LITIGATING CLAIMS UNDER THE CONTRACT DISPUTES ACT
John G. DeGooyer Philip A. Nacke Steven C. Lambert November 2007
LITIGATING CLAIMS UNDER THE CONTRACT DISPUTES ACT U.S. Court of - - PowerPoint PPT Presentation
LITIGATING CLAIMS UNDER THE CONTRACT DISPUTES ACT U.S. Court of Federal Claims & Boards of Contract Appeals John G. DeGooyer Philip A. Nacke Steven C. Lambert November 2007 Overview Historical Background Contract Disputes Process
John G. DeGooyer Philip A. Nacke Steven C. Lambert November 2007
2
Historical Background Contract Disputes Process CDA Coverage Contractor Claim Submission Contracting Officer’s Decision Government Claims Appeal Forums Forum Selection Factors
3
Pre-Civil War situation Reforms during/post Civil War Development of disputes clauses Creation of Boards of Contract Appeals The Contract Disputes Act of 1978
Federal Courts Improvement Act of 1982
4
Federal Courts Improvement Act
Federal Acquisition Streamlining
5 Contractor or Government Claim Contracting Officer’s Final Decision Choose One No Appeal 90 Days BCA 120 Days 12 Months COFC 60 Days CAFC Writ of Certiorari U.S. Supreme Court
6
Applies to any express or implied contract
CDA does not apply to contracts for the
7
The non-appropriated fund
8
Board of Governors of the Federal
Federal Prison Industries, a wholly-owned
U.S. Mint, within the Treasury Department
9
CDA does not apply to the
10
Who may submit a CDA claim?
11
Written demand to the contracting
Seeking as a matter of right
Submitted for a final decision
12
Monetary claims in excess of $100,000 must
13
Interest Statute of limitations
14
Time limits
15
Uncertified and defectively certified
Failure to issue a final decision –
Finality of a written decision
16
Requirement for final decision No certification requirement Interest Finality
17
Article I court 16 judges, serving 15 year terms, and
No government contracts experience
World-wide jurisdiction Can tax costs and assess attorney fees Single judge decides the case
18
Goals: informal, quick, cheap Experienced judges Decisions by panels, but a single
19
Armed Services Board of Contract
20
Civilian Board of Contract Appeals
21
22
Contracting officer’s final decision Time for appeal
Complexity of case
23
COFC (exclusive of bid protests):
ASBCA:
24
COFC (exclusive of bid protests)
ASBCA
25
Selection of forum is usually binding
26
Research binding authority
Research forum decisions
27
COFC
Boards
28
COFC – Department of Justice
Boards – Agency counsel
29
COFC and Boards both encourage ADR
30
Pretrial Discovery Motions Trials Decisions
31
41 U.S.C. § 604
32
28 U.S.C. § 2514
Civil False Claims Act (31 U.S.C. §
33
COFC can apply each of the foregoing
BCAs have no jurisdiction under the
34
Implications for “split” contractor
35
COFC
Law – De novo Facts – Final unless clearly erroneous
36
Boards
Law – De novo Facts – Final unless fraudulent, arbitrary,