Legislative and Regulatory Updates September 16, 2015 Saskatchewan - - PowerPoint PPT Presentation

legislative and regulatory updates september 16 2015
SMART_READER_LITE
LIVE PREVIEW

Legislative and Regulatory Updates September 16, 2015 Saskatchewan - - PowerPoint PPT Presentation

Drinking Water and Wastewater Legislative and Regulatory Updates September 16, 2015 Saskatchewan Water and Wastewater Association Sam Ferris Executive Director Environmental and Municipal Management Services Division Water Security Agency


slide-1
SLIDE 1

Drinking Water and Wastewater Legislative and Regulatory Updates September 16, 2015 Saskatchewan Water and Wastewater Association

Sam Ferris Executive Director Environmental and Municipal Management Services Division Water Security Agency

slide-2
SLIDE 2

Presentation Outline

  • Background & Regulatory History – Where have we been /

Where are we headed.

  • Regulatory Roles and Responsibilities
  • Authorities, Changes and Implications - Environmental

Management and Protection Act – 2010

  • Requirements, Changes and Implications - The Waterworks

and Sewage Works Regulations

  • Environmental Codes – Status
  • Questions?
slide-3
SLIDE 3

Background – Legislative History

  • The Environmental Management and Protection Act, 2010

(EMPA 2010) and The Waterworks and Sewage Works Regulations (WSWR) serves as the ongoing evolution of environmental and water related legislation in Saskatchewan.

  • EMPA 2002 and The Water Regulations,2002 created following

the waterborne disease outbreak affecting Walkerton, ON and North Battleford, SK of 2000 and 2001 and have served well to initially address the need for improved drinking water and wastewater management in Saskatchewan.

  • Marked improvement in drinking water related compliance.
slide-4
SLIDE 4

Background – Progress

Operator Certification: Created under The Water Pollution Control and Waterworks Regulations.

slide-5
SLIDE 5

Background – Progress

Operator Certification: Created under The Water Pollution Control and Waterworks Regulations.

Table 3: Per cent of communities with human consumptive waterworks whose operators have received some level of certification

Sept 30, 2004 Mar 31, 2006 Mar 31, 2007 Mar 31, 2008 Mar 31, 2009 Mar 31, 2010 Mar 31, 2011 Mar 31, 2012 Mar 31, 2013 Mar 31, 2014 Mar 31, 2015 Annual Change (2014-15) Per cent of communities with human consumptive waterworks whose

  • perators have

received some level of certification 54.3 96.8 98.9 99.2 99.2 98.9 98.3 99.6 99.4 99.8 99.8 0%

slide-6
SLIDE 6

Background – Progress

Bacteriological Standards Compliance:

slide-7
SLIDE 7

Background – Progress

Disinfection Standards Compliance:

slide-8
SLIDE 8

Background – Progress

Health and Toxicity Compliance:

Table 5: Health and toxicity sample submission and parameter result compliance 2015-13 to 2011-12 fiscal years*

Fiscal Year Health and Toxicity Sample Submission Compliance Rate (Percentage) Parameter Standards Compliance Rate (Percentage) 2014-15 86.88 92.20 2013-14 84.27** 92.14 2012-13 71.65 90.93 2011-12 70.90 91.14

slide-9
SLIDE 9

Background – Progress

Works not meeting minimum treatment requirements:

slide-10
SLIDE 10

Background – Progress

Waterworks inspection findings:

Table 7: Waterworks inspection finding summary (2014-15)

Inspection Element Non- Compliant N/A or No Response* Compliant Disinfection continuous at plant 34 20 906 Disinfection Free chlorine > or = 0.1 mg/L leaving the plant 129 200 631 Monitoring daily chlorine 68 26 866 Reservoirs in good repair 29 121 810 Water treatment plant in clean and orderly condition 35 54 871 A total chlorine residual not <0.5 mg/l or a free chlorine residual not <0.1 mg/l in the distribution system 122 45 793 Bacteriological testing after completion, alteration, extension or repair 11 80 869 Reporting of chlorine upsets 70 80 810 Record keeping 9 12 939

slide-11
SLIDE 11

Background – Progress

Waterworks PDWA and EBWO:

As of Sept 11, 2015:

  • 3,423 PDWA / 90 EBWO since 1999
  • 70 PDWA / 1 EBWO currently in effect
  • 41 PDWA / 1 EBWO in effect for > 6 months.

Table 8: EBWO/PDWA Statistics for 2014-15 – Water Security Agency Regulated Waterworks Time EBWO PDWA

In effect prior to reporting period 2 63 Added during the reporting period 5 576 In effect at end of reporting period 2 61

slide-12
SLIDE 12

Background – Progress

Facultative Lagoon Inspection Findings:

Table 14: Facultative lagoon wastewater works inspection finding summary (2014-15)

Inspection Element Non- Compliant N/A* or No Response Compliant Two basins in series 34 25 514 Immediate reporting of upset/bypass condition 14 144* 415 Maintenance work & failure of treatment components 48 31 494 Dates of discharge of sewage and volumes of discharge 44 201* 328 Locations from which samples are taken 23 183* 367 Results of any tests 15 175* 383 Approved system 9 4 ** 560 Certified operator 59 57 457 Maintained in appropriate manner 103 28 442 Sampling done as required 43 167* 363

slide-13
SLIDE 13

Background – Progress

Mechanical wastewater works inspection findings:

Table 15: Mechanical wastewater works inspection finding summary (2014-15)

Inspection Element Non- Compliant N/A* or No Response Compliant No interconnection between sanitary sewer and storm sewer 5 1 12 Pumping stations must have mechanically forced air ventilation 2 1 15 Effluent quality demonstrated to meet permit requirements for BOD5 2 2 14 Effluent quality demonstrated to meet permit requirements for TSS 7 2 9 Immediate reporting of upset/bypass condition 1 17 Disinfection performed as per permit 1 5 12 Immediate reporting of failure of disinfection equipment 7 11 Locations from which samples are taken 18 Results of any tests 2 16 Approved system 1 17 Certified operator 18 Reporting of exceedance 1 3 14 On-site testing completed as required 3 1 14 Sampling done as required 4 1 13

slide-14
SLIDE 14

Background Current Legislation – EMPA 2010

  • The Environmental Management and Protection Act, 2010
  • Current empowering legislation. Effective June 1, 2015.
  • Combined general environmental protection legislation/powers, enviro

reporting, discharges/discovery, corrective action plans, contaminated site transfer, drinking water, wastewater, aquatic habitat protection, aquatic nuisance control, solid waste, beverage containers, recycling , air quality, industrial waste management and orphan env impacted sites fund, and aspects and associated authorities and responsibilities into a single legislative instrument.

  • Environmental Assessment remains separate.
  • Introduces Environmental Codes and their operation, some regulations

replaced by code, some by formally adopted “standards”.

  • Compliance toolkit: PDWA, WWPO, SWPO, Env Prot Orders, Emergency

Orders, Admin Penalties, SOPA Penalties, Orders from convicting courts.

slide-15
SLIDE 15

Background Current Regulation – EMPA 2010

  • The Environmental Management and Protection Act, 2010 –

related NEW REGULATIONS include:

  • The Waterworks and Sewage Works Regulations;
  • The Environmental Management and Protection (General)

Regulations

  • Contains stranded elements such as: AHPP, Aquatic Nuisance Control,

various on site discharge exemptions, designation of industrial/commercial facilities requiring permits, beverage containers, industrial air quality aspects, Env impacts sites, Admin penalties.

  • The Environmental Management and Protection

(Saskatchewan Environmental Code Adoption) Regulations

  • Adopts various standards used by WSWR,
  • Lays out and formally brings into force various Environmental Code

chapters: Water Main and Sewer Main Code chapters.

  • All took effect June 1, 2015
slide-16
SLIDE 16

Background Current Regulation – EMPA 2010

  • The Environmental Management and Protection Act, 2010 –

continued regulations include:

  • The Municipal Refuse Management Regulations
  • Covers Liquid Domestic Waste collection and disposal – now

administered by WSA – remains unchanged.

  • Former landfill and transfer station provisions remain.
  • The Hazardous Substances and Waste Dangerous Goods

Regulations

  • Storage of chemicals at water and wastewater treatment plants
  • The Mineral Industry Environmental Protection Regulations
  • WSA has some involvement related to discharges to water.
  • Other recycling related regulations remain: Scrap Tire, Waste Paint, Waste

Electronic Equipment, Used Petroleum and Antifreeze, Household Packaging and Paper Stewardship

slide-17
SLIDE 17

Legislative History – EMPA 2002

  • The Environmental Management and Protection Act, 2002
  • Predecessor to EMPA 2010. Effective Oct 1, 2002 to May 31, 2015.
  • Combined general environmental protection legislation, unauthorized

discharges, contaminated sites, drinking water, wastewater, aquatic habitat protection, aquatic nuisance control, industrial effluent management and halocarbon management aspects and associated authorities and responsibilities into a single legislative instrument.

  • Air Quality, Litter Control, State of Environment Reporting and

Environmental Assessment remained separate.

  • Focus was on specified scope of application, authorities with a command

and control type approach reliant on permits and authorizations.

  • Compliance toolkit: PDWA, WWPO, SWPO, Env Prot Orders, Emergency

Orders, Enjoining Orders, Admin Penalties, (SOPA Penalties) – useful and employed in DW and WW management in Saskatchewan.

slide-18
SLIDE 18

Legislative History – EMPA (84-02)

  • The Environmental Management and Protection Act
  • Predecessor to EMPA 2002. Effective July 1, 1984 to Sept 30, 2002.
  • Covered general environmental protection powers, unauthorized

discharges, environmental restoration, aquatic habitat protection, aquatic nuisance control, industrial effluent management and associated authorities and responsibilities.

  • Focus on general pollution control, monitoring and abatement – somewhat

limited direct application to waterworks and sewage works.

  • Power to inspect water and sewage works, collect samples,(veto on

permits or may add conditions).

  • Compliance Toolkit: Order to Restore or Protect the Environment,

Department Immediate Action, Order Respecting Water and Sewage Works (similar to WWPO & SWPO).

  • Complimented The Water Corporation Act:
  • Permits for construction and operation of water treatment & sewage treatment

plants and operation of distribution & collection systems.

  • May issue orders for operations, maintenance, repair, extension, or alteration of

those works.

slide-19
SLIDE 19

Legislative History – Dept. of Env Act (78-84) Water Resources Management Act (80-84)

  • The Department of Environment Act:
  • Predecessor to EMPA. Effective 1978 to June 30, 1984.
  • Created/continued Dept of Environment and associate responsibilities,

grants, stop work orders, committees and councils.

  • Assigned administration of various Acts to DoE: Groundwater

Conservation, Water Resources Management, Water Rights, Water Power

  • Compliance Toolkit: Stop Order.
  • Water Resources Management Act:
  • Predecessor to EMPA, Effective July 1980
  • Covered general duties, planning, international and interprovincial waters,

water management, reservoir land use, waterworks, sewage works and pollution control

  • Compliance toolbox: General court based provisions
  • Water Pollution Control Regulations, Jan 11, 1980.
  • Focused on waterworks and sewage works.
  • Included design specifications, permit requirements, operation and

testing and records

slide-20
SLIDE 20

Regulatory History Drinking Water and Wastewater Mgmt.

  • The Waterworks and Sewage Works Regulations – June 1, 2015
  • Focus on waterworks, sewage works, OCB, and operator certification
  • Water Main and Sewer Main Environmental Code Chapters
  • The Water Regulations, 2002, Dec 5, 2002 – May 31, 2015
  • Governed waterworks, sewage works, industrial effluents, aquatic habitat

protection, aquatic nuisance control, OCB, operator certification, admin penalties.

  • Water Pollution Control and Waterworks Regulations, Jun87-Sep02
  • Focus on sewage works, industrial effluent works, waterworks, OCB, with

later amendments requiring operator certification.

  • Water Pollution Control Regulations, Jan 80 – Jun 87.
  • Focused on waterworks and sewage works.
  • Included design specifications, permit requirements, operation and testing and

records

slide-21
SLIDE 21

Current Roles and Responsibilities

  • As of October 2012 the Water Security Agency serves as regulator

for drinking water and wastewater systems as follows under EMPA 2010 and WSWR :

  • Municipal waterworks
  • Municipal wells connected to a distribution system
  • Water pipelines directly connected to a municipal waterworks
  • Water pipelines not otherwise directly connected to a municipal waterworks
  • r dist system with >15 service connections
  • Other waterworks with a design flow of >18m3/d
  • All municipal sewage works
  • All regional sewage works
  • Other sewage works with a design flow of >18m3/d
  • WSA also regulates monitoring of Limited Scope Water Pipelines

under The Health Hazard Regulations.

  • MoU with MoE for compliance and enforcement action support.
slide-22
SLIDE 22

Legislative Revisions EMPA 2010

slide-23
SLIDE 23

Authorities, Changes and Implications – EMPA 2010

  • S.2: Definitions:
  • “Qualified Person”: New definition added for qualified person to support rules

associated with various Environmental Code Chapters which are in part relianct on QP’s – as prescribed in the code or as designated by the Minister.

  • “Water”: Definition now includes surface water, groundwater and drinking
  • water. Previously only surface and groundwater.
  • S.4: Advisory Committee:
  • Establishes advisory committee by which environmental code chapters are

in part created or revised. Revisions to the codes is an involved and potentially time consuming process.

  • S.8: Prohibition on Discharges:
  • Generally carried over from EMPA, 2002, S. 4(1). Reworded to include

discharges authorized by the Code or an Environmental Protection Plan and therefore captures discharges in relation the construction of water and sewer mains in cities. Most sewage works operational permits contain reference to S8 or S4 (EMPA 2002) and prohibit release of substances that may or is causing an adverse effect. Trip point for unauthorized discharges or bypasses.

slide-24
SLIDE 24

Authorities, Changes and Implications – EMPA 2010

  • S.9 & S.10: Duty to Report and Take Immediate Action
  • Duty to report now includes activities under the Code – and therefore any

discharge from a water or sewer main constructed pursuant to the code that may or is causing and adverse effect needs to be reported. Report to EPO

  • r the WSA 24/7 Upset report line.
  • 9(4) requires municipal employees to report spills or discovery of

contaminated sites, as may occur in relation to construction projects – formerly part of The Environmental Spill Control Regs.

  • S10 requires persons report spills and contamination to take action to

reduce the risk in relation to the discovery/spill and take measures as needed to protect health, life, property and the environment.

slide-25
SLIDE 25

Authorities, Changes and Implications – EMPA 2010

  • S.24: & Table 1. Permits Required
  • New provision added to define types of activities requiring permits.

Underlying rationale includes high risk activities which may impact human health or environment. May also involve the assessment of new technology. Incorporates s. 21 & 35 of EMPA, 2002.

  • Permits required for:
  • Operation of all regulated waterworks and sewage works;
  • Construction of all water treatment works and sewage treatment works
  • Construction of a water distribution works or sewage collection works for

a system serving fewer than 5,000 people

  • By exclusion of water distribution and sewage collection works serving >

5,000 people it effectively enables operation of the water and sewer main codes.

  • S.25: Regulations and codes respecting permits
  • New provision. Provides authority to make requirements and regulations for

permit, financial assurances, environmental protection plans and notice of an

  • activity. This applies from high risk to low risk activities.
slide-26
SLIDE 26

Authorities, Changes and Implications – EMPA 2010

  • S.26: Minister may require or waive permits
  • New provision added to define types of activities requiring permits.

Underlying rationale includes high risk activities which may impact human health or environment. May also involve the assessment of new technology. Incorporates s. 21 & 35 of EMPA, 2002.

  • Certain waterworks, sewage works and portions thereof may be required to

have a permit, even if covered by code chapters.

  • May waive permit requirement if assured the person carrying out the activity

will otherwise comply, provide the same or better level of protection, and in the public interest to do so. Waiver not applicable to S.24 regulated works.

  • S.27: Minister’s decision on permits and EPP’s
  • Application in specified format req’d, may issue or refuse to issue permit.
  • Contains new provisions that lay out authorities and follow-up provisions for

dealing with any submitted environmental protection plan.

  • New provisions for dealing EPP’s submitted as alternative solutions. May

impose terms and conditions on an EPP, provide a 30 day period for written representations if additional conditions imposed or if plan is refused. Require s LG in C approval for decision. Accepted automatically after 45 days.

slide-27
SLIDE 27

Authorities, Changes and Implications – EMPA 2010

  • S.28: Amendment, suspension, cancellation of permits, accepted

environmental protection plans and status of qualified persons

  • This section confers on the Minister the ability to amend permits or EPP’s.

This is a continuation of an authority the Minister has in the existing Act (S.34(2)(4)and 60 of EMPA, 2002). Modified to meet the new provisions of the Act. Added 28(1)(c) to include EPP.

  • Lays out reasons why a permit may be amended, suspended or cancelled

such as contraventions of a permit or accepted EPP, clerical errors, false or misleading statement, changes made without required approval, or in public interest.

  • Written notice and 30 period for written representations.
  • May apply for cancellation of permit or EPP.
  • S.29: Offences
  • Requires compliance with permits, EPP’s, orders.
  • Carried over section of EMPA, 2002
  • New provision added to taking into account the environmental protection
  • plan. Makes basic prohibition for failing to comply with terms of an

environmental protection plan or upon rejection of an EPP by the Minister.

slide-28
SLIDE 28

Authorities, Changes and Implications – EMPA 2010

  • S30: Duties Imposed on QP’s re: Certificates, Documents, Opinions
  • New provision added to provide legislative backing for requirement for

qualified persons to provide accurate documentation. Wording change for clarification, added requirement for complying with acceptable professional standards.

  • PART V – Protection of Water – S. 31: Definitions.
  • Relocated definitions that just apply to “water”.
  • New definitions of person’s responsible for waterworks, sewage works, etc.
  • Old S.16 – Minister’s Powers Regarding Water – moved to EMPA 2010, S3.
  • Old S.17 – Collection of water data – moved to EMPA 2010, S3.
  • S.32: Drinking Water Report
  • Carried over from S.19 of EMPA 2002 unchanged
  • S.33: Duty to Provide Safe Water
  • Carried over from S.20 of EMPA 2002.
  • Removed reference to non-application to those noted limitations on water use

for consumptive purposes.

  • Old S.21 – Permit required for construction, alteration of water or sewage

works – now covered by S. 24 and Table 1.

slide-29
SLIDE 29

Authorities, Changes and Implications – EMPA 2010

  • S.34: Easements
  • Renumbered and provisions added to carry forward from EMPA 2002 and

the 2007 amendments which created this revised section, otherwise no substantial changes.

