Leicester School MAY 21, 2019 AT 7:00PM Building Project - - PowerPoint PPT Presentation

leicester school
SMART_READER_LITE
LIVE PREVIEW

Leicester School MAY 21, 2019 AT 7:00PM Building Project - - PowerPoint PPT Presentation

Leicester School MAY 21, 2019 AT 7:00PM Building Project Leicester Middle School Gymnasium 70 Winslow Ave COMMUNITY FORUM Agenda Introduction Project Overview Project Cost Scenarios Educational Visioning Sessions Challenges Opportunities


slide-1
SLIDE 1

Leicester School Building Project

COMMUNITY FORUM MAY 21, 2019 AT 7:00PM Leicester Middle School Gymnasium 70 Winslow Ave

slide-2
SLIDE 2

Agenda

Introduction Project Overview Project Cost Scenarios Educational Visioning Sessions Challenges Opportunities Q & A

slide-3
SLIDE 3

School Building Committee Members

Mark Armington Community Member and Engineer Sarah Bayer Teacher/Parent/Resident Jeff Berthiaume Director of Technology and Digital Learning Eileen Boisvert Parent/Resident Tina Boss School Principal, Memorial School Harry Brooks SBC Chair, Member Board of Selectmen Chris Clark Community Member and Parent Chris Fontaine School Assistant Principal , Leicester Middle School David Genereux Town Administrator, SBC who is MCPPO certified Tim Hickey Council on Aging T

  • m Lauder

School Committee Chair Kristina Looney Leicester MS Teacher, Music Education Joyce Nelson School Principal, Leicester Middle School Cady Maynard Director of Finance and Operations Dennis McGrail Finance Advisory Board and Parent Paul McCarthy Community Member and Parent Jim Reinke Member of the Commission on Disabilities Marilyn T encza School Superintendent David White Local Official for Building Maintenance

slide-4
SLIDE 4

Project Schedule

March 2016 December 2017 June 2018 December 2018 July 2019 August 2019 February 2020 April 2020 May 2020 June 2021 July 2021 September 2023 Statement of Interest to the MSBA MSBA Invitation into Core Program OPM Award Designer Selection Feasibility Study MSBA Board Approval of Feasibility Study Schematic Design MSBA Board Approval of Schematic Design Local Vote/Funding Approval DD/CD/Bidding Commence Construction Substantial Completion/School Opens

slide-5
SLIDE 5

Schedule Overview - Next Steps

April 2019 April / June 2019 June 20, 2019 July 10, 2019 August 28, 2019 August 2019 January 3, 2020 February 14, 2020 May 2020 Submit Preliminary Design Program Develop Study Options SBC Vote on Preferred Alternative Submit Preferred Schematic Report (PSR) to MSBA MSBA Board Vote: Preferred Alternative Begin Schematic Design Submit Schematic Design to MSBA MSBA Board Vote: Project Scope and Budget Agreement Town Meeting – Funding Approval

slide-6
SLIDE 6

What is the MSBA?

Created in 2004, The Massachusetts School Building Authority (MSBA) is a state government authority that works with local communities to create affordable, sustainable, energy efficient and educationally appropriate public schools across Massachusetts. One penny of the state’s 6.25 percent sales tax supports the MSBA’s funding for public school capital projects. MSBA reimbursement rates for eligible school construction costs are based on a formula.

slide-7
SLIDE 7

MSBA Effective Reimbursement Rate

2019 Base Reimbursement Rate for Leicester is 59.21%

  • Applies only to eligible school project costs

Limits site reimbursement Limits size of project and cost/SF Does not apply to auditoriums and playing fields

  • Rate may be increased for incentive points

Sustainable Design – 2.0% (LEED Silver) Maintenance Program – 1.41%

  • Incentive points subject to change by the MSBA
slide-8
SLIDE 8

Educational Visioning

slide-9
SLIDE 9

Core Academic Spaces (Classrooms) Special Education Art & Music Vocations & Technology Health & Physical Education Media Center Dining & Food Service Medical Administrative & Guidance Custodial & Maintenance

Educational Program Needs

slide-10
SLIDE 10

Visioning Workshop # 1: January 29, 2019 Visioning Workshop #2: February 5, 2019 School Tours: February 14, 2019

Hunking Middle School (Grades K-8) Haverhill, MA Beverly Middle School (Grades 5-8) Beverly, MA

