LBNF/DUNE Beam & Target System John Back, University of Warwick - - PowerPoint PPT Presentation

lbnf dune beam target system
SMART_READER_LITE
LIVE PREVIEW

LBNF/DUNE Beam & Target System John Back, University of Warwick - - PowerPoint PPT Presentation

LBNF LBNF/DUNE Beam & Target System John Back, University of Warwick DUNE UK Meeting March 5, 2019 Introduction Neutrinos from decays of secondary particles ( , ,K): - 120 GeV proton collisions with graphite target, 1.2 MW then


slide-1
SLIDE 1

LBNF

LBNF/DUNE Beam & Target System

John Back, University of Warwick DUNE UK Meeting March 5, 2019

slide-2
SLIDE 2

Introduction

2

  • Neutrinos from decays of secondary particles (,,K):
  • 120 GeV proton collisions with graphite target, 1.2 MW then 2.4 MW
  • 3-horn focusing system, ~2m long (4) graphite target
  • See Beam Optimisation Task Force report: DUNE-doc-2901
  • High Power Target RAL group (Chris Densham et al.) is to build

the target:

  • Fermilab will do Horns & rest of Target Station (e.g. shielding)
  • News on:
  • RAL target proposal & preliminary designs
  • Target physics performance
slide-3
SLIDE 3

LBNF Beamline Layout

3

Fig from DUNE-doc-7338

slide-4
SLIDE 4

Target Station Geometry

4

Fig from DUNE-doc-7554

slide-5
SLIDE 5

RAL “LBNF/DUNE Beam & Target System” Project

5

  • Phase 1: Jan 2019 – Mar 2022: design, prototyping & costing
  • Successful full funding obtained from STFC (~£1.4M)
  • Very strong science case & impact recognised by Projects Peer

Review Panel (PPRP) and Accelerator Strategy Board (ASB)

  • No project descoping  maximises design phase effort
  • Phase 2: Apr 2022 – Mar 2026: procurement & manufacture
  • Proposal due 1st half 2021 for PPRP review (~£4.6M)
  • Phase 3: Apr 2026 – Sept 2028: installation & commissioning
  • Dates depend on international project schedule
  • Sept 2028 onwards: ongoing maintenance & support similar to T2K
slide-6
SLIDE 6

Target Project Priority List

6

  • Design & build 1 prototype & 1 operational target (1.2 MW)
  • Design & build target support & interface with 1st magnetic horn
  • Design & build target remote handling/replacement system
  • Specify, select & supply master-slave manipulators
  • Specify & supply key components for He target cooling plant
  • Design & build instrumented collimator, protecting downstream

components from missteered beam

slide-7
SLIDE 7

2m Target with Downstream Support

7

slide-8
SLIDE 8

2m Target with Downstream Support

8

slide-9
SLIDE 9

Double (2 x 1m) Target Concept

9

Target 1 Target 2 Horn current striplines Beam

slide-10
SLIDE 10

Upstream Target He Cooling

10

slide-11
SLIDE 11

Double (2 x 1m) Target Downstream Detail

11

He flow

slide-12
SLIDE 12

Single Cantilevered Target

12

slide-13
SLIDE 13

CP Sensitivity vs Target Length: Geant4 studies

13

3+3 years running, normal hierarchy, 120 GeV protons, 1.2 MW power, target R = 8 mm, beam  = R/3

slide-14
SLIDE 14

Summary

14

  • Successful STFC funding for Phase 1 target engineering design
  • Investigating 3 graphite target options:
  • Single ~2 m cylinder with upstream & downstream supports
  • Double (2 x ~1m) cylindrical target
  • Single ~1.5 m cantilevered target (upstream support only)
  • Detailed design work by RAL:
  • Target supports, interface with 1st horn, alignment & He cooling
  • Assuming full 2.4 MW beam power
  • Checking physics performance with Geant4 (Warwick)
slide-15
SLIDE 15

LBNF Beamline Schedule (DUNE-doc-7338)

15

FY28 FY27 FY26 FY25 FY24 FY23 FY22 FY21 FY20 FY19 FY18

March-30 CD-4 (early completion)

FY29

Dec-19 CD-2/3b Project Baseline & FS

  • Constr. Approval

Primary Beam Enclosure Beneficial Occupancy Conventional Facilities Construction Complete Absorber Hall Beneficial Occupancy Beamline Complete March-22 CD-3 NS

  • Constr. Approval

FY30

Target Hall Beneficial Occupancy

Extraction Enclosure (Long Shut Down) Primary Beam Enclosure

Magnets Horns Target Shield Pile Disassemble MI Components Conventional Construction Install New / Existing Components Upstream of Shield Wall - completed during long shut down Downstream of Shield Wall

Beamline Design Target Hall Beamline Checkout Period

Install Target Shield Pile Mechanical and Electrical Rough-in Install Horn A, B, C and initial Power-up Absorber Component Installation Remote Handling and Muon DAQ Mechanical and Electrical Rough-in Remote Handling Commissioning

Start MI Long Shutdown

Procurement and Assembly