lsst system verification and commissioning chuck claver
play

LSST System Verification and Commissioning Chuck Claver System - PowerPoint PPT Presentation

LSST System Verification and Commissioning Chuck Claver System Scientist & Commissioning Manager LSST2018 Project & Community Workshop Monday, August 13, 2018 #lsst2018 #lsst2018 LSST Project and Community Workshop 2018 Tucson


  1. LSST System Verification and Commissioning Chuck Claver System Scientist & Commissioning Manager LSST2018 Project & Community Workshop Monday, August 13, 2018 #lsst2018 #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 1

  2. LSST Project Schedule – 8.5 Months Contingency Data Management Final DRP Release Telescope & Site Facility Support Pre Commissioning Preparations Early Integration & Testing Com Cam on Summit Engineering First Light Camera MIE to Ops CD-4 NSF MREFC Full Integration & Verification System First Light +8.5 DOE MIE Schedule Contingency Operational Readiness Review Commissioning Full Operations Pre- Operations Construction Critical Path Full System Science Now Start Integration “Start” Operations Start 8 Dec 2017 #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 2

  3. Verification and Validation Process has Started We are here! Integrate Design Build #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 3

  4. Interface Verification is Underway LSE-80 LSE-64 LSE-18 #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 4

  5. Cam-Tel Utility Interface #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 5

  6. Telescope Top End & Utilities TMA - Camera utility interface Telescope Mount Assembly in Factory Acceptance Testing – completion scheduled for the end of September. #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 6

  7. Early Integration Activities EIA Activities related to Auxiliary Telescope - Key activity of Phase 0: Pre-Commissioning - Involves interaction between all principal subsystem control software Mainly focused on software, but hardware - becoming involved - Performs interface testing - Designed to clarify and solidify those interfaces - Used to identify areas of deficiency and EIA Activities related to Main Camera address those issues - Exercises build on the work of previous ones - Test early, test often! - Reduces verification risk by doing early testing EIA Status Details – Physical & Functional Integration Breakout #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 7

  8. Some Recently Completed Exercises - 1 Visit Night with Images AuxTel • First test of Auxiliary Telescope APIs • Ran through AuxTel nominal visit cadence - Manual Control of Multiple Physical Devices AuxTel First test of hardware control for monochromator • calibration - FITS File Assembly at NCSA • Test for correct image assembly for single CCD - MCM/OCS Bridge Integration Test • Control AuxTel Spectrograph sensor and Dewar to produce images • Tests ACCS, AT Header Service and AT Archiver #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 8

  9. ComCam is coming together This image cannot currently be displayed. This image cannot currently be displayed. Feb. 2019: ComCam Cyostat delivered to Tucson Feb. - July 2019: ComCam Integration and Test Aug. 2019: ComCam ready to ship #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 9

  10. Commissioning Team working with DM on SW Tooling Automated scripted analysis through LSST Science - Tucson based weekly “Stack Club” + periodic Platform JupyterLab interface running at NCSA. “boot camps” with DM, T&S and Commissioning. Example is QA for galaxy identification. - B uilding experience and expertise with data analysis tools - Scripted data analysis tooling with LSST SW Stack - Interactive image analysis tooling - Deployment of early Camera DAQ -CCS instances for cross - subsystem integration tests Interactive image analysis tooling #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 10

  11. LSST Science Platform Comes to Life! Commissioning t eam developing procedures within LSST stack in LSP #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 11

  12. DM SQuaSH Extension for System Verification #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 12

  13. On-Sky Data Planning for Science Validation Critical sky positions where some form of “truth” is known have been identified. #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 13

  14. Commissioning Data Release Policy Early Operations Team will commit to supporting the following: Images from a given commissioning phase will be released aftera 3 - - months following that phase’s conclusion Catalogs will be released 3 - months thereafter - Principal Commissioning Phases Includes: - AuxTel Integration: March 2019 - ComCam- Tel. Integration: July 2020 - LSSTCam- Tel. Integration: September 2020 - ComCam Sustained Observing: October 2020 - LSSTCam Sustained Observing: July 2021 - Operations Readiness mini- Surveys: September 2021 #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 14

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend