ▪ Floor Slabs, Roof Structure, Soffits

  8. CTE ROBOTICS LAB Equipment • HAAS Mini Mill • Metal Laser Cutter • CNC Router • 3D Printer • CNC Mill • 80 Gallon Compressor • 10 AMP 50’ Cord Reel • 8’ Workbench 8

  9. CTE COMPUTER LAB 9

  10. UPDATED STEM CLASSROOM LAYOUT Lab Station Locations • Relocated from peninsulas to islands in the center of the classroom • (8) Total Lab Spaces • Teaching Island 10

  11. Questions and Comments Alexander Martensson

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend