LHC Collimation Project Status Stefano Redaelli, CERN, BE-ABP for - - PowerPoint PPT Presentation

lhc collimation project status
SMART_READER_LITE
LIVE PREVIEW

LHC Collimation Project Status Stefano Redaelli, CERN, BE-ABP for - - PowerPoint PPT Presentation

20 th US-LARP Collaboration Meeting - CM20 April 8 th -10 th , 2013 Embassy Suites - Napa Valley, CA, USA LHC Collimation Project Status Stefano Redaelli, CERN, BE-ABP for the Collimation Project and HL-LHC-WP5 teams The HiLumi LHC Design


slide-1
SLIDE 1

Stefano Redaelli, CERN, BE-ABP for the Collimation Project and HL-LHC-WP5 teams

LHC Collimation Project Status

20th US-LARP Collaboration Meeting - CM20 April 8th-10th, 2013 Embassy Suites - Napa Valley, CA, USA

The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404.
slide-2
SLIDE 2
  • S. Redaelli, US-LARP CM20 08/04/2013

Introduction

2

Baseline collimation upgrade strategy for LS1 defined in 2011

  • Decided to postpone major changes in the dispersion suppressors (DSs)
  • Other important upgrades will take place in LS1: Collimators with BPM design

The good performance at 4 TeV (up to 140 MJ!) confirmed this strategy, but uncertainties remain for the extrapolations to 7 TeV

  • Need to review cleaning, lifetime assumptions, quench limits, impedance...

The possible needs for local collimation in the dispersion suppressor have steered the development of the 11 T dipoles

  • Important progress - see magnet talks. Can we get them in LS2 if needed?
  • What do we need to decide now to be ready to take a decision in 2015?

External collimation review is being organized: 30-31/05/2013

  • Scope: present the baseline on collimation upgrades on mid and long term:

(1) Full beam intensity and luminosity; (2) x2 design; (3) HL-LHC.

  • Mandate: advice on 11 T dipole strategy until post-LS1 operation, for actions in LS2.

Other important studies for collimation upgrades are ongoing, within and outside CERN, to ensure readiness for HL-LHC era!

slide-3
SLIDE 3
  • S. Redaelli, US-LARP CM20 08/04/2013

Outline

3

Introduction Collimation up to 140 MJ News on upgrade studies Conclusions

slide-4
SLIDE 4
  • S. Redaelli, US-LARP CM20 08/04/2013

(Some) collimation people

4
slide-5
SLIDE 5
  • S. Redaelli, US-LARP CM20 08/04/2013

Contributions for this talk

5
  • B. Salvachua (2012-13 performance)
  • R. Bruce (post-LS1 performance)
  • G. Stancari, A. Valishev, W. Fisher (hollow e-lens)
  • N. Simos, A. Bertarelli, N. Mariani, L. Lari (BNL radiation tests)
  • A. Bertarelli et al. (collimator material studies)
  • M. Sapinski (non-collimation quench tests)
  • W. Scandale, D. Mirarchi (crystal studies)
  • O. Bruning, L. Rossi, H. Schmickler (overall strategy within HL-LHC)

Core collimation team in the LHC accelerator physics group:

  • R. Bruce, M. Cauchi, D. Deboy, L. Lari, D. Mirarchi, E. Quaranta,
  • M. Salvachua, A. Rossi, A. Marsili, G. Valentino.

Members who left recently: R. Assmann, D. Wollmann. Acknowledgements: OP team, ADT team and many others.

slide-6
SLIDE 6
  • S. Redaelli, US-LARP CM20 08/04/2013

2012-13: “tight” collimator settings (TCP gaps as at 7 TeV!) for higher β*: 60 cm for protons, 80cm for ions.

Collimation cleaning at 4 TeV (β*=60cm)

6

Off-momentum Dump TCTs TCTs TCTs TCTs Betatron

1/10000

0.00001 0.000001

Beam 1

Highest COLD loss location: efficiency of > 99.99% ! Most of the ring actually > 99.999%

  • B. Salvachua

Cleaning inefficiency [BLM/BLMtcp]

BLMi BLMtcp

Cleaning defined here as:

slide-7
SLIDE 7
  • S. Redaelli, US-LARP CM20 08/04/2013

How “tight” tight settings are?

7

“Tight” collimator settings in the betatron cleaning (IR7):

  • Primary collimator gaps are the nominal as at 7 TeV!
  • Secondary collimator retracted by 2 sigmas (σ4TeV).
  • Tertiary collimators at 9 sigma for a β* of 60 cm!
2 4 6 8 1 2 3 4 5 6 7 N Collimator full gap [ mm ] 2 4 6 8 5 10 15 20 25 N Collimator full gap [ mm ]

±1.05 mm from the 140 MJ beam (4 TeV)!