  • This Section provides to protect the interests an investment of sewage works
  • wners in ensuring long term access to wastewater discharge routes where

these cross property of others.

  • Now also applies to sewage collection works as regional sewage systems

are being developed which will include collection systems used to move sewage from the point of collection to the sewage treatment works and will cross other landowners property.

  • Old S.29 – Public Highways – not required –dropped.
  • S.35: Waterworks & Sewage Works Protection Orders
  • Renumbered and moved from former EMPA 2002 S.31 as applied to water

and sewage works

  • May also apply to water main and sewer main code projects.
slide-30
SLIDE 30

Authorities, Changes and Implications – EMPA 2010

  • S.36: Advisories and Emergency Orders
  • Carried over from former EMPA 2002, S.32. Largely unchanged
  • Application time period changed from 15 days to 45 days.
  • S.37: Amendments of Orders
  • Carries forward standard provisions for order amendment from

s.34(3),(4),(5),(6),(7),(8) EMPA 2002.

  • Added provision to provide written notice to person being issued orders.

Currently the ministry provides written notice as matter of common law but was not required to in EMPA, 2002.

  • S.38: Offences
  • Carried over from S.33 of EMPA, 2002 largely unchanged.
  • Still an offence to discharge a substance into water that would make it

unsafe for consumption, fail to meet permit requirements for compliance with DW Quality standards, fail to meet permit operational requirements, fail to comply with an order

  • Now includes references to offence for alterations to bed, bank and

boundary from 36(1) of EMPA, 2002.

slide-31
SLIDE 31

Authorities, Changes and Implications – EMPA 2010

  • S.55: Immediate Environmental Protection Orders
  • Carried over from former S. 47. Otherwise no change from EMPA 2002.
  • Emergency Environmental Protection Orders now endure for 45 days instead
  • f 15 days.
  • S.56: Environmental Protection Orders
  • Carried over from EMPA 2002, S.47
  • Provides authority for minister to allocate responsibility in cases where there

is more than one person responsible.

  • S.57: Service of Environmental Protection Orders
  • No change from S. 48 of EMPA 2002.
  • S.58: Process for issuing and amending environmental protection
  • rders
  • Largely unchanged from S.49 of EMPA, 2002.
  • S.59: Project Manager
  • Unchanged from EMPA, 2002, S.50.
  • S.60: When the Minister may carry out an EPO.
  • Unchanged from EMPA, 2002, S.51
slide-32
SLIDE 32

Authorities, Changes and Implications – EMPA 2010

  • S.68: Compliance Audits
  • New provision Provides the minister authority to require person regulated

pursuant to the Act to conduct a compliance audit to ensure compliance with the Act, regulations, code or environmental protection plans. These audits will be done by a third party. MoE may also carry out compliance audits

  • Work to be performed at the cost of the regulated party.
  • S.69: Obligation to gather and supply information
  • Provides authority for minister to gather information from municipality,

government organizations or any other person with respect to the stated

  • perations. Applies to water related information.
  • S.84: Offences
  • Fines extended to $1M/day or part thereof from previous max of $1M.
  • Added provision to extend fine beyond $1,000,000 where monetary benefits

accrued to the offender.

  • S.88: Admin Penalties
  • Moved from regulations to EMPA, 2010 and now more widely applicable.
  • New right of appeal from such penalties. Fines in EMPA (General) Regs.
slide-33
SLIDE 33

Regulatory Revisions The Waterworks and Sewage Works Regulations

slide-34
SLIDE 34

Requirements, Changes and Implications – WSWR

Major Changes

  • Regulations now only address drinking water and wastewater
  • aspects. Aquatic Habitat Protection, Industrial Effluent Works,

Aquatic Nuisance Control all moved to other regulations.

  • Formally moves buffer zones for sewage works from guidelines to

regulations.

  • Now includes MWWE and WSER related wastewater

management requirements.

  • Several new or revised drinking water quality standards and

associated timelines.

  • Permit exclusion for water and sewer mains serving > 5,000

people – now to Code.

slide-35
SLIDE 35

Requirements, Changes and Implications – WSWR

  • S.2: Definitions – Revised and New
  • Drinking Water – from potable to water intended for human consumption or

consumptive use. Improved clarity of intent.

  • Effluent – Removed linkage to liquid waste from industrial works
  • Lagoon – Removed linkage to use for storage of industrial effluent, now only

for treatment or storage of sewage.

  • Mechanical Treatment Facility – clarified to include a sewage treatment

facility the processes of which are controlled primarily by mechanical means, but does not include facilities employing only non-aerated lagoons.

  • Permittee – revised to remove reference to AHPP, ANC or Industrial effluent

facility and now includes those caught under S 24, 25 and 26 of EMPA.

  • Person – expanded to also expressly include an unincorporated association,

partnership or other organization, a municipality, a Crown corporation or an agency of the Crown;

slide-36
SLIDE 36

Requirements, Changes and Implications – WSWR

  • S.2: Definitions – Revised and New
  • Regional Sewage Works – New definition, means a sewage system:

(i) employed to collect and treat sewage with properties equivalent or similar to sewage from municipal sources; (ii) employed to collect and treat sewage from a communal collection system that serves one or more of the following: (A) permanent or seasonal residences; (B) acreages or farmsteads; (C) trailer courts; (D) commercial or industrial buildings, or any other similar facility not directly served by a municipal sewage works; and (iii) with a design flow exceeding 18 cubic metres in any 24-hour period;

  • Secondary Treatment Process – Removed reference to industrial effluent.

Now industrial waste works to include all forms of waste

  • Sewage Treatment Facility – Definition added to capture that part of a

sewage works.

slide-37
SLIDE 37

Requirements, Changes and Implications – WSWR

  • S.2: Definitions – Revised and New
  • Surface Water Treatment Plant - Revised to include the concept that the

definition of surface water treatment plants includes water plants that treat source water derived from groundwater under the direct influence of surface water.

  • Water Pipeline - Removed reference to association as this is considered to

be a “person”.

