KENSINGTON COMMUNITY REFERENCE GROUP
MEETING 9 11 FEBRUARY 2020
KENSINGTON COMMUNITY REFERENCE GROUP MEETING 9 11 FEBRUARY 2020 - - PowerPoint PPT Presentation
KENSINGTON COMMUNITY REFERENCE GROUP MEETING 9 11 FEBRUARY 2020 PLANNING PREVIOUS APPROVALS Early Works Plan amendment approved 24/12/2018 Site establishment commenced 29/01/2019 Western Portal Development Plan approved May 2019
KENSINGTON COMMUNITY REFERENCE GROUP
MEETING 9 11 FEBRUARY 2020
Proposed updates include:
access to the rail corridor for maintenance as required Next steps:
days from Monday 9 March 2020 until 5pm, Friday 27 March 2020
Completed activities
feedback
Next Steps
feedback (Timing TBC)
letterbox drop and social media (Timing TBC)
February Feedback received during Development Plan public display period:
Ponds Creek corridor
Communication and