2011

± 1.5 mm from the 110 MJ beam (3.5TeV)!

2012

slide-8
SLIDE 8
  • S. Redaelli, US-LARP CM20 08/04/2013

Loss maps in IR7

8

1/10000

  • B. Salvachua

Critical locations (both beams): losses in the dispersion suppressor magnets Q7-Q11, from single diffractive interactions at the primary collimators.

Beam 1

slide-9
SLIDE 9
  • S. Redaelli, US-LARP CM20 08/04/2013

Stability of cleaning in 2010-12

9 18/06/10 28/07/10 11/08/10 27/08/10 04/10/10 18/10/10 11/03/11 04/04/11 12/04/11 MD nominal MD tight 15/05/11 24/06/11 13/07/11 05/09/11 22/10/11 29/03/12 31/03/12 02/04/12 30/04/12 30/04/12 MD nominal MD nominal RC 01/07/12 01/07/12 01/07/12 11/07/12 16/07/12 16/07/12 16/07/12 23/11/12 23/11/12

Cleaning inefficiency

  • 5

10

  • 4

10

  • 3

10

B1 HOR B1 VER B2 HOR B2 VER

2010-2012 Collimation Cleaning Performance

2010 2011 2012

tight settings MD nominal settings MD nominal settings MD 4 TeV, “tight” 3.5 TeV, “relaxed”

Excellent stability of cleaning performance observed! Achieved with only 1 alignment per year in IR3/6/7 (2x30 collimators). New alignments are only repeated for new physics configurations (it remains crucial to be efficient!)

  • B. Salvachua
MAY 2010 MAR 2011 MAR 2012 MAY 2012 MD OCT 2012 MD 5 10 15 20 Setup Time per Collimator [min] Collimator Alignments

Setup time per collimator (2010-2012)

Plotted: cleaning at the worse cold location versus time

3.5 TeV, “relaxed”

slide-10
SLIDE 10
  • S. Redaelli, US-LARP CM20 08/04/2013

Stability of cleaning in 2010-12

10 18/06/10 28/07/10 11/08/10 27/08/10 04/10/10 18/10/10 11/03/11 04/04/11 12/04/11 MD nominal MD tight 15/05/11 24/06/11 13/07/11 05/09/11 22/10/11 29/03/12 31/03/12 02/04/12 30/04/12 30/04/12 MD nominal MD nominal RC 01/07/12 01/07/12 01/07/12 11/07/12 16/07/12 16/07/12 16/07/12 23/11/12 23/11/12

Cleaning inefficiency

  • 5

10

  • 4

10

  • 3

10

B1 HOR B1 VER B2 HOR B2 VER

2010-2012 Collimation Cleaning Performance

2010 2011 2012

tight settings MD nominal settings MD nominal settings MD 4 TeV, “tight” 3.5 TeV, “relaxed”

Excellent stability of cleaning performance observed! Achieved with only 1 alignment per year in IR3/6/7 (2x30 collimators). New alignments are only repeated for new physics configurations (it remains crucial to be efficient!)

  • B. Salvachua
MAY 2010 MAR 2011 MAR 2012 MAY 2012 MD OCT 2012 MD 5 10 15 20 Setup Time per Collimator [min] Collimator Alignments

Setup time per collimator (2010-2012)

Plotted: cleaning at the worse cold location versus time

3.5 TeV, “relaxed”

Collimation cleaning not enough to define the LHC performance: beam lifetime and quench limits at 7 TeV must be considered.

slide-11
SLIDE 11
  • S. Redaelli, US-LARP CM20 08/04/2013

LHC quench tests with beam

11

ns-losses for Ebeam>4 TeV (async.beam dump)

6 TeV

UFO-timescale losses Steady-state with orbital bump

20 mW/cc
  • Recap. on the LHC beam loss monitoring system:
  • Beam losses are monitored over 12 “running sums” (RS), from 40μs (1/2 turn) to 80s.
  • Independent thresholds for each RS to protect the machine from ultra-fast to steady-state losses.

Five quench tests were proposed at the end of the 2012-13 run to probe different time scales:

  • Collimator test with protons
  • Collimator test with ions (not done due to unavailability of ion beams)
  • Orbital bumps
  • Fast losses on UFO range
  • Single-pass with injected beam
  • M. Sapinski for the Quench
Strategy Working Group

Steady-state dispersion suppressor with protons Steady-state dispersion suppressor with ions (not done!)