  • Works – removed reference to industrial facilities
  • S.3: Person Responsible for Water and Sewage Works
  • Simplified definition to eliminate what is already included in the definition of a

person and added reference to a permittee whose permit has been suspended or cancelled or whose permit expired.

slide-38
SLIDE 38

Requirements, Changes and Implications – WSWR

Part II Sewage Works

  • S.4: Through definition of the “Permittee” S.4 applies Part II to:

(i) any of the following activities pursuant to section 24 of the Act: (A) operation of a sewage works; (B) construction of a sewage treatment works; (C) construction of a sewage collection works for a system serving fewer than 5,000 people; (ii) an activity in relation to a sewage works for which a permit is required pursuant to section 25 of the Act; or (iii) an activity in relation to a sewage works for which a permit is required pursuant to S. 26 of the Act.

  • Formally adopts the Sewage Works Design Standard, EPB 503 – similar to the

Guidelines for Sewage Works Design, EPB 203, but revised and updated.

  • Standard provides more detail regarding design than is readily possible directly in

the Regulations, however requirements remain mandatory.

  • Standards can be revised without Code Committee consideration through

Gazette postings.

slide-39
SLIDE 39

Requirements, Changes and Implications – WSWR

  • S.5: Designation of Sewage Works
  • Designates and therefore regulates the following sewage works

(a) all municipal sewage works; (b) all regional sewage works; (c) all sewage works, other than those mentioned in clause (a) or (b):

  • (i) with a design flow exceeding 18 cubic metres in any 24-hour period; and
  • (ii) that collect and treat sewage with properties equivalent or similar to

sewage from municipal sources.

  • Adds regional sewage works – new examples exist
  • Directly defines just what is regulated versus the previous format that

defined what was generally not regulated.

  • S.6: Compliance Required
  • Requires compliance with this part, cause sewage works to conform with

requirements, inform employees, agents of permittee of the permit and its requirements, and design any new, upgraded, altered or extended sewage works in accordance with the sewage works design standard.

slide-40
SLIDE 40

Requirements, Changes and Implications – WSWR

  • S.7: No interconnection between sanitary sewers and storm

sewers – unchanged from Water Regulations, 2002.

  • S.8: Pumping stations
  • Still requires mechanically forced air ventilation.
  • Still requires backflow prevention device to prevent backflow to any water
  • utlet.
  • S.10: Buffer Zones
  • Moves Buffer zone requirements to regulations from Guidelines (EPB 203)
  • Defines buffer zone as the physical distance between:

(a) the outside edge of a liquid surface in a facultative lagoon or a mechanical treatment facility; and (b) the closest corner or side of the nearest single isolated residence, built- up residential area, institutional area or commercial area.

  • Requires permittee to ensure that all new or expanded facultative lagoons or

mechanical treatment facilities constructed after the coming into force of these regulations are designed, sited and constructed to have a buffer zone that meets the requirements set out in Table 1.

slide-41
SLIDE 41

Wastewater Management Requirements

Table 1: Facultative Lagoon and Mechanical Treatment Facility Buffer Zones

Facultative Lagoon Buffer Zone (Metres) Mechanical Sewage Works Buffer Zone (Metres) Single Isolated Residence 300 300(1) Built-up Residential Area 550(1) 300(1) Institutional 550(1) 300(1) Commercial (with no built-up residential area) 300 300(1)

slide-42
SLIDE 42

Requirements, Changes and Implications – WSWR

  • S.10: Buffer Zones
  • Applies to new or upgraded lagoons of mechanical works after June 1, 2015.
  • Establishes buffer zones as a formal regulatory requirement because of the

concerns and complaints associated with odours from lagoons.

  • Reduction of some buffer zone requirements allowed with agreement of

permittee and under specified conditions.

  • 550M may be reduced to 450M minimum
  • 300M may be reduced to 150 M minimum
  • Consideration interaction with Government Relations Municipal Regulations

– 347 M buffer.

  • Applies to construction of sewage works and other facilities in proximity

to sewage works.

  • Some reduction in GR requirements possible.
slide-43
SLIDE 43

Requirements, Changes and Implications – WSWR

  • S.11: Sewage Treatment Facilities and Associated Performance

Requirements

  • Required to meet permit limits and stated regulated requirements
  • Basic requirements found in S11(2) ensure that all sewage treatment

facilities in a sewage works include: (a) a secondary treatment process that produces effluent with no more than: (i) 30 milligrams per litre of BOD5; (ii) 25 milligrams per litre of CBOD5; and (iii) 30 milligrams per litre of total suspended solids; or (b) facultative lagoons designed, constructed and operated in accordance with section 12. – a min of 2 basins in series and designed/constructed in accordance with requirements set out in Table 2.

slide-44
SLIDE 44

Requirements, Changes and Implications – WSWR

  • S.11(3): Requirements Applicable to Works Discharging or that will

Discharge to Water Frequented by Fish

  • Incorporates requirements that parallel MWWE-CWS and WSER.
  • (a) with no more than 30 milligrams per litre of BOD5;
  • (b) with no more than 25 milligrams per litre of CBOD5;
  • (c) with no more than 25 milligrams per litre of total suspended solids;
  • (d) with no more than 0.02 milligrams per litre of total chlorine residual;
  • (e) that is not acutely toxic at the point of discharge;
  • (f) that does not contain un-ionized ammonia in excess of 1.24 milligrams

per litre, expressed as nitrogen at 15 degrees centigrade, plus or minus one degree centigrade; and

  • (g) that achieves the effluent discharge objective set out in the permittee’s

permit, within the timelines laid out in the permittee’s permit.

  • Applies to both WSER and MWWE captured works >100 cms/d and >10 cms/d

influent

  • No averaging as in WSER, upgrade timelines consistent with WSER/MWWE

timelines via permits.

slide-45
SLIDE 45

Requirements, Changes and Implications – WSWR

  • S.12: Facultative Lagoon Requirements and Timelines
  • Applies to lagoon standards for new or expanded sewage works. Provides

for achievement of MWWE standards in the future.

  • If facultative lagoons are used to treat sewage, the permittee shall ensure

that all facultative lagoons:

  • (a) have a minimum of two basins in series; and
  • (b) are designed and constructed in accordance with the requirements

set out in Table 2.

  • Increase storage times for effluent irrigation based systems.
  • Reduced loading to meet WSER/MWWE-CWS requirements.
  • See table
slide-46
SLIDE 46

Wastewater Management Requirements

  • Table 2 Facultative Lagoon Design Requirements and Compliance Dates.

