Moose Lake Utilities Repair P r e p a r e - D e p l o y - E n a b - - PowerPoint PPT Presentation

moose lake utilities repair
SMART_READER_LITE
LIVE PREVIEW

Moose Lake Utilities Repair P r e p a r e - D e p l o y - E n a b - - PowerPoint PPT Presentation

Eielson Air Force Base R e a d y T o G o A t 5 0 B e l o w Moose Lake Utilities Repair P r e p a r e - D e p l o y - E n a b l e 1 Overview Project Duration: late February 30 September Cost: $31.4M for the Entire Moose


slide-1
SLIDE 1

R e a d y T o G o … A t 5 0 B e l o w

Eielson Air Force Base

P r e p a r e - D e p l o y - E n a b l e

1

Moose Lake Utilities Repair

slide-2
SLIDE 2

P r e p a r e - D e p l o y - E n a b l e

Overview

 Project Duration: late February– 30 September  Cost: $31.4M for the Entire Moose Lake Subdivision  Phase A 2016 (completed) – Eielson Place/Timberwolf Ct  Phase B 2017 – Misty Fjord/Sundog Ct  Phase C 2018 (projected) – South Mukluk Loop  Phase D 2019 (projected) – North Mukluk Loop/Coldfoot St  Project Provides Upgraded Utilities to Moose Lake Residents

2

slide-3
SLIDE 3

P r e p a r e - D e p l o y - E n a b l e

Construction Overview

3

slide-4
SLIDE 4

P r e p a r e - D e p l o y - E n a b l e

Parking/Two-way Traffic One-way Traffic Construction Fencing Walking Path

5

Construction Overview

slide-5
SLIDE 5

P r e p a r e - D e p l o y - E n a b l e

Impacts

 Work Hours-  Authorized: 7 days/week from 0800-2000  Planned: 6 days/week (Monday-Saturday) from 0800-1800  Frequent Contractor Access to Mech Rooms Starting Late Feb

thru 30 Sep

 Mech Rms & Thru-Path Clear of Personal Property by 20 Feb  Outages-  Minimum of 48 hour Notice (Except in Case of Emergencies)  Cannot Start Prior to 0900 or Exceed 6 hours in Duration  See Following Slides for Tentative Timeline  Heavily Weather Dependent (May Slip Forward or Backward)  Dewatering-  Pumps will be Online 24/7 for the Duration of the Project

6

slide-6
SLIDE 6

P r e p a r e - D e p l o y - E n a b l e

Safety / What to Expect

 Residents - Avoid All Construction Areas  Street Light & Tree Removal  Dust and Noise  Changes in Traffic Patterns and Parking – Parking Provided

Behind Homes (2 Spaces/Home)

 Excavation Begins Mid Apr  No Heat After 4 days with Low Temperature Above 40oF

(historically Mid May – Mid Sep)

 No Access to Front Yard, Street, Driveway  Large Garage Items Should be Removed Prior to Project Start

Unless They Can be Left There for Project Duration

7

slide-7
SLIDE 7

P r e p a r e - D e p l o y - E n a b l e

Expected Utility Outages

8

Outage Type Affected Units Purpose Tentative Start Date Duration Water Sundog, Misty Fjord Temp Water Heater Install Late Feb 4 hours Water and Sewer Sundog, Misty Fjord Temp Lift Station Install Mid Apr 4 hours Hot Water and Heat

  • N. Mukluk, Misty Fjord, Sundog,

Coldfoot Switch to Temp Hot Water Early May 6 hours Water Timberwolf, Eielson Place, Mukluk, Misty Fjord, Sundog, Coldfoot Cut Loop to Existing Utilities Early May 6 hours Heat

  • N. Mukluk, Coldfoot, Misty Fjord,

Sundog Demo Existing Heat Weather Dependent Thru Project Hot Water

  • N. Mukluk, Coldfoot

Demo Existing Heat Weather Dependent 6 hours Water Sundog, Misty Fjord, N. Mukluk, Coldfoot Commission New Water Line End Jul 6 hours Hot Water Sundog, Misty Fjord, N. Mukluk, Coldfoot Tie In New Heat to Existing End Jul 6 hours Water and Sewer Sundog, Misty Fjord Commission New Sewer Line Early Aug 2 hours

slide-8
SLIDE 8

P r e p a r e - D e p l o y - E n a b l e

Expected Power/Comm Outages

9

Affected Units Purpose Tentative Start Date Duration ALL Base, GCI, ACS Outage Mid May 6 hours ALL Primary Power Outage Mid May 6 hours ALL Secondary Power Outage Mid May 6 hours

slide-9
SLIDE 9

P r e p a r e - D e p l o y - E n a b l e

Expected Road Closures

10

Affected Roads Purpose Tentative Start Date Duration Moose Lake between Timberwolf and Coldfoot Temp Utility Crossing Install Mid Mar 12 hours Mukluk Temp Lift Station Install Mid Mar 12 hours Moose Lake between Timberwolf and Coldfoot Temp Tie In at Mech Rooms Early May Thru Mid Sep Misty Fjord Cut Loop to Existing Utilities Early May Thru Mid Sep Sundog Demo Existing Heat Early May Thru Mid Sep

slide-10
SLIDE 10

P r e p a r e - D e p l o y - E n a b l e

Safety – What to Expect

11

slide-11
SLIDE 11

P r e p a r e - D e p l o y - E n a b l e

Safety – What to Expect

12

slide-12
SLIDE 12

P r e p a r e - D e p l o y - E n a b l e

Project Contact Information

 Project Contact Info: 907-377-2100 (CE Customer Service)  Inform the Operations Manager that your call is related

to the Moose Lake Utilities Project

13

slide-13
SLIDE 13

P r e p a r e - D e p l o y - E n a b l e

Questions?

slide-14
SLIDE 14

P r e p a r e - D e p l o y - E n a b l e

RESIDENT SUPPO RT DURING UT ILIT Y C O NST RUC T IO N

slide-15
SLIDE 15

P r e p a r e - D e p l o y - E n a b l e

Resident/family Support

 Little Things Go A Long Way

Monthly Neighborhood Outdoor Dinner – Food Provided by Corvias

Mosquito Abatem ent

Yard Carts

ATV/ RV Storage in FSS Lot – Paid by Corvias!!!

Trash Service – We will have a centralized are that will have dum psters. We will update as we determ ine that location.

slide-16
SLIDE 16

P r e p a r e - D e p l o y - E n a b l e

Resident/family Support

 Utilities  We are working with Conservice to determ ine the best

way to adjust to the im pacts.

 Garage Im pact Concession

 $40 0 one tim e check (one tim e paym ent in Septem ber)  Will be prorated for fam ilies that m ove our during that tim e.  If you occupy the hom e from and past the 15th of that m onth you

will receive the whole prorate for that m onth.  PCS Move Out Support

 Corvias/ HMO will Coordinate Move Out Dates With Construction

Schedule

slide-17
SLIDE 17

P r e p a r e - D e p l o y - E n a b l e

Contacts

 90 7-372-230 0 during business hours  90 7-372-230 2 after hours