Truly impressive amount

  • f work done by MANY

teams involved. Dedicate WG started to consistently address all the experimental results.

slide-12
SLIDE 12
  • S. Redaelli, US-LARP CM20 08/04/2013

Collimator proton quench tests

12

s [m]

19400 19600 19800 20000 20200 20400 20600

BLM signal [Gy/s]

  • 7

10

  • 6

10

  • 5

10

  • 4

10

  • 3

10

  • 2

10

  • 1

10 1 10

2

10

cold collimator warm

Losses Fill_3569 B1_B2 4000GeV 2013-02-15 03:15:03

1.06 MW

  • n TCPʼs

1 kW at Q8

  • B. Salvachua

Achieved by blowing up the beam with damper excitation

Controlled beam excitation over several seconds: Peak losses > 1MW on TCP! Worsened cleaning by relaxing collimator settings (“very relaxed”). Achieved 2 to 5 times the assumed quench limit at 4.0 TeV without quenching! (2011: only achieved ~65% of 3.5 TeV limit.)

Preliminary analysis of beam tests done on 14/02/2013

slide-13
SLIDE 13
  • S. Redaelli, US-LARP CM20 08/04/2013

Collimator proton quench tests

13

s [m]

19400 19600 19800 20000 20200 20400 20600

BLM signal [Gy/s]

  • 7

10

  • 6

10

  • 5

10

  • 4

10

  • 3

10

  • 2

10

  • 1

10 1 10

2

10

cold collimator warm

Losses Fill_3569 B1_B2 4000GeV 2013-02-15 03:15:03

1.06 MW

  • n TCPʼs

1 kW at Q8

  • B. Salvachua

Achieved by blowing up the beam with damper excitation

Controlled beam excitation over several seconds: Peak losses > 1MW on TCP! Worsened cleaning by relaxing collimator settings (“very relaxed”). Achieved 2 to 5 times the assumed quench limit at 4.0 TeV without quenching! (2011: only achieved ~65% of 3.5 TeV limit.)

Preliminary analysis of beam tests done on 14/02/2013

slide-14
SLIDE 14
  • S. Redaelli, US-LARP CM20 08/04/2013

Achieved losses vs quench limit

14

New method to excite controlled blow-up with the transverse damper (ADT): could probes “steady” losses between 1.3s and 5.2s! Achieved loss rate a factor 2-5 larger than the assumed quench limits!

Remark: We have seen this type of losses during 2012! Collimator BLMs are set to dump beams in case of losses > 200kW)!

  • B. Salvachua

RS09 = 1.3 s 1.3 s RS10 = 5.2 s 5.2 s Ramp 3: ~1MW BLM Measurement [Gy/] Assumed Quench Limit [Gy/s] Ratio BLM to Quench Limit BLM Measurement [Gy/] Assumed Quench Limit [Gy/s] Ratio BLM to Quench Limit BLMQI.08L7.B2I10_MQ 1.08E-02 4.65E-03

2.3

8.42E-03 1.67E-03 5.1 BLMQI.08L7.B2I20_MQ 3.81E-03 6.40E-03 0.6 2.87E-03 2.29E-03 1.3

2011 (3.5TeV) 2012 (4 TeV)

slide-15
SLIDE 15
  • S. Redaelli, US-LARP CM20 08/04/2013

Ongoing work for review

15

Ntot = τRq ˜ ηc

Minimum (assumed) beam lifetime Quench limit of SC magnets Collimation cleaning at limiting cold location

LHC total intensity reach from collimation

(Some) items being addressed: Tracking + energy deposition simulations of quench test conditions.

  • Understand in detail the energy deposited in SC coils.

Refined beam lifetime analysis and dump statistics. Ion cleaning: effect of cryo collimator of DS in IR2 (no more details here).

  • Efficiency of DS collimator in IR2 and parametric study (length, material).
  • Review IR7 performance reach in light of new quench tests.

LHC impedance limitations: trade off between settings, instabilities and beta*.

slide-16
SLIDE 16
  • S. Redaelli, US-LARP CM20 08/04/2013

Tentative agenda of collimation review

16

Dates frozen: 30-31 May 2013 Introduction to present collimation system Sources of performance limitation:

  • Lifetime and cleaning efficiency
  • Quench margin from beam measurements (with energy deposition studies)
  • Quench form magnet studies
  • Impedance

Estimated performance reach (including beta star) DS collimation (in collision points and cleaning insertions):

  • 11 T dipole status: what do we need to be ready in LS2
  • Scenarii for heat loads (protons and ions)
  • Technology choice and integration issues

