LITIGATING CLAIMS UNDER THE CONTRACT DISPUTES ACT U.S. Court of - - PowerPoint PPT Presentation

litigating claims under the contract disputes act
SMART_READER_LITE
LIVE PREVIEW

LITIGATING CLAIMS UNDER THE CONTRACT DISPUTES ACT U.S. Court of - - PowerPoint PPT Presentation

LITIGATING CLAIMS UNDER THE CONTRACT DISPUTES ACT U.S. Court of Federal Claims & Boards of Contract Appeals John G. DeGooyer Philip A. Nacke Steven C. Lambert November 2007 Overview Historical Background Contract Disputes Process


slide-1
SLIDE 1

LITIGATING CLAIMS UNDER THE CONTRACT DISPUTES ACT

John G. DeGooyer Philip A. Nacke Steven C. Lambert November 2007

U.S. Court of Federal Claims & Boards of Contract Appeals

slide-2
SLIDE 2

2

Overview

Historical Background Contract Disputes Process CDA Coverage Contractor Claim Submission Contracting Officer’s Decision Government Claims Appeal Forums Forum Selection Factors

slide-3
SLIDE 3

3

Historical Background

Pre-Civil War situation Reforms during/post Civil War Development of disputes clauses Creation of Boards of Contract Appeals The Contract Disputes Act of 1978

– (41 U.S.C. §§ 601-13)

Federal Courts Improvement Act of 1982

slide-4
SLIDE 4

4

Historical Background (Cont’d.)

Federal Courts Improvement Act

  • f 1992

Federal Acquisition Streamlining

Act of 1994

slide-5
SLIDE 5

5 Contractor or Government Claim Contracting Officer’s Final Decision Choose One No Appeal 90 Days BCA 120 Days 12 Months COFC 60 Days CAFC Writ of Certiorari U.S. Supreme Court

Contract Disputes Process

slide-6
SLIDE 6

6

CDA Coverage

Applies to any express or implied contract

entered into by an “executive agency” for

– The procurement of property, other than real property in being – The procurement of services – The procurement of construction, alteration, repair or maintenance of real property – The disposal of personal property

CDA does not apply to contracts for the

Government to provide services

slide-7
SLIDE 7

7

CDA Coverage (Cont’d.)

The non-appropriated fund

instrumentality (NAFI):

– CDA applies to contracts of those NAFIs identified in 28 U.S.C. § 1491. These are the so-called exchange services: Army and Air Force Exchange Service, Navy Exchanges, Marine Corps Exchanges, etc. – CDA does not apply to the contracts of lower tier military NAFIs, such as individual morale and recreation funds

slide-8
SLIDE 8

8

CDA Coverage (Cont’d.)

– CDA does not apply to the contracts of executive agencies that operate without the use of appropriated funds. For example:

Board of Governors of the Federal

Reserve System

Federal Prison Industries, a wholly-owned

government corporation within the Federal Bureau of Prisons which in turn is within the Department of Justice

U.S. Mint, within the Treasury Department

slide-9
SLIDE 9

9

CDA Coverage (Cont’d.)

CDA does not apply to the

contracts of the Federal Aviation Administration

slide-10
SLIDE 10

10

Contractor Claim Submission

Who may submit a CDA claim?

–The prime contractor – yes –Subcontractors – not directly –Sureties – no

slide-11
SLIDE 11

11

Contractor Claim Submission (Cont’d.)

Basics Of A Claim

Written demand to the contracting

  • fficer

Seeking as a matter of right

– Payment of money in a sum certain, – Adjustment or interpretation of contract term, or – Other relief arising under or relating to a contract

Submitted for a final decision

slide-12
SLIDE 12

12

Contractor Claim Submission (Cont’d.)

Monetary claims in excess of $100,000 must

be certified

– Claim is made in good faith – Supporting data are accurate and complete to the best of the contractor’s knowledge and belief – Amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable – Person submitting the claim is duly authorized to certify the claim on the contractor’s behalf

slide-13
SLIDE 13

13

Contractor Claim Submission (Cont’d.)

Interest Statute of limitations

slide-14
SLIDE 14

14

Contracting Officer’s Decision

Time limits

–Due within 60 days, or –If involving a certified claim in excess

  • f $100,000 within 60 days the

contracting officer must notify the contractor of a firm date by which a final decision will be issued

slide-15
SLIDE 15

15

Contracting Officer’s Decision (Cont’d.)

Uncertified and defectively certified

claims exceeding $100,000

Failure to issue a final decision –

deemed denial

Finality of a written decision

slide-16
SLIDE 16

16

Government Claims

Requirement for final decision No certification requirement Interest Finality

slide-17
SLIDE 17

17

Appeal Forums

Court of Federal Claims

Article I court 16 judges, serving 15 year terms, and

an additional 10 active senior judges

No government contracts experience

needed

World-wide jurisdiction Can tax costs and assess attorney fees Single judge decides the case

slide-18
SLIDE 18

18

Appeal Forums (Cont’d.)

Boards of Contract Appeals

Goals: informal, quick, cheap Experienced judges Decisions by panels, but a single

judge takes the evidence

slide-19
SLIDE 19

19

Appeal Forums (Cont’d.)