Type of lagoon and discharge method Primary Basin Loading Design Combined design storage capacity in all basins other than primary basins Compliance Date Type 1: Existing facultative lagoon that discharges or will discharge via effluent irrigation. Primary basin surface area sufficient to ensure a CBOD5

  • f not greater than 25

kilograms/hectare/day and a BOD5 of not greater than 30 kilograms/hectare/day Design storage for 240 days of average day sewage input for the population served. November 1, 2025 Type 2: Expanded, upgraded or new facultative lagoon that discharges or will discharge via effluent irrigation. Primary basin surface area sufficient to ensure a CBOD5

  • f not greater than 25

kilograms/hectare/day and a BOD5 of not greater than 30 kilograms/hectare/day Design storage for 240 days of projected average day sewage input to the population to be served over a projected minimum 20-year design life. Date on which expansion, upgrade or new lagoon is commissioned.

slide-47
SLIDE 47

Wastewater Management Requirements

  • Table 2 Facultative Lagoon Design Requirements and Compliance Dates,

Cont’d.

Type of lagoon and discharge method Primary Basin Loading Design Combined design storage capacity in all basins other than primary basins Compliance Date Type 3: Expanded, upgraded or new facultative lagoon

  • ther than Type 1
  • r Type 2 lagoons.

Primary basin surface area sufficient to ensure a CBOD5

  • f not greater than 25

kilograms/hectare/day and a BOD5 of not greater than 30 kilograms/hectare/day Design storage for 220 days of projected average day sewage input to the population to be served over a projected minimum 20-year design life. Date on which expansion, upgrade or new lagoon is commissioned. Type 4: Existing facultative lagoon

  • ther than Type 1
  • r Type 2 lagoons.

Primary basin surface area sufficient to ensure a BOD5 of not greater than 30 kilograms/hectare/day Design storage for 180 days of average day sewage input for the population served. December 5, 2002

slide-48
SLIDE 48

Requirements, Changes and Implications – WSWR

  • S.13: Upset Reporting – carried over from Water Regs, 2002
  • S.14: Effluent Disinfections – carried over
  • S.15: Record Keeping – Sewage Works – carried over
  • Note: revisions to S. 13, 14 and 15 remove references to industrial effluent

works as these will be managed through the Saskatchewan Environmental Code or the EMPA General Regulations or directly via permits.

slide-49
SLIDE 49

Requirements, Changes and Implications – WSWR

Part III - Waterworks

  • S.16: Through definition of the “Permittee” S16 applies Part III to:

(i) any of the following activities pursuant to section 24 of the Act: (A) operation of a waterworks; (B) construction of a water treatment works; (C) construction of a water distribution works for a system serving fewer than 5,000 people; (ii) an activity in relation to a waterworks for which a permit is required pursuant to section 25 of the Act; or (iii) an activity in relation to a waterworks for which a permit is required pursuant to S. 26 of the Act.

  • Formally adopts the Waterworks Design Standard, EPB 501 – similar to the

Waterworks Design Guide, EPB 201, but revised and updated.

  • Standard provides more detail regarding design than is readily possible directly in

the Regulations, however requirements remain mandatory.

  • Standards can be revised without Code Committee consideration through

Gazette postings.

slide-50
SLIDE 50

Requirements, Changes and Implications – WSWR

  • S.17: Designation of Waterworks
  • Designates and therefore regulates the following waterworksfor human

consumptive use or hygienic use:

  • (a) all municipal waterworks;
  • (b) all municipal wells that are connected to a distribution system;
  • (c) all water pipelines directly connected to a municipal waterworks,

regardless of volume of water supplied or number of service connections;

  • (d) all water pipelines, not otherwise directly connected to a municipal

waterworks or distribution system, serving 15 or more service connections;

  • (e) all waterworks, other than those mentioned in clauses (a) to (d), with

a design flow exceeding 18 cubic metres in any 24-hour period.

  • No change to list of regulated works, although added previously stated

determination of “direct” connections for pipelines.

  • Piping on premise and plumbing within a building are not regulated.
slide-51
SLIDE 51

Requirements, Changes and Implications – WSWR

  • S.19: Compliance Required
  • Requires compliance with this part, cause waterworks to conform with

requirements, inform employees, agents of permittee of the permit and its requirements, and design any new, upgraded, altered or extended waterworks in accordance with the waterworks design standard.

  • S.20: Hygienic Works Requirements – Municipal Systems and

Municipal Wells

  • Unchanged from Water Regulations, 2002.
  • S.21: Hygienic Works Requirements – Pipelines and Other

Systems

  • Unchanged from Water Regulations, 2002.
  • Note: EPB 300 Hygienic Systems policy sets out conditions for classification of

systems as Hygienic – WSA and consultation based decision.

slide-52
SLIDE 52

Requirements, Changes and Implications – WSWR

  • S.22: Wells – Related Requirements - Carry over from Water

Regulations, 2002 with additions – Wells shall have:

  • (a) has a durable well casing;
  • (b) is constructed of new materials;
  • (c) is constructed with a sanitary well cap and maintained to prevent the

entry of surface water, dirt or other material into the well casing;

  • (d) is constructed in a way that ensures the annulus is sealed in order to

prevent vertical fluid migration along the annulus;

  • (e) is constructed in a way that ensures that water will not pool around the

well; and

  • (f) is cleaned and disinfected:
  • (i) during drilling operations;
  • (ii) after the well has been completely constructed but before use; and
  • (iii) each time after:
  • (A) a new pump has been installed; or
  • (B) maintenance or repairs have been carried out on a well or

pump that is connected to the well

  • Added and expanded (c), (d) and (e) to reduce risk and increase safety.
slide-53
SLIDE 53

Requirements, Changes and Implications – WSWR

  • S.23: Pipes: No change from Water Regulations, 2002.
  • No combined trenches, or
  • Separation and orientation in common trenches in accordance with specified

requirements.

