R e a d y T o G o … A t 5 0 B e l o w
Eielson Air Force Base
P r e p a r e - D e p l o y - E n a b l e
1
Moose Lake Utilities Repair P r e p a r e - D e p l o y - E n a b - - PowerPoint PPT Presentation
Eielson Air Force Base R e a d y T o G o A t 5 0 B e l o w Moose Lake Utilities Repair P r e p a r e - D e p l o y - E n a b l e 1 Overview Project Duration: late February 30 September Cost: $31.4M for the Entire Moose
R e a d y T o G o … A t 5 0 B e l o w
P r e p a r e - D e p l o y - E n a b l e
1
P r e p a r e - D e p l o y - E n a b l e
Project Duration: late February– 30 September Cost: $31.4M for the Entire Moose Lake Subdivision Phase A 2016 (completed) – Eielson Place/Timberwolf Ct Phase B 2017 – Misty Fjord/Sundog Ct Phase C 2018 (projected) – South Mukluk Loop Phase D 2019 (projected) – North Mukluk Loop/Coldfoot St Project Provides Upgraded Utilities to Moose Lake Residents
2
P r e p a r e - D e p l o y - E n a b l e
3
P r e p a r e - D e p l o y - E n a b l e
Parking/Two-way Traffic One-way Traffic Construction Fencing Walking Path
5
P r e p a r e - D e p l o y - E n a b l e
Work Hours- Authorized: 7 days/week from 0800-2000 Planned: 6 days/week (Monday-Saturday) from 0800-1800 Frequent Contractor Access to Mech Rooms Starting Late Feb
thru 30 Sep
Mech Rms & Thru-Path Clear of Personal Property by 20 Feb Outages- Minimum of 48 hour Notice (Except in Case of Emergencies) Cannot Start Prior to 0900 or Exceed 6 hours in Duration See Following Slides for Tentative Timeline Heavily Weather Dependent (May Slip Forward or Backward) Dewatering- Pumps will be Online 24/7 for the Duration of the Project
6
P r e p a r e - D e p l o y - E n a b l e
Residents - Avoid All Construction Areas Street Light & Tree Removal Dust and Noise Changes in Traffic Patterns and Parking – Parking Provided
Behind Homes (2 Spaces/Home)
Excavation Begins Mid Apr No Heat After 4 days with Low Temperature Above 40oF
(historically Mid May – Mid Sep)
No Access to Front Yard, Street, Driveway Large Garage Items Should be Removed Prior to Project Start
Unless They Can be Left There for Project Duration
7
P r e p a r e - D e p l o y - E n a b l e
8
Outage Type Affected Units Purpose Tentative Start Date Duration Water Sundog, Misty Fjord Temp Water Heater Install Late Feb 4 hours Water and Sewer Sundog, Misty Fjord Temp Lift Station Install Mid Apr 4 hours Hot Water and Heat
Coldfoot Switch to Temp Hot Water Early May 6 hours Water Timberwolf, Eielson Place, Mukluk, Misty Fjord, Sundog, Coldfoot Cut Loop to Existing Utilities Early May 6 hours Heat
Sundog Demo Existing Heat Weather Dependent Thru Project Hot Water
Demo Existing Heat Weather Dependent 6 hours Water Sundog, Misty Fjord, N. Mukluk, Coldfoot Commission New Water Line End Jul 6 hours Hot Water Sundog, Misty Fjord, N. Mukluk, Coldfoot Tie In New Heat to Existing End Jul 6 hours Water and Sewer Sundog, Misty Fjord Commission New Sewer Line Early Aug 2 hours
P r e p a r e - D e p l o y - E n a b l e
9
Affected Units Purpose Tentative Start Date Duration ALL Base, GCI, ACS Outage Mid May 6 hours ALL Primary Power Outage Mid May 6 hours ALL Secondary Power Outage Mid May 6 hours
P r e p a r e - D e p l o y - E n a b l e
10
Affected Roads Purpose Tentative Start Date Duration Moose Lake between Timberwolf and Coldfoot Temp Utility Crossing Install Mid Mar 12 hours Mukluk Temp Lift Station Install Mid Mar 12 hours Moose Lake between Timberwolf and Coldfoot Temp Tie In at Mech Rooms Early May Thru Mid Sep Misty Fjord Cut Loop to Existing Utilities Early May Thru Mid Sep Sundog Demo Existing Heat Early May Thru Mid Sep
P r e p a r e - D e p l o y - E n a b l e
11
P r e p a r e - D e p l o y - E n a b l e
12
P r e p a r e - D e p l o y - E n a b l e
Project Contact Info: 907-377-2100 (CE Customer Service) Inform the Operations Manager that your call is related
to the Moose Lake Utilities Project
13
P r e p a r e - D e p l o y - E n a b l e
P r e p a r e - D e p l o y - E n a b l e
P r e p a r e - D e p l o y - E n a b l e
Little Things Go A Long Way
Monthly Neighborhood Outdoor Dinner – Food Provided by Corvias
Mosquito Abatem ent
Yard Carts
ATV/ RV Storage in FSS Lot – Paid by Corvias!!!
Trash Service – We will have a centralized are that will have dum psters. We will update as we determ ine that location.
P r e p a r e - D e p l o y - E n a b l e
Utilities We are working with Conservice to determ ine the best
way to adjust to the im pacts.
Garage Im pact Concession
$40 0 one tim e check (one tim e paym ent in Septem ber) Will be prorated for fam ilies that m ove our during that tim e. If you occupy the hom e from and past the 15th of that m onth you
will receive the whole prorate for that m onth. PCS Move Out Support
Corvias/ HMO will Coordinate Move Out Dates With Construction
Schedule
P r e p a r e - D e p l o y - E n a b l e
90 7-372-230 0 during business hours 90 7-372-230 2 after hours