Boards of Contract Appeals (Cont.)

Armed Services Board of Contract

Appeals (ASBCA)

–Jurisdiction over DoD and NASA CDA contracts –All other jurisdiction (e.g., HHS, AID) eliminated effective January 6, 2007 –17 members

slide-20
SLIDE 20

20

Appeal Forums (Cont’d.)

Boards of Contract Appeals (Cont’d.)

Civilian Board of Contract Appeals

(CBCA)

– Operational January 6, 2007 – Consolidated eight pre-existing civilian boards, the most active of which was the General Services Administration Board of Contract Appeals (GSBCA)

slide-21
SLIDE 21

21

Appeal Forums (Cont’d.)

Boards of Contract Appeals (Cont’d.)

– CBCA has jurisdiction over all civilian agency CDA contracts other than those of the Postal Service and the Tennessee Valley Authority – 18 members (6 coming from GSBCA)

slide-22
SLIDE 22

22

Forum Selection Factors

Jurisdiction – COFC and Boards

Contracting officer’s final decision Time for appeal

– COFC – 12 months after receipt of decision – Board – 90 days after receipt of decision

Complexity of case

– Need for considerable preparation time may suggest appeal to COFC rather than Board

slide-23
SLIDE 23

23

Forum Selection Factors (Cont’d.)

Workload – Contract Actions Filed

COFC (exclusive of bid protests):

– 1997-2006: 275 cases/year; 37% of docket – 2004-2006: 382 cases/year; 41% of docket

ASBCA:

– 2002-2005: 450 cases/year

slide-24
SLIDE 24

24

Forum Selection Factors (Cont’d.)

Length of Process – Complaint to Decision

COFC (exclusive of bid protests)

– 1997-2006: 2 years, 8 months – 2004-2006: 3 years

ASBCA

– 2002-2005: 1 year, 4 months

slide-25
SLIDE 25

25

Forum Selection Factors (Cont’d.)

Election Doctrine

Selection of forum is usually binding

– Cannot dismiss and refile in other forum – Selection is binding even if claim is not properly certified – But if selected forum lacks jurisdiction (e.g., appeal to Board more than 90 days after receipt of final decision), election is not binding

slide-26
SLIDE 26

26

Forum Selection Factors (Cont’d.)

Legal Issues – Governing Precedent

Research binding authority

– Federal Circuit and Court of Claims – U.S. Supreme Court

Research forum decisions

– Technical government contract issues may suggest selecting Board rather than COFC

slide-27
SLIDE 27

27

Forum Selection Factors (Cont’d.)

Need For Legal Counsel

COFC

– Representation by an attorney is required – Pro se representation limited

Boards

– Contractors may appear pro se

slide-28
SLIDE 28

28

Forum Selection Factors (Cont’d.)

Different Government Counsel

COFC – Department of Justice

– Parties lose settlement flexibility – But fresh look by DoJ may facilitate settlement

Boards – Agency counsel

– Parties retain some settlement flexibility – But positions may be entrenched, impairing settlement possibilities

slide-29
SLIDE 29

29

Forum Selection Factors (Cont’d.)

Alternate Dispute Resolution

COFC and Boards both encourage ADR

– Voluntary process – Many forms of ADR available

slide-30
SLIDE 30

30

Forum Selection Factors (Cont’d.)

Litigation Procedures – COFC and Boards

Pretrial Discovery Motions Trials Decisions

slide-31
SLIDE 31

31

Forum Selection Factors (Cont’d.)

Forfeiture of Claims and Other Government Remedies For Fraudulent Claims

41 U.S.C. § 604

– Liability for the unsupported part of a claim attributed to misrepresentation of fact or fraud, in addition to the cost to the Government of reviewing that part of the claim – Can be applied by the COFC

slide-32
SLIDE 32

32

Forum Selection Factors (Cont’d.)

28 U.S.C. § 2514

– Forfeiture in toto of claims made by those who commit or attempt to commit fraud in connection with any part of the claim – Can be applied by the COFC – Application ranges far beyond the literal words of the statute

Civil False Claims Act (31 U.S.C. §

3729 et seq.)

slide-33
SLIDE 33

33

Forum Selection Factors (Cont’d.)

COFC can apply each of the foregoing

statutes in a case before it, if fraud is found

BCAs have no jurisdiction under the

CDA over fraud issues. The government must move to stay the action pending decision in a government-initiated district court action

slide-34
SLIDE 34

34

Forum Selection Factors (Cont’d.)

Implications for “split” contractor

claims: transfer of Board proceedings to the COFC and consolidation with the case pending there

slide-35
SLIDE 35

35

Forum Selection Factors (Cont’d.)

Appellate Review

COFC

– Appeal to Federal Circuit – Appeal within 60 days after entry of judgment – Standard of review

Law – De novo Facts – Final unless clearly erroneous

slide-36
SLIDE 36

36

Forum Selection Factors (Cont’d.)

Appellate Review (Cont’d.)

Boards

– Appeal to Federal Circuit – Appeal within 120 days after receipt of adverse Board decision – Standard of review

Law – De novo Facts – Final unless fraudulent, arbitrary,

capricious, grossly erroneous or not supported by substantial evidence