Visioning Workshop #3: February 29, 2019 Faculty Workshop: March 5, 2019

Educational Visioning

slide-11
SLIDE 11

Visioning Workshop # 1: January 29, 2019

Priorities and Considerations

Educational Visioning

Innovation and Engagement Shared Culture Community Access Agile Classroom Outdoor Spaces and Connections Sustainability Safety and Security Parking and Drop-off Robust Technology Ease of Access Flexible and Collaborative Spaces Ease of Use and Maintenance Building Display

slide-12
SLIDE 12

Visioning Workshop # 2: February 5, 2019

Desired 21st Century Design Patterns 2.0

Educational Visioning

Breakout Areas Multi-Purpose Spaces Safety, Security, & Welcoming Outdoor Connections Flexible & Agile Connections Sustainability Media Space as Learning Hub Community Access Display & Exhibition Clusters of Learning Quiet Spaces Push-in Special Education Distributed Dining Branding & Identity Flexible Furniture Distributed Resources Visible Learning & Transparency Maker Spaces & FAB lab Natural Light Timeless Look

Breakout Spaces Safe, Secure, & Welcoming Media Space as Learning Hub Quiet Spaces

slide-13
SLIDE 13

Visioning Workshop # 2: February 5, 2019

Guiding Principles 1. Innovation and Engagement 2. Collaboration and Cooperation 3. A Place You Want to Be 4. Community Access 5. Adaptability and Flexibility 6. Outdoor and Nature Connections 7 . Sustainability

Educational Visioning

  • 1. Innovation and Engagement
  • 2. Collaboration and Cooperation
  • 3. A Place

You Want to Be

  • 4. Community Access
  • 5. Adaptability and Flexibility
  • 6. Outdoor and Nature Connections

7 . Sustainability

INTEGRATED PHOTOVOLTAICS SUPER INSULATED ROOF DISPLACEMENT VENTILATION GEOTHERMAL WELLS NATURAL VENTILATION RAINWATER COLLECTION SUPER INSULATED INNER ENVELOPE OPERABLE GLAZING
slide-14
SLIDE 14

Visioning Workshop # 3: February 29, 2019

Educational Visioning

Media Center & Innovation Hub Two Schools, One Roof Navigating Existing Topography Whole School Entry Sequence Community Access

slide-15
SLIDE 15

Challenges & Opportunities

slide-16
SLIDE 16

Need for Welcoming & Inviting Entrance Opportunity Challenge

Zervas Elementary, Newton, MA Existing Leicester Middle School

slide-17
SLIDE 17

Undersized Classrooms Opportunity Challenge

Zervas Elementary, Newton, MA Existing Leicester Middle School

slide-18
SLIDE 18

Non-compliant Circulation Opportunity Challenge

Methuen High School, Methuen, MA Existing Leicester Middle School

slide-19
SLIDE 19

Need for Administrative Control Opportunity Challenge

Concord-Carlisle High School, Concord, MA Existing Leicester Middle School

slide-20
SLIDE 20

Non-Compliant Doors & Clearances Opportunity Challenge

Hunking Middle School, Haverhill, MA Existing Leicester Middle School

slide-21
SLIDE 21

Outdated & Inefficient Equipment Opportunity Challenge

Gibbs School, Arlington, MA Existing Leicester Middle School

slide-22
SLIDE 22

Underutilized Outdoor Connections Opportunity Challenge

Arlington School, Tacoma, WA Existing Leicester Middle School

slide-23
SLIDE 23

Inefficent Energy Performance Opportunity Challenge

INTEGRATED PHOTOVOLTAICS SUPER INSULATED ROOF DISPLACEMENT VENTILATION GEOTHERMAL WELLS NATURAL VENTILATION RAINWATER COLLECTION SUPER INSULATED INNER ENVELOPE OPERABLE GLAZING