HL-LHC challenges for collimation:

  • Cleaning with ATS optics and needs for DS collimation in LS3

Perspective of hollow lens Status of Crystal New collimator materials (impedance vs robustness) Lifetime of collimator hardware and radiation handling Wrap-up and outline a consistent strategy for LS2 and LS3

slide-17
SLIDE 17
  • S. Redaelli, US-LARP CM20 08/04/2013

Outline

17

Introduction Collimation up to 140 MJ News on upgrade studies Conclusions

slide-18
SLIDE 18
  • S. Redaelli, US-LARP CM20 08/04/2013

Collimator robustness at HRM

18

!"#$%&% !"#$%'% !"#$%(%

! !"#$%"&"'()*% !!"#$%&# ! +$,#-.%/",.0*% '((# ! 1#23%0#456(#,*% )!#((#

*%+,#)# *%+,#'# *%+,#-# $./0# 1%/(#2(3/4,#%5627/0%8,#,.# #)#9:;#<684=#>#?*%&# @A%8,2BC#.8+%,#.B#30/+,24# A/(/D%# @8A64%#+%7%E%#A/(/D%#.8#,=%# 4.002(/,.E#F/G# @(3/4,#0.4/,2.8# 7"5.%8#29%:,%;<=>%$$?% 7"5.%8#29%/@2&%;6ABC%$$?% DE(0.%8#29%/@2&%;6ABC%$$?% H60+%#28,%8+2,C#I3J# CBCF%G%=>=H% =B>I%G%=>=H% JBCI%G%=>=H% K6(<%E#.B#<684=%+# HI% F% KH% 1684=#+3/428D#I8+J# L>% L>% L>% 1%/(#+2L%## I!M#N#!C#((J# >BLC%G%>BCF% >BLC%G%>BCF% >BLC%G%>BCF%

Address by beam tests the robustness of the TCT (critical for β* reach). Complementary dedicated material tests to find “ideal” collimator materials.

  • A. Bertarelli, et al

Sketch of TCT collimator

slide-19
SLIDE 19
  • S. Redaelli, US-LARP CM20 08/04/2013

Collimator robustness at HRM

19

!"#$%&% !"#$%'% !"#$%(%

! !"#$%"&"'()*% !!"#$%&# ! +$,#-.%/",.0*% '((# ! 1#23%0#456(#,*% )!#((#

*%+,#)# *%+,#'# *%+,#-# $./0# 1%/(#2(3/4,#%5627/0%8,#,.# #)#9:;#<684=#>#?*%&# @A%8,2BC#.8+%,#.B#30/+,24# A/(/D%# @8A64%#+%7%E%#A/(/D%#.8#,=%# 4.002(/,.E#F/G# @(3/4,#0.4/,2.8# 7"5.%8#29%:,%;<=>%$$?% 7"5.%8#29%/@2&%;6ABC%$$?% DE(0.%8#29%/@2&%;6ABC%$$?% H60+%#28,%8+2,C#I3J# CBCF%G%=>=H% =B>I%G%=>=H% JBCI%G%=>=H% K6(<%E#.B#<684=%+# HI% F% KH% 1684=#+3/428D#I8+J# L>% L>% L>% 1%/(#+2L%## I!M#N#!C#((J# >BLC%G%>BCF% >BLC%G%>BCF% >BLC%G%>BCF%

!"#$%&% '&%()*%+,-./%0%1!"23% !"#$%4% '5-#"$%67%89:9;"3% !"#$%<% '14%=>=%+,-./"#3%

Address by beam tests the robustness of the TCT (critical for β* reach). Complementary dedicated material tests to find “ideal” collimator materials.

!"# !"##$%&'%()'*&& +&,&-.& /0%-*%1&2&3"4).%5*6&
  • A. Bertarelli, et al

Sketch of TCT collimator

slide-20
SLIDE 20
  • S. Redaelli, US-LARP CM20 08/04/2013

Updated robustness limits

20

!"#$%#&'()*+',-'./"01#2' 3456.7#"/%+',-'8'(99'./"01#2' :5;704<+',-'./"01#2'=-'>?'' @4<<#$AB;C%4"7' (99'./"01#2'' 3456.7#"/%A@4<<#$AB;C%4"7' (99'./"01#2'' 3456.7#"/%A:$C<1;&#'=D'E$C7#2?'' (99'./"01#2''

  • A. Bertarelli:

MP workshop 2013 Recent ATS seminar

Challenge for the collimator commissioning at 7 TeV that required a few nominal bunches for collision and orbit setup! Need follow up! Studied alternative materials for future collimator jaws!

