LBNF/DUNE Beam & Target System John Back, University of Warwick - - PowerPoint PPT Presentation
LBNF/DUNE Beam & Target System John Back, University of Warwick - - PowerPoint PPT Presentation
LBNF LBNF/DUNE Beam & Target System John Back, University of Warwick DUNE UK Meeting March 5, 2019 Introduction Neutrinos from decays of secondary particles ( , ,K): - 120 GeV proton collisions with graphite target, 1.2 MW then
Introduction
2
- Neutrinos from decays of secondary particles (,,K):
- 120 GeV proton collisions with graphite target, 1.2 MW then 2.4 MW
- 3-horn focusing system, ~2m long (4) graphite target
- See Beam Optimisation Task Force report: DUNE-doc-2901
- High Power Target RAL group (Chris Densham et al.) is to build
the target:
- Fermilab will do Horns & rest of Target Station (e.g. shielding)
- News on:
- RAL target proposal & preliminary designs
- Target physics performance
LBNF Beamline Layout
3
Fig from DUNE-doc-7338
Target Station Geometry
4
Fig from DUNE-doc-7554
RAL “LBNF/DUNE Beam & Target System” Project
5
- Phase 1: Jan 2019 – Mar 2022: design, prototyping & costing
- Successful full funding obtained from STFC (~£1.4M)
- Very strong science case & impact recognised by Projects Peer
Review Panel (PPRP) and Accelerator Strategy Board (ASB)
- No project descoping maximises design phase effort
- Phase 2: Apr 2022 – Mar 2026: procurement & manufacture
- Proposal due 1st half 2021 for PPRP review (~£4.6M)
- Phase 3: Apr 2026 – Sept 2028: installation & commissioning
- Dates depend on international project schedule
- Sept 2028 onwards: ongoing maintenance & support similar to T2K
Target Project Priority List
6
- Design & build 1 prototype & 1 operational target (1.2 MW)
- Design & build target support & interface with 1st magnetic horn
- Design & build target remote handling/replacement system
- Specify, select & supply master-slave manipulators
- Specify & supply key components for He target cooling plant
- Design & build instrumented collimator, protecting downstream
components from missteered beam
2m Target with Downstream Support
7
2m Target with Downstream Support
8
Double (2 x 1m) Target Concept
9
Target 1 Target 2 Horn current striplines Beam
Upstream Target He Cooling
10
Double (2 x 1m) Target Downstream Detail
11
He flow
Single Cantilevered Target
12
CP Sensitivity vs Target Length: Geant4 studies
13
3+3 years running, normal hierarchy, 120 GeV protons, 1.2 MW power, target R = 8 mm, beam = R/3
Summary
14
- Successful STFC funding for Phase 1 target engineering design
- Investigating 3 graphite target options:
- Single ~2 m cylinder with upstream & downstream supports
- Double (2 x ~1m) cylindrical target
- Single ~1.5 m cantilevered target (upstream support only)
- Detailed design work by RAL:
- Target supports, interface with 1st horn, alignment & He cooling
- Assuming full 2.4 MW beam power
- Checking physics performance with Geant4 (Warwick)
LBNF Beamline Schedule (DUNE-doc-7338)
15
FY28 FY27 FY26 FY25 FY24 FY23 FY22 FY21 FY20 FY19 FY18
March-30 CD-4 (early completion)
FY29
Dec-19 CD-2/3b Project Baseline & FS
- Constr. Approval
Primary Beam Enclosure Beneficial Occupancy Conventional Facilities Construction Complete Absorber Hall Beneficial Occupancy Beamline Complete March-22 CD-3 NS
- Constr. Approval
FY30
Target Hall Beneficial Occupancy
Extraction Enclosure (Long Shut Down) Primary Beam Enclosure
Magnets Horns Target Shield Pile Disassemble MI Components Conventional Construction Install New / Existing Components Upstream of Shield Wall - completed during long shut down Downstream of Shield Wall
Beamline Design Target Hall Beamline Checkout Period
Install Target Shield Pile Mechanical and Electrical Rough-in Install Horn A, B, C and initial Power-up Absorber Component Installation Remote Handling and Muon DAQ Mechanical and Electrical Rough-in Remote Handling Commissioning
Start MI Long Shutdown
Procurement and Assembly