The Foundry Existing Leicester Middle School

slide-24
SLIDE 24

Undersized Cafeteria Opportunity Challenge

Hunking Middle School, Haverhill, MA Existing Leicester Middle School

slide-25
SLIDE 25

Outdated Gymnasium Opportunity Challenge

Beverly Middle School, Beverly, MA Existing Leicester Middle School

slide-26
SLIDE 26

Design Explorations

slide-27
SLIDE 27

Alternative Sites

Leicester Middle School

slide-28
SLIDE 28

Alternative Sites

Leicester Middle School

Ample parking Multiple field configurations

  • T
  • wn owned land
  • Suitable soil
  • Easy community access
  • Minimal tree removal
  • Creates central school

campus Access throughout the site Revise existing access drive P SCHOOL

slide-29
SLIDE 29

Alternative Sites

Memorial School

slide-30
SLIDE 30

Alternative Sites

Memorial School

  • T
  • wn owned land
  • Requires demo of

existing school

  • Narrow site not suitable

for development

  • 2.2 mi from school

campus

  • Limited space for playing

fields Limited site access P Substantial tree removal required for playing fields Land not conducive for development Steep sloped terrain SCHOOL Limited site circulation

slide-31
SLIDE 31

Alternative Sites

Hillcrest Golf Course

slide-32
SLIDE 32

Alternative Sites

Hillcrest Golf Course

  • T
  • wn owned land
  • Removes 3 holes from

golf course

  • .5 mi from school

campus Limited space for playing fields Limited availability for parking Limited site circulation P S C H O O L

slide-33
SLIDE 33

Alternative Sites

1675 Main Street - Drive-In Theater

slide-34
SLIDE 34
  • Requires land acquisition

($)

  • 2.6 mi from school

campus

  • Located near WalMart

traffic

  • Site is landlocked

Alternative Sites

1675 Main Street - Drive-In Theater

Requires substantial tree removal for development One point of site access P SCHOOL Traffic on Rt. 9 (only way into Worcester)

slide-35
SLIDE 35

OPTION Grades 6 - 8

(330 enrollment)

Grades 5 - 8

(440 enrollment)

Grades Pre-K - 8

(930 enrollment)