slide-21
SLIDE 21
  • S. Redaelli, US-LARP CM20 08/04/2013

Material properties under high doses

21

Fast loss studies at HRM address robustness against failure scenario, with impact on β* reach. We work with high priority on understanding the material behaviour under high irradiation doses! Collaboration with Russia (Kurchatov) and USA (BNL within LARP): testing a panel of 6 new materials. Thanks a lot to the US-LARP friends for supporting this new study proposed in 2012! Supported also by EuCARD + EuCARD2. Key issues: Variation of dimensions (swelling)

  • Change of thermo-mechanical
  • properties (increased impedance!)
  • A. Ryazanov, Kurchatov
slide-22
SLIDE 22
  • S. Redaelli, US-LARP CM20 08/04/2013

New material studies at BNL

22

Proposal brought forward at the CM18 a Fermilab (Apr. 2012). Approved by US-LARP: endorsement at the Frascati meeting in Nov. (when basic program and goals were presented). Complements and extends important studies ongoing at Kurchatov.

Not possible to give many details here - just brief status.

slide-23
SLIDE 23
  • S. Redaelli, US-LARP CM20 08/04/2013

Status of BNL irradiation tests

23

Following the US-LARP support announced at the Frascati meeting in Nov., much progress has been made: Defined materials and optimum sample shapes. Ordered new materials; soon to be shipped to BNL. Energy deposition and structural analysis. Presentation to the safety committee at BNL

  • Experiment Safety Review meeting of 27/03/2013

Metallic ¡materials ¡samples: ¡ Molybdenum ¡+ ¡Glidcop Other Tensile ¡tests Composite ¡materials ¡samples: ¡ CuCD ¡+ ¡MoGRCF Parallelepiped ¡shape ¡for ¡all ¡tests

4.00+/-0.05
  • N. Mariani, EN-MME
  • L. Lari,

BE-ABP

We are expecting that the tests will take place during this yearʼs RHIC run!

slide-24
SLIDE 24
  • S. Redaelli, US-LARP CM20 08/04/2013

Status of BNL irradiation tests

24

Following the US-LARP support announced at the Frascati meeting in Nov., much progress has been made: Defined materials and optimum sample shapes. Ordered new materials; soon to be shipped to BNL. Energy deposition and structural analysis. Presentation to the safety committee at BNL

  • Experiment Safety Review meeting of 27/03/2013

Metallic ¡materials ¡samples: ¡ Molybdenum ¡+ ¡Glidcop Other Tensile ¡tests Composite ¡materials ¡samples: ¡ CuCD ¡+ ¡MoGRCF Parallelepiped ¡shape ¡for ¡all ¡tests

4.00+/-0.05
  • N. Mariani, EN-MME
  • L. Lari,

BE-ABP

We are expecting that the tests will take place during this yearʼs RHIC run!

slide-25
SLIDE 25
  • S. Redaelli, US-LARP CM20 08/04/2013

Tevatron hollow e-lens for the LHC

25

Timeline for the definition of a CERN strategy for the usage of TEL2. CERN review in Nov. 2012

  • Brought up comprehensively technical aspects for installation in LHC or SPS.

HiLumi annual meeting in Frascati, end of Nov. 2012

  • CERN iterated the strong interest to pursue this option for HL-LHC.
  • Promised a response to US-LARP request on TEL2 usage by spring 2013.
  • Jan. 2013
  • CERN internal executive meeting with directorate to propose a
  • strategy base on the technical input of the the review.

April 8th

  • Presentation to HL-LHC technical committee and proposal of working plan.

April 2013

  • Present CERN strategy to US-LARP CM20 to steer their contribution.

End of may 2013

  • More technical details at the collimation review: putting together lifetime
  • analysis and results of quench tests.

See talk by Valentina P. for technical details

slide-26
SLIDE 26
  • S. Redaelli, US-LARP CM20 08/04/2013

Hollow e-lens review outcome

26

Very positive outcome for the review: a lot of support/interest within CERN for this topic! This message was passed on to LARP at Frascatiʼs meeting in Nov. There are very convincing indications that the LHC could profit from the scraping functionality. The excellent Tevatron results indicate that hollow e-beams could provide this functionality (Do we really need new tests?) But cannot state now that without scraping the LHC performance will be limited!

  • The final answer must wait until the first operational experience at ~7 TeV

The upgraded “TEL2” hardware is appropriate for the LHC and for beam tests at the SPS. However, the required time for an implementation in the LHC is 4-5 months (driven by cryogenics works in IP4). SPS estimates to be finalized. 1 technical concern: effect on beam core emittance from hollow e-beam “edge”. Alternative methods for active beam scraping must be studied with high priority. Presently, lacking alternatives solidly proved by beam tests.

