CITY OF SOUTH BEND, INDIANA LEEPER Project Information Meeting PARK 12.04.2018 MEETING Project Information Meeting AGENDA 12.04.2018 LEEPER 2 PARK AGENDA The format of the meeting features a formal presentation with an informal open


slide-1
SLIDE 1

LEEPER PARK

Project Information Meeting 12.04.2018

CITY OF SOUTH BEND, INDIANA

slide-2
SLIDE 2

LEEPER PARK

MEETING AGENDA

Project Information Meeting 12.04.2018

2

slide-3
SLIDE 3

LEEPER PARK

AGENDA

  • Project background
  • Park Plans
  • Timeline and next steps
  • Open house discussion

3

The format of the meeting features a formal presentation with an informal open house session following the presentation. The open house session will provide an opportunity to view project displays and to interact with the project team. The purpose of this meeting is to obtain your views regarding the developing plans and proposed park features.

slide-4
SLIDE 4

LEEPER PARK

PROJECT BACKGROUND

Project Information Meeting 12.04.2018

4

slide-5
SLIDE 5

LEEPER PARK

PROJECT BACKGROUND

5

slide-6
SLIDE 6

LEEPER PARK

CONCEPT PLAN

6

Project Information Meeting 12.04.2018

slide-7
SLIDE 7

LEEPER PARK

7

BRIEF HISTORY

1895 East end of park 1902 Central area of park 1905 Beyer Plan, Bugbee Fountain 1912 West end 1915 Kessler Plan, central ridge 1916 Concrete steps 1918 Sunken Garden 1919 Central floral garden 1924-1925 Roses at Sunken Garden 1925-1954 Continued maintenance and improvements 1960’s Ziegler Pavilion 1970’s Powell Home 1997 Landmark designation 1998 Cultural landscape report 2016 Riverfront framework plan 2016 Labyrinth and lavender garden 2018-2019 Design, phase 1 construction

slide-8
SLIDE 8

LEEPER PARK

8

slide-9
SLIDE 9

LEEPER PARK

9

Beyer Plan

slide-10
SLIDE 10

LEEPER PARK

10

Kessler Plan

slide-11
SLIDE 11

LEEPER PARK

11

2016 Framework

slide-12
SLIDE 12

LEEPER PARK

12

slide-13
SLIDE 13

LEEPER PARK

13

Overall Plan

slide-14
SLIDE 14

LEEPER PARK

14

East End

Reservoir Rose Garden Pumping Station Ziegler Pavilion Michigan Street

  • Simple path network
  • Improve access to existing

features

  • Strengthen connection to

neighborhood

  • Riverwalk will extend south

to proposed bridge at Marion Street

slide-15
SLIDE 15

LEEPER PARK

15

  • Repurpose comfort

station as shelter

  • Elevate the Powell

Foundation experience

  • Redesign sensory

gardens along path while maintaining character, provide ADA access

East End

slide-16
SLIDE 16

LEEPER PARK

16

Proposed Phase 1

slide-17
SLIDE 17

LEEPER PARK

17

West End

  • Relocate playground south of tennis courts
  • Closer to parking, restrooms
  • New paths along playground and north to

Riverside Drive

slide-18
SLIDE 18

LEEPER PARK

18

West End

  • Pods of age-related

play equipment

  • Low fence between

play and parking

  • Poured-in-place

safety surface

  • Multipurpose field
  • Use of sail structures

and trees for shade

  • Seating
slide-19
SLIDE 19

LEEPER PARK

19

Central

  • Simple path

network

  • Formal avenue
  • Studebaker

Fountain

  • Overlook at river
slide-20
SLIDE 20

LEEPER PARK

20

Central

slide-21
SLIDE 21

LEEPER PARK

21

Fountain

slide-22
SLIDE 22

LEEPER PARK

22

Fountain

slide-23
SLIDE 23

LEEPER PARK

23

Ornament

slide-24
SLIDE 24

LEEPER PARK

TIMELINE & NEXT STEPS

24

  • Phase 1 Design: Winter, 2018-2019
  • Phase 1 Bidding: Spring, 2019
  • Phase 1 Construction: Late Spring and Summer, 2019
  • Tennis Court Upgrades: Summer, 2019 *
  • Restroom Enhancements: Summer, 2019 *
slide-25
SLIDE 25

THANK YOU

Jonathan Mooney

Lochmueller Group 574.334.5487 jmooney@lochgroup.com

LEEPER PARK

Kyle Silveus

City of South Bend 574.235.9083 ksilveus@southbendin.gov

Matthew Moyers

South Bend Venues Parks & Arts 574.235.7499 mmoyers@southbendin.gov