Code Upgrade Only Addition/ Renovation Track Street Wings

19 37 SUBURBAN-AGRICULTURAL ZONE P A R C E L D I V I S I O N RESIDENTIAL 2 ZONE SENIOR CENTER SOIL: UDORTHENTS, SMOOTHED SOIL PILES RECENT WATER LINE INSTALLATION SOIL: PAXTON FINE SANDY LOAM, 3 TO 8 PERCENT SLOPES SOIL: RIDGEBURY FINE SANDY LOAM, 0-3 PERCENT SLOPES, EXTREMELY STONY WETLAND PAXTON STREET PATRICKS DRIVE 2 5 ’ N O B U I L D S E T B A C K 1 ’ W E T L A N D B U F F E R WETLAND WETLAND 1 5 ’ S I D E S E T B A C K 40’ SETBACK 15’ SIDE SETBACK LEGEND - SITE ANALYSIS # Parking Spaces ( 299 total) MIDDLE SCHOOL FOOTBALL PRACTICE SOFTBALL SOCCER BASEBALL UNDERSIZED TRACK IN POOR CONDITION STEEP SLOPE S T E E P S L O P E WETLAND Summer Winds Winter Sunrise Winter Sunset Spring/Fall Sunset SENIOR CENTER RECENT WATER LINE INSTALLATION WETLAND PAXTON STREET PATRICKS DRIVE 2 5 ’ N O B U I L D S E T B A C K 1 ’ W E T L A N D B U F F E R WETLAND WETLAND 1 5 ’ S I D E S E T B A C K T B A C K 40’ SETBACK 15’ SIDE SETBACK E X I S T I N G B U I L D I N G RENOVATE EXISTING BUILDING NEW BUILDING WETLAND SOFTBALL PLAY SVC CARS B U S E S FILL SLOPE R E T A I N I N G W A L L FILL SLOPE RECONSTRUCT TRACK SENIOR CENTER RECENT WATER LINE INSTALLATION WETLAND PAXTON STREET PATRICKS DRIVE 2 5 ’ N O B U I L D S E T B A C K 1 ’ W E T L A N D B U F F E R WETLAND WETLAND 1 5 ’ S I D E S E T B A C K T B A C K 40’ SETBACK 15’ SIDE SETBACK E X I S T I N G B U I L D I N G RENOVATE EXISTING BUILDING NEW BUILDING WETLAND SOFTBALL PLAY SVC CARS B U S E S FILL SLOPE R E T A I N I N G W A L L FILL SLOPE RECONSTRUCT TRACK SENIOR CENTER RECENT WATER LINE INSTALLATION WETLAND PAXTON STREET PATRICKS DRIVE 2 5 ’ N O B U I L D S E T B A C K 1 ’ W E T L A N D B U F F E R WETLAND WETLAND 1 5 ’ S I D E S E T B A C K T B A C K 40’ SETBACK 15’ SIDE SETBACK E X I S T I N G B U I L D I N G NEW BUILDING WETLAND RENOVATE EXISTING BUILDING SOFTBALL PLAY SVC CARS B U S E S FILL SLOPE R E T A I N I N G W A L L FILL SLOPE RECONSTRUCT TRACK SENIOR CENTER SOIL: UDORTHENTS, SMOOTHED RECENT WATER LINE INSTALLATION WETLAND PAXTON STREET PATRICKS DRIVE 2 5 ’ N O B U I L D S E T B A C K 1 ’ W E T L A N D B U F F E R WETLAND WETLAND 1 5 ’ S I D E S E T B A C K T B A C K 40’ SETBACK 15’ SIDE SETBACK E X I S T I N G B U I L D I N G N E W B U I L D I N G WETLAND NEW TRACK AND BLEACHERS S V C CAR QUEUE PLAY B U S E S SOFTBALL R E T A I N I N G W A L L FILL SLOPE SENIOR CENTER RECENT WATER LINE INSTALLATION WETLAND PAXTON STREET PATRICKS DRIVE 2 5 ’ N O B U I L D S E T B A C K 1 ’ W E T L A N D B U F F E R WETLAND WETLAND 1 5 ’ S I D E S E T B A C K E T B A C K 40’ SETBACK 15’ SIDE SETBACK E X I S T I N G B U I L D I N G N E W B U I L D I N G WETLAND SOFTBALL PLAY S V C C A R S B U S E S R E T A I N I N G W A L L FILL SLOPE RECONSTRUCT TRACK SENIOR CENTER RECENT WATER LINE INSTALLATION WETLAND PAXTON STREET PATRICKS DRIVE 2 5 ’ N O B U I L D S E T B A C K 1 ’ W E T L A N D B U F F E R WETLAND WETLAND 1 5 ’ S I D E S E T B A C K E T B A C K 40’ SETBACK 15’ SIDE SETBACK E X I S T I N G B U I L D I N G N E W B U I L D I N G WETLAND PLAY S V C C A R S B U S E S R E T A I N I N G W A L L FILL SLOPE SOFTBALL RECONSTRUCT TRACK SENIOR CENTER RECENT WATER LINE INSTALLATION WETLAND PAXTON STREET PATRICKS DRIVE 2 5 ’ N O B U I L D S E T B A C K 1 ’ W E T L A N D B U F F E R WETLAND WETLAND 1 5 ’ S I D E S E T B A C K E T B A C K 40’ SETBACK 15’ SIDE SETBACK E X I S T I N G B U I L D I N G N E W B U I L D I N G WETLAND PLAY S V C C A R S B U S E S RECONSTRUCT TRACK R E T A I N I N G W A L L FILL SLOPE SOFTBALL SENIOR CENTER RECENT WATER LINE INSTALLATION WETLAND PAXTON STREET PATRICKS DRIVE 2 5 ’ N O B U I L D S E T B A C K 1 ’ W E T L A N D B U F F E R WETLAND WETLAND 1 5 ’ S I D E S E T B A C K E T B A C K 40’ SETBACK 15’ SIDE SETBACK E X I S T I N G B U I L D I N G NEW BUILDING WETLAND R E T A I N I N G W A L L FILL SLOPE PLAY CARS B U S E S SOFTBALL RECONSTRUCT TRACK FILL SLOPE SENIOR CENTER RECENT WATER LINE INSTALLATION WETLAND PAXTON STREET PATRICKS DRIVE 2 5 ’ N O B U I L D S E T B A C K 1 ’ W E T L A N D B U F F E R WETLAND WETLAND 1 5 ’ S I D E S E T B A C K E T B A C K 40’ SETBACK 15’ SIDE SETBACK E X I S T I N G B U I L D I N G NEW BUILDING WETLAND R E T A I N I N G W A L L FILL SLOPE PLAY CARS B U S E S SOFTBALL RECONSTRUCT TRACK FILL SLOPE SENIOR CENTER RECENT WATER LINE INSTALLATION WETLAND PAXTON STREET PATRICKS DRIVE 2 5 ’ N O B U I L D S E T B A C K 1 ’ W E T L A N D B U F F E R WETLAND WETLAND 1 5 ’ S I D E S E T B A C K T B A C K 40’ SETBACK 15’ SIDE SETBACK E X I S T I N G B U I L D I N G NEW BUILDING WETLAND R E T A I N I N G W A L L FILL SLOPE PLAY CARS B U S E S SOFTBALL RECONSTRUCT TRACK FILL SLOPE
slide-36
SLIDE 36