  • If there are problems in 2015, the available single device will not help
  • Several options on the table: narrow damper excitation (see Wolfgang H. talk); tune
  • modulation by rippling quadrupole currents; beam wire compensators; scraping with TCPʼs.

Strong message on the need to improve halo diagnostics! See Gianluigiʼs A. talk.

slide-27
SLIDE 27
  • S. Redaelli, US-LARP CM20 08/04/2013

CERN strategy

27

Taking into account the present financial situation and the manpower commitment to the LS1 activities, CERN cannot decide now on the installation of the available Tevatron hardware in the SPS or the LHC. This also takes into account that firm indications of LHC critical performance limitations without scraping, can only become apparent after some operational experience at energies near to 7 TeV. The CERN management fully supports the studies on hollow e-lens and strongly recommends to focus the presently available resources towards the preparation of a possible production of 2 hollow e-lens for the LHC. Design of a device optimized for the LHC at 7 TeV (improve integration into the LHC infrastructure and improve instrumentation). Actively participate to beam tests worldwide on this topic. Specifically, CERN endorses the setup of hollow e-beam tests in RHIC. Start building competence at CERN on the hollow e-beam hardware. Continue working on alternative methods for halo scraping. Work with very high priority on improving the halo diagnostic at the LHC.

slide-28
SLIDE 28
  • S. Redaelli, US-LARP CM20 08/04/2013

Synergies with US-LARP

28

(Based on discussions with G. Stancari, A. Valishev, W. Fisher, H. Schmickler, et al.)

FNAL is interested to work on an optimum conceptual design for the LHC:

  • Time structure of beam; Improved instrumentation; Improved impedance; Better

integration in LHC cryo system; reduced impedance.

  • First specifications in the next 6 months, to be followed by detailed design.
  • Continue measurements to characterize new gun for the LHC parameters.

At CERN, we established links to achieve a design report by the end of 2014

  • Main links from collimation (S. Redaelli), instrumentation (R. Jones) and
  • engineering design team (F. Bertinelli) to follow up a detailed design.

FNAL is interested to continue simulation and theoretical works for hollow e- lens as well as for alternative methods!

  • First priority: model the effect of hollow beam “edges” on beam core emittance.
  • Continue joint effort on diffusion measurement and modelling.
  • Study alternative methods: effect on beam tails/core from tune modulation.

CERN link from collimation aspects for alternative scraping: R. Bruce

  • ADT narrow-band excitation -> see talk tomorrow by W. Höfle.

We would like profit from the RHIC e-lens setup to make more beam tests

  • Interest from RHIC side to work on that - see talk by Wolfram F.
  • Tests are subject to their successful commissioning for the RHIC p run!
  • Possibility to change the gun to get hollow beams (limited resources needed).
  • Primary goal: verify with beam effect on beam core from beam “edge”.

The EPFL in Lausanne (L. Rivkin) is interested in participating to this study!

slide-29
SLIDE 29
  • S. Redaelli, US-LARP CM20 08/04/2013

LHC crystal collimation studies

29

Slide presented at the CM18; More details at Frascati (D. Mirarchi)

slide-30
SLIDE 30
  • S. Redaelli, US-LARP CM20 08/04/2013

LHC crystal collimation studies

30

Slide presented at the CM18; More details at Frascati (D. Mirarchi) New measurements in 2012:

  • Cleaning around the ring with higher beam intensities.
  • More detailed measurements for proton and ions
slide-31
SLIDE 31
  • S. Redaelli, US-LARP CM20 08/04/2013

LHC crystal collimation studies

31

Slide presented at the CM18; More details at Frascati (D. Mirarchi) New measurements in 2012:

  • Cleaning around the ring with higher beam intensities.
  • More detailed measurements for proton and ions

Status for the LHC studies:

  • Following the endorsement of the LHCC (Sep. 2011),

the installation into the LHC was accepted by the CERN directorate.

  • Request of works for the crystal experiment was

approved and is presently in the LS1 work plan.

  • Working on detailed LHC layouts - plan to circulate

soon an Engineering Change request for approval.

  • Realistic to have a minimum setup (crystals only, no

dedicated additional instrumentation). Need to discuss here if there is interest from US-LARP in participating into this effort!

  • D. Mirarchi

Crystal TCSG DS losses

slide-32
SLIDE 32
  • S. Redaelli, US-LARP CM20 08/04/2013

Conclusions

32

The LHC and its collimation system performed remarkably well in the Run1 with stored energies up to ~140MJ! We could postpone major collimation until after LS1, but we must be

be ready if the operation at 7 TeV shows problems.