  • S.24: Water Storage Reservoirs shall:
  • (a) has a watertight cover;
  • (b) is maintained in a state that is, in the opinion of the minister, of good

repair;

  • (c) in the case of a reservoir that is designed and constructed after the

coming into force of these regulations, meets the following specifications:

  • (i) the reservoir must not have a direct drain connection to a sewer or a

storm drain, and must have appropriate backflow protection;

  • (ii) the reservoir must have convenient access to the interior of the

reservoir for cleaning, maintenance and safety; and

  • (iii) the reservoir must allow for draining and maintenance without

causing loss of pressure in the distribution system; and

  • (d) otherwise complies with this section.
  • Included subsection (c) from former Guide to Waterworks Design, EPB 201.
slide-54
SLIDE 54

Requirements, Changes and Implications – WSWR

  • S.24: Reservoirs, Con’t
  • Included length of tight fitting manhole cover for clarity.
  • All manholes providing access to a reservoir must:
  • (a) be equipped with a tight fitting cover designed to prevent entry of

water that extends down around the frame to at least 50 millimetres.

  • Added (c) and (d) below from former guidelines to regulations.
  • An opening or pipe used to ventilate a reservoir must:
  • (a) be designed to prevent the entry of birds, rodents, rain water or

foreign matter;

  • (b) be screened;
  • (c) be vented separately from any overflows; and
  • (d) be designed and constructed to avoid open construction between

the reservoir sidewall and roof.

  • S.25: Water Treatment Facilities and Pump Houses
  • Minor rewording for clarification only
slide-55
SLIDE 55

Requirements, Changes and Implications – WSWR

  • S.26: Drinking Water Quality Guidelines
  • Adopts most recent edition of National Guidelines, August 2012 summary

table.

  • Compliance with standards, permit and national guidelines remains

mandatory

  • Saskatchewan has typically only applied those national guidelines for

parameters found or likely to be found in provincial waters.

  • S.27: Chemical Treatment Standards for Water
  • Adopted revised NSF/ANSI Standard 60 for drinking water treatment

chemicals to NSF/ANSI 60-2011

  • Any chemicals used for water treatment must still be NSF/ANSI approved or

shown to be equivalent to the Minister.

  • Still must disinfect new, altered, extended or repaired distribution systems

before use

  • Standards for disinfection remain the same:
  • > 0.1 mg/L free residual in water entering the distribution system; and
  • > 0.5 mg/L total or > 0.1 mg/L free residual throughout the dist. system.
slide-56
SLIDE 56

Requirements, Changes and Implications – WSWR

  • S.27: Chemical Treatment Standards for Water – Cont’d
  • May approve alternate disinfection schemes with equivalent or greater level
  • f safety, with agreement/consent of permittee, and as set out in the permit.
  • Where fluoridating, maintain and operate equipment and to achieve fluoride

levels of < 0.7 mg/L.

  • S.28: Standards for constituents in water – new or altered works
  • To meet bacteriological, turbidity and chemical standards when any new or

altered works upon coming into service of works.

  • Upgrades and alterations will trigger the need to meet new/ revised chemical

standards at an earlier date in comparison as to what is prescribed elsewhere.

  • Does not apply to any plans at or beyond the predesign stage as of June 1,

2015.

slide-57
SLIDE 57

Requirements, Changes and Implications – WSWR

  • S.29: Microbial / Bacteriological Water Quality Standards
  • Adopts revised “Standard Method for Examination of Water and Wastewater,

22nd edition, 2012. Replaces faecal coliform standard with E. coli standard.

  • Most important of all WQ standards:
  • Every permittee of a waterworks supplying water intended or used for human

consumptive use or hygienic use shall cause to be maintained throughout the distribution system water that has:

  • (a) the following levels, unless otherwise set out in the permittee’s permit:
  • (i) total coliform levels of zero organisms detectable per 100 millilitres;
  • (ii) Escherichia coli levels of zero organisms detectable per 100 millilitres;

and

  • (iii) background bacteria levels of less than 200 organisms per 100 millilitres
  • r no overgrowth; or
  • (b) if permitted by the permittee’s permit, no presence of total coliform or

Escherichia coli as determined:

  • (i) if required by the permit authorizing the operation of the waterworks, in

the case of microbiological constituents, by initial field presence/absence tests that meet specification 9223 set out in the examination of water and wastewater standards; or

  • (ii) by the method set out in the permittee’s permit.
slide-58
SLIDE 58

Requirements, Changes and Implications – WSWR

  • S.30: Water Turbidity Standards
  • Most source specific turbidity standards remain unchanged.
  • Compliance level for membrane filtration systems moves from 0.1 NTU 95%
  • f time to 0.1 NTU 99% of time in 30(2)(b)(i)(A) and (B) – consistent with

revised national guidelines. Readily achieved by functioning intact membrane systems.

  • Added reference to additional log removal, cyst/oocyst inactivation or

wellhead protection requirements, dependent of consistent with national standards on turbidity. Degraded source water quality at certain times of the year, following significant precipitation events, or as a result of other circumstances, may result in elevated levels of Giardia lamblia and Cryptosporidium parvum which may not be adequately removed based on clauses (a) through (e) requirements alone. This is the latest material emerging from national review of turbidity standards.

  • (f) subject to variations in source water quality resulting in elevated mean

concentrations of Giardia lamblia and Cryptosporidium parvum as determined through source water quality monitoring, any greater water source protection measures, log removal or inactivation for Giardia lamblia and Cryptosporidium parvum as may be required by and in accordance with the timelines set out in the permittee’s permit conditions.

slide-59
SLIDE 59

Requirements, Changes and Implications – WSWR

  • S.30: Water Turbidity Standards – Cont’d.
  • Previous 3-log parasite and 4-log viral standard (S.30(2)(d)) and newer

source water dependent reduction (S30(2)(f)) may be demonstrated through pilot studies or other approved means.

  • Alternative terms and conditions to achieve (d) and (f) may be approved in

consultation with permittee if equal or greater level of protection can be achieved.

  • S.31: Chemical Standards for Human Consumptive Use
  • Added general reference to the need to use appropriate filtration technology

for source water to achieve required standards.

  • Some new/revised DW quality standards with compliance date of July 1,

2020

  • Permittee to provide compliance plan to Minister by July 1, 2017 as to how

standards will be achieved.