Addition/Renovation Option 5 - 8

PRIMARY SCHOOL

WATER RESOURCES PROTECTION HYLAND AVENUE SENIOR CENTER RECENT WATER LINE INSTALLATION BECKER COLLEGE LEICESTER CAMPUS WETLAND P A X T O N S T R E E T P A T R I C K S D R I V E 25’ NO BUILD SETBACK 2 5 ’ N O B U I L D S E T B A C K 100’ WETLAND BUFFER 1 ’ W E T L A N D B U F F E R WETLAND WETLAND W I N S L O W A V E N U E 2 5 ’ F R O N T S E T B A C K 15’ SIDE SETBACK 40’ SETBACK 40’ SETBACK 4 ’ S E T B A C K 4 ’ S E T B A C K 1 5 ’ S I D E S E T B A C K

EXISTING HIGH SCHOOL

ELECTRIC TRANSMISSION LINE E X I S T I N G B U I L D I N G R E N O V A T E E X I S T I N G B U I L D I N G

NEW BUILDING

WETLAND SOFTBALL PLAY SVC C A R S B U S E S F I L L S L O P E RETAINING WALL FILL SLOPE RECONSTRUCT TRACK NORTH 0’ 30’ 60’ 120’

Building Area: 94,716 SF

slide-37
SLIDE 37

Addition/Renovation Option Pre-K - 8

PRIMARY SCHOOL

W A T E R R E S O U R C E S P R O T E C T I O N HYLAND AVENUE SENIOR CENTER RECENT WATER LINE INSTALLATION BECKER COLLEGE LEICESTER CAMPUS WETLAND PAXTON STREET P A T R I C K S D R I V E 25’ NO BUILD SETBACK 25’ NO BUILD SETBACK 100’ WETLAND BUFFER 100’ WETLAND BUFFER WETLAND WETLAND WINSLOW AVENUE 25’ FRONT SETBACK 15’ SIDE SETBACK 40’ SETBACK 40’ SETBACK 40’ SETBACK 40’ SETBACK 15’ SIDE SETBACK

EXISTING HIGH SCHOOL

ELECTRIC TRANSMISSION LINE EXISTING BUILDING

NEW BUILDING

WETLAND RENOVATE EXISTING BUILDING SOFTBALL PLAY SVC CARS BUSES FILL SLOPE RETAINING WALL FILL SLOPE RECONSTRUCT TRACK NORTH 0’ 30’ 60’ 120’

Building Area: 139,024 SF

slide-38
SLIDE 38

Street Option 5 - 8

W A T E R R E S O U R C E S P R O T E C T I O N HYLAND AVENUE SENIOR CENTER RECENT WATER LINE INSTALLATION BECKER COLLEGE LEICESTER CAMPUS WETLAND PAXTON STREET P A T R I C K S D R I V E 25’ NO BUILD SETBACK 25’ NO BUILD SETBACK 100’ WETLAND BUFFER 100’ WETLAND BUFFER WETLAND WETLAND WINSLOW AVENUE 25’ FRONT SETBACK 15’ SIDE SETBACK 40’ SETBACK 40’ SETBACK 40’ SETBACK 40’ SETBACK 15’ SIDE SETBACK

EXISTING HIGH SCHOOL

ELECTRIC TRANSMISSION LINE EXISTING BUILDING

N E W B U I L D I N G

WETLAND PLAY SVC CARS BUSES RETAINING WALL FILL SLOPE SOFTBALL RECONSTRUCT TRACK

PRIMARY SCHOOL

NORTH 0’ 30’ 60’ 120’