The upgrade strategy is being reviewed based on the OP experience: a collimator review in May will address mid- and long-term plans. Immediate goal: decide on the 11 T dipole strategy until post-LS1 operation.

Can we get them in LS2 if the operation at 2015 show that they are needed? It seems clear that they will be needed for HL-LHC.

Other exciting studies are ongoing to meet the HL-LHC challenges. Important material studies, different aspects (slow/fast losses, impedance, ..)

New collimator designs (improved present design, BPM design, SLAC RC, ...)

Advanced concepts like hollow e-lens, crystals, etc. The contribution to collimation from US-LARP is much appreciated! New proposed strategy for the hollow e-lens, which relies on the competence!

Defined a plan for BNL material studies that complements our studies. Hoping to motivate the USA friends on new R&D topics!

slide-33
SLIDE 33
  • S. Redaelli, US-LARP CM20 08/04/2013
33

Reserve slides

slide-34
SLIDE 34
  • S. Redaelli, US-LARP CM20 08/04/2013

Cleaning for HL-LHC optics (ATS)

34

!"#$%&'(&)*+#&,'-%."#"&.'++&-/%+&01#2&34& '%5,+&6/+".17"&89:!&('*&;<,-=>&?@"75)"@& %'++16."&,*15,/.&.'++&.',/5'7+&'$#+1@"&A!&'(& ?BC&DE&7""@&#'&1-%*'F"&#2"&?BC&,."/717GH& & !1-$./5'7&'(&%2I+1,+&@"6*1+&.'++"+&('*& %*'#'7&,'..1+1'7+>& & !"#$%&'()(*#+,-!+.# /0123#45#6&'1#72)8-12&9# :01%1&49#;)0%9(9<# =0:&('#5&47#>(<>#)27(94'(1?#

Present simulations indicate that adding a DS collimator would solve the problem

  • f losses in other arcs, which is otherwise

a potential show-stopper for ATS!

slide-35
SLIDE 35
  • S. Redaelli, US-LARP CM20 08/04/2013

Lifetime during OP cycle

35

Couple of illustrative examples taken randomly from the LHC elogbook... Ramp + Squeeze + Adjust Physics

25h

Ramp Physics Squeeze Adjust Injection

10 h

Will this be a serious issue after LS1? Detailed analysis of quench tests will provide improved estimates. Needs of possible scraping methods (hollow e-lens or similar) are being studied. Can always open the collimators, at the cost of larger β*.

slide-36
SLIDE 36
  • S. Redaelli, US-LARP CM20 08/04/2013

Beam lifetime analysis

21-Mar 20-Apr 20-May 19-Jun 19-Jul 18-Aug 17-Sep 17-Oct

  • Min. BCT Lifetime [h]
  • 2

10

  • 1

10 1 10

= 5sec

int

! BEAM 1 BEAM 2

ADJUST

Year 2012 [day-month]

21-Mar 20-Apr 20-May 19-Jun 19-Jul 18-Aug 17-Sep 17-Oct

  • Min. BCT Lifetime [h]
  • 2

10

  • 1

10 1 10

= 5sec

int

! BEAM 1 BEAM 2

SQUEEZE

New Collision BP TS2 TS1 Change Octuple Polarity Increase Q’

  • B. Salvachua

ADJUST: 30 dumps SQUEEZE: 16 dumps 0.1-0.3 h 0.1-0.3 h

slide-37
SLIDE 37
  • S. Redaelli, US-LARP CM20 08/04/2013

Cleaning for Pb ion beams at 4 TeV

37

1/100

Experience at 4 TeV confirmed the 2011 results at 3.5 TeV: Betatron cleaning

  • f a few percent only, i.e. more than a factor 100 worst than for protons.

Limiting location still the dispersion suppressor, but different loss distribution than for protons: fragmented ion beams lost at specific locations.

slide-38
SLIDE 38
  • S. Redaelli, US-LARP CM20 08/04/2013

Losses from luminosity debris

38
  • In 2012, we have started using the TCL collimators in IP1 and IP5 that catch physics debris.
  • Set to 10σ since the start of the run.
  • We have performed TCLs scans to understand the impact on reducing the losses and the

load to the magnets. At 10σ measured losses at Q8 reduced by a factor of 50!

