LSST System Verification and Commissioning Chuck Claver System - - PowerPoint PPT Presentation

lsst system verification and commissioning chuck claver
SMART_READER_LITE
LIVE PREVIEW

LSST System Verification and Commissioning Chuck Claver System - - PowerPoint PPT Presentation

LSST System Verification and Commissioning Chuck Claver System Scientist & Commissioning Manager LSST2018 Project & Community Workshop Monday, August 13, 2018 #lsst2018 #lsst2018 LSST Project and Community Workshop 2018 Tucson


slide-1
SLIDE 1

1

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

LSST System Verification and Commissioning Chuck Claver System Scientist & Commissioning Manager LSST2018 Project & Community Workshop Monday, August 13, 2018

slide-2
SLIDE 2

2

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

LSST Project Schedule – 8.5 Months Contingency

Camera

Full Integration & Verification Operational Readiness Review Early Integration & Testing

Data Management Telescope & Site

+8.5 Construction Start Full System Integration “Start” Science Operations Start Now

Final DRP Release

Pre Commissioning Preparations

Facility Support

Full Operations

CD-4 Com Cam on Summit

Pre-

NSF MREFC DOE MIE Commissioning Operations Schedule Contingency

8 Dec 2017

MIE to Ops

Critical Path Engineering First Light System First Light

slide-3
SLIDE 3

3

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

Verification and Validation Process has Started

Design Build Integrate

We are here!

slide-4
SLIDE 4

4

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

Interface Verification is Underway

LSE-80 LSE-64 LSE-18

slide-5
SLIDE 5

5

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

Cam-Tel Utility Interface

slide-6
SLIDE 6

6

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

Telescope Top End & Utilities

Telescope Mount Assembly in Factory Acceptance Testing – completion scheduled for the end of September.

TMA-Camera utility interface

slide-7
SLIDE 7

7

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

  • Key activity of Phase 0: Pre-Commissioning
  • Involves interaction between all principal

subsystem control software

  • Mainly focused on software, but hardware

becoming involved

  • Performs interface testing
  • Designed to clarify and solidify those interfaces
  • Used to identify areas of deficiency and

address those issues

  • Exercises build on the work of previous ones
  • Test early, test often!
  • Reduces verification risk by doing early testing

Early Integration Activities

EIA Status Details – Physical & Functional Integration Breakout EIA Activities related to Auxiliary Telescope EIA Activities related to Main Camera

slide-8
SLIDE 8

8

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

  • 1 Visit Night with Images AuxTel
  • First test of Auxiliary Telescope APIs
  • Ran through AuxTel nominal visit cadence
  • Manual Control of Multiple Physical Devices AuxTel
  • First test of hardware control for monochromator

calibration

  • FITS File Assembly at NCSA
  • Test for correct image assembly for single CCD
  • MCM/OCS Bridge Integration Test
  • Control AuxTel Spectrograph sensor and Dewar to

produce images

  • Tests ACCS, AT Header Service and AT Archiver

Some Recently Completed Exercises

slide-9
SLIDE 9

9

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

ComCam is coming together

This image cannot currently be displayed. This image cannot currently be displayed.
  • Feb. 2019: ComCam Cyostat delivered to Tucson

Feb.-July 2019: ComCam Integration and Test

  • Aug. 2019: ComCam ready to ship
slide-10
SLIDE 10

10

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

Commissioning Team working with DM on SW Tooling

  • Tucson based weekly “Stack Club” + periodic

“boot camps” with DM, T&S and Commissioning.

  • Building experience and expertise with data

analysis tools

  • Scripted data analysis tooling with LSST SW Stack
  • Interactive image analysis tooling
  • Deployment of early Camera DAQ-CCS instances

for cross-subsystem integration tests

Automated scripted analysis through LSST Science Platform JupyterLab interface running at NCSA. Example is QA for galaxy identification. Interactive image analysis tooling

slide-11
SLIDE 11

11

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

LSST Science Platform Comes to Life!

Commissioning team developing procedures within LSST stack in LSP

slide-12
SLIDE 12

12

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

DM SQuaSH Extension for System Verification

slide-13
SLIDE 13

13

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

On-Sky Data Planning for Science Validation

Critical sky positions where some form of “truth” is known have been identified.

slide-14
SLIDE 14

14

LSST Project and Community Workshop 2018 • Tucson • August 13 - 17

#lsst2018

Early Operations Team will commit to supporting the following:

  • Images from a given commissioning phase will be released aftera 3-

months following that phase’s conclusion

  • Catalogs will be released 3-months thereafter

Principal Commissioning Phases Includes:

  • AuxTel Integration: March 2019
  • ComCam-Tel. Integration: July 2020
  • LSSTCam-Tel. Integration: September 2020
  • ComCam Sustained Observing: October 2020
  • LSSTCam Sustained Observing: July 2021
  • Operations Readiness mini-Surveys: September 2021

Commissioning Data Release Policy