Building Area: 82,091 SF

slide-39
SLIDE 39

Street Option Pre-K - 8

W A T E R R E S O U R C E S P R O T E C T I O N HYLAND AVENUE SENIOR CENTER RECENT WATER LINE INSTALLATION BECKER COLLEGE LEICESTER CAMPUS WETLAND PAXTON STREET P A T R I C K S D R I V E 25’ NO BUILD SETBACK 25’ NO BUILD SETBACK 100’ WETLAND BUFFER 100’ WETLAND BUFFER WETLAND WETLAND WINSLOW AVENUE 25’ FRONT SETBACK 15’ SIDE SETBACK 40’ SETBACK 40’ SETBACK 40’ SETBACK 40’ SETBACK 15’ SIDE SETBACK

EXISTING HIGH SCHOOL

ELECTRIC TRANSMISSION LINE EXISTING BUILDING

N E W B U I L D I N G

WETLAND PLAY SVC CARS BUSES RECONSTRUCT TRACK RETAINING WALL FILL SLOPE SOFTBALL

PRIMARY SCHOOL

NORTH 0’ 30’ 60’ 120’

Building Area: 143,793 SF

slide-40
SLIDE 40

Wings Option 5 - 8

PRIMARY SCHOOL

W A T E R R E S O U R C E S P R O T E C T I O N HYLAND AVENUE SENIOR CENTER RECENT WATER LINE INSTALLATION BECKER COLLEGE LEICESTER CAMPUS WETLAND PAXTON STREET P A T R I C K S D R I V E 25’ NO BUILD SETBACK 25’ NO BUILD SETBACK 100’ WETLAND BUFFER 100’ WETLAND BUFFER WETLAND WETLAND WINSLOW AVENUE 25’ FRONT SETBACK 15’ SIDE SETBACK 40’ SETBACK 40’ SETBACK 40’ SETBACK 40’ SETBACK 15’ SIDE SETBACK

EXISTING HIGH SCHOOL

ELECTRIC TRANSMISSION LINE EXISTING BUILDING

N E W B U I L D I N G

WETLAND RETAINING WALL FILL SLOPE PLAY CARS BUSES SOFTBALL RECONSTRUCT TRACK FILL SLOPE NORTH 0’ 30’ 60’ 120’

Building Area: 81,452 SF

slide-41
SLIDE 41

Wings Option Pre-K - 8

PRIMARY SCHOOL

W A T E R R E S O U R C E S P R O T E C T I O N HYLAND AVENUE SENIOR CENTER RECENT WATER LINE INSTALLATION BECKER COLLEGE LEICESTER CAMPUS WETLAND PAXTON STREET P A T R I C K S D R I V E 25’ NO BUILD SETBACK 25’ NO BUILD SETBACK 100’ WETLAND BUFFER 100’ WETLAND BUFFER WETLAND WETLAND WINSLOW AVENUE 25’ FRONT SETBACK 15’ SIDE SETBACK 40’ SETBACK 40’ SETBACK 40’ SETBACK 40’ SETBACK 15’ SIDE SETBACK

EXISTING HIGH SCHOOL

ELECTRIC TRANSMISSION LINE EXISTING BUILDING

N E W B U I L D I N G

WETLAND RETAINING WALL FILL SLOPE PLAY CARS BUSES SOFTBALL RECONSTRUCT TRACK FILL SLOPE NORTH 0’ 30’ 60’ 120’

Building Area: 142,121 SF

slide-42
SLIDE 42

OPTION Grades 5 - 8 Grades Pre-K - 8 Addition/ Renovation $45 Mil $62 Mil Street $46 Mil $70 Mil Wings $48 Mil $70 Mil

Estimate of Probable Cost

slide-43
SLIDE 43

Project Cost Scenarios

Approved Enrollment: Approximate Project Size:

  • Est. Construction Cost:

Add Soft Costs: Adjust for Escalation: 930 Student Enrollment (Grades Pre-K - 8) 141,241 SF per MSBA Space Templates $500/SF* per Independent Est. Firms Approximately 25% of construction cost Estimated 3% per year / year to construction mid-point New K-8 on Existing Site: Estimated Total Project Cost: $87 mil Estimated Facilities Grant: $41 mil Estimated District Share: $45 mil Estimated Residential Tax Impact: $830/year

*MSBA will reimburse up to $350/SF

slide-44
SLIDE 44
  • Effjciency
  • Safety
  • Community Improvement
  • Increased Property Value
  • Community Use
  • Financially Responsible Choice

Benefits of Building a New School

slide-45
SLIDE 45

Future Forward Educational Setting

slide-46
SLIDE 46

leicesterbuildingproject.com

slide-47
SLIDE 47

Questions & Answers