12.9 13 13.1 13.2 13.3 13.4 13.5 13.6 13.7 10
  • 6
10
  • 5
10
  • 4
10
  • 3
Longitudinal position [ km ] Beam losses [ Gy/s ] IP5

Q4/Q6 Q8

Proton operation in 2011

12.9 13 13.1 13.2 13.3 13.4 13.5 13.6 13.7 13.8 10
  • 6
10
  • 5
10
  • 4
10
  • 3
Longitudinal position [ km ] Beam losses [ Gy/s ]

Proton operation in 2012

Q9

IP5 IP5

Losses going down Losses going down

TCL TCL

Significant improvement of SEU's in IR1 and IR5

slide-39
SLIDE 39
  • S. Redaelli, US-LARP CM20 08/04/2013

3.5 TeV losses with Pb-Pb collisions

39

Bound-free pair production secondary beams from IPs

IBS & Electromagnetic dissociation at IPs, taken up by momentum collimators

?? Losses from collimation inefficiency, nuclear processes in primary collimators

  • J. Jowett
slide-40
SLIDE 40
  • S. Redaelli, US-LARP CM20 08/04/2013

Secondary beam at the IR2 DS

40

Cannot separate BFPP and main beam in warm area (eg by Roman pots a la TOTEM).

  • J. Jowett
slide-41
SLIDE 41
  • S. Redaelli, US-LARP CM20 08/04/2013

LS1 collimation activities

41

BPM buttons

Courtesy O. Aberle, A. Bertarelli, F. Carra, A. Dallocchio,

  • L. Gentini et al.

16 Tungsten TCTs in all IRs and the 2 Carbon TCSGs in IR6 will be replaced by new collimators with integrated BPMs.

  • Gain: can align the collimator jaw without “touching” the beam ➙ no dedicated low-intensity fills.
  • ➙ Drastically reduced setup time => more flexibility in IR configurations
  • ➙ Reduced orbit margins in cleaning hierarchy => more room to squeeze β*: ≥ ~30 cm (R. Bruce)
  • ➙ Improved monitoring of local orbit and interlocking strategy

Updated TCL layouts in IR1/5 for physics debris absorption

  • ➙ Add 1-2 TCL collimator per beam. Expected to be compatible with HL proton luminosity.

Improve protection of warm MQW magnets in IR3 by adding passive absorbers

  • ➙ Improve lifetime by a factor ~5 and allow more flexibility for loss sharing IR3/IR7.

Other smaller improvements/consolidation works

➙ IR8 vacuum layout. ➙ Replace a TCP that was heating.

slide-42
SLIDE 42
  • S. Redaelli, US-LARP CM20 08/04/2013

Main features of BPM collimators

42
  • R. Bruce: CMAC 2012

Measured beam position within jaws [mm] Achieved collimator alignment to 10 um resolution in less than 20 seconds with 20mm full gap!

  • G. Valentino,
  • M. Gasior

Machine Protection workshop at Annecy (11-13/03/2013): acknowledged great potential

  • f this new feature for MP purposes!

Equip dump region + TCT: allows reducing

  • rbit margins for

protection and gives flexibility for IR configurations.

slide-43
SLIDE 43
  • S. Redaelli, US-LARP CM20 08/04/2013

Basic hollow e-lens concepts

43 Setup at the Tevatron, court.
  • f G. Stancari

A hollow electron beam runs parallel to the proton beam

  • Halo particles see a field that depends on (Ax,Ay) plane
  • Beam core not affected!

Adjusting the e-beam parameter, one can control diffusion speed of particles in the area that overlaps to e-beam.

  • Drives halo particles unstable by enhancing (even small)
  • non-linearities of the machine.

Particles excited are selected by their transverse amplitude.

  • Completely orthogonal to tune space.

This is an ideal scraper that is robust by definition. Conceptual integration in the LHC collimation system:

  • The halo absorption is done by the standard collimators.
  • Hollow beam radius smaller than primary collimator aperture.

Complex beam dynamics required beam data validation.

slide-44
SLIDE 44
  • S. Redaelli, US-LARP CM20 08/04/2013

Prototyping of cryostat by-pass

44
  • D. Duarte Ramos

Will be tested at SM18 in 2014

slide-45
SLIDE 45
  • S. Redaelli, US-LARP CM20 08/04/2013

Technology choice for DS collimator

45

!"#$%"&%'()%*"+,%*"++-./'"#%0)/1-2-+-'3%4'5,3%')/.6%7"87+5,),%'(/'%'()%9:/#.;%<4% 7"++-./'"#%:-'(%/%23=>/11%7#3"1'/'%-1%'()%2)1'%1"+5?"8%&"#%'()%@A*B%%

!"#$%&$'%()$'%((*+,-%&$)./*0&$1*(($'%&-&2.$34256!#7$