  • Those parameters not routinely found in water supplies have a retroactive

compliance timeline – Dec 2010.

slide-60
SLIDE 60

Requirements, Changes and Implications – WSWR

Drinking Water Requirements – See Table 3 of Regulations

  • Revised/New DW Quality Standards
  • Arsenic 10 ug/L (Dec 2010)
  • Bromate 10 ug/L (July 2020)
  • Chlorate 1 mg/L (July 2020)
  • Chlorite 1 mg/L (July 2020)
  • HAA 80 ug/L seasonal running average (July 2020)
  • Microcystin LR 1.5 ug/L (July 2020)
  • Radiological: Gross Alpha and Beta, Lead-210, Radium-226,

Tritium, Strontium-90, Iodine-131, Cesium-137 (per Nat GL) (Dec 2010)

  • MCPA 0.2 mg/L (Dec 2010)
slide-61
SLIDE 61

Requirements, Changes and Implications – WSWR

  • S.32: Waterworks System Assessments
  • Carried over from Water Regulations, 2002, no significant changes.
  • Would a sewage works system assessment be valuable?
  • S.33: Required Notices for Hygienic Systems
  • Carried over from Water Regulations, 2002, no significant changes.
  • Still required to provide twice annual notification to consumers receiving

hygienic use water.

  • S.34: Upset Reporting - Waterworks
  • Carried over from Water Regulations, 2002,
  • Added requirement to report any missing on-site water quality testing

methods.

  • New telephone number 1-844-536-9494 – now a SaskWater service.
  • Waterworks owners, operators, agents, etc. still required to equipment

failures, failure to meet disinfection or more general plant upsets.

  • S.35: Accredited Laboratories
  • Carried over from Water Regulations, 2002, no significant changes.
  • Laboratories still need to be accredited for drinking water related testing they

perform for WSA regulated waterworks.

slide-62
SLIDE 62

Requirements, Changes and Implications – WSWR

  • S.37: Testing and Test Results
  • Adopts revised Bacteriological Standard, EPB 505, Nov 15, 2012. Similar to

former guideline EPB 205.

  • Requirements for sample collection in accordance with permit requirements

remains unchanged.

  • Samples still to be submitted to an accredited lab. May perform in house

testing for chlorine residuals and turbidity.

  • Additional testing still required in the event of exceedences.
  • Labs still required to report results to permittee and Minister (WSA) within 7

days of date of completion of the test. More immediate reporting required for bacteriological exceedences. In turn, permittee is to inform Minister (WSA)

  • f measures to address adverse monitoring results, inform consumers and

take any other measures as directed by the Minister to protect health and public safety.

slide-63
SLIDE 63

Requirements, Changes and Implications – WSWR

  • S.38: Testing After Alteration, Extension, Repair.
  • Carried over from Water Regulations, 2002, no significant changes.
  • Bacteriological water quality testing still required following alteration,

extension or repair of works. Applies to both consumptive and hygienic systems.

  • Commissioning of new systems to typically follow AWWA Standards.
  • S.39: Fluoride in Drinking Water
  • Carried over from Water Regulations, 2002, no significant changes.
  • Samples to be submitted to an accredited lab in accordance with permit

requirements where fluoride is applied to drinking water supplies.

  • S.40: Operational Records
  • Carried over from Water Regulations, 2002, no significant changes.
  • Operational records to be kept in the same manner as under the previous

regulatory framework.

  • Considers what is to be tracked and how. Records to be made available to

the Minister on request.

slide-64
SLIDE 64

Requirements, Changes and Implications – WSWR

  • S.41: Quality Assurance Quality Control Policies
  • Carried over from Water Regulations, 2002. Phase in dates removed.
  • Formally adopts guidelines employed to aid and guide waterworks owners in

developing the QA/QC and Emergency Response Plans.

  • (a) the Quality Assurance and Quality Control for Water Treatment Utilities

Standard - Drinking Water Quality Management, EPB 542, as established by the minister on November 15, 2012;

  • (b) the Waterworks Emergency Response Planning Standard, EPB 540, as

established by the minister on November 15, 2012;

  • (c) the Water Quality Emergency Planning Standard - An Overview, EPB 541A,

as established by the minister on November 15, 2012; and

  • (d) before commencement of operation of the waterworks, the Water Quality

Contingency Planning Standard, EPB 540B, as established by the minister on November 15, 2012.

  • Monthly review of records by permittee and reporting of anomalies, including

missing records (added), is still required.

slide-65
SLIDE 65

Requirements, Changes and Implications – WSWR

  • S.42: Annual Notice to Consumers
  • Carried over from Water Regulations, 2002, no significant changes.
  • Annual notification to consumers on compliance with water quality and

sample submission requirements is still required.

  • Templates exist on SaskH2O web site to aid waterworks owners in preparing

consumer notifications.

  • May notify by paper or electronic means.
  • Copy to Minister (typically EPO) is still required.
  • S.43 to S.71: Operator Certification Board / Operator Certification
  • Carried over from Water Regulations, 2002, no significant changes.
  • Formally adopts the “Saskatchewan Water and Wastewater Works Operator

Certification Standards, EPB 539”, as established by the minister on November 15, 2012, respecting the training and qualifications of operators and the classification of facilities as adopted pursuant to the Adoption of Standards Chapter of the Saskatchewan Environmental Code;

slide-66
SLIDE 66

Requirements, Changes and Implications – WSWR

  • S.72: Easements for Sewage Works
  • Carried over from Water Regulations, 2002, no significant changes.
  • Revised slightly to reflect numbers related revisions in EMPA, 2010.
slide-67
SLIDE 67

Environmental Codes - Status

  • Water Main and Sewer Main Code chapters came into force on

June 1, 2015

  • Coincidental timing with the coming into force of EMPA, 2010 and

The Environmental Management and Protection (Saskatchewan Environmental Code Adoption) Regulations.

  • Adopts various standards used by WSWR,
  • Lays out and formally brings into force various Environmental Code

chapters, Water Main and Sewer Main Code chapters.

  • Jasmine Wang, P. Eng, Senior Standards Engineer, will discuss the code chapter

content and application.

  • Dan McGill will address Enforcement and Compliance in Drinking Water and

Wastewater.

  • Kelly Neuert will address Regional/Contract Operator Program requirements.
slide-68
SLIDE 68

For More Information

  • What’s New and What’s the Same - Comparing The Waterworks

and Sewage Works Regulations & The Water Regulations, 2002

http://www.saskh2o.ca/pdf/epb220.pdf

  • The Environmental Management and Protection Act, 2010:
  • http://www.qp.gov.sk.ca/documents/english/Statutes/Statutes/e10-22.pdf
  • The Waterworks and Sewage Works Regulations:
  • http://www.qp.gov.sk.ca/documents/English/Regulations/Regulations/E10-22R3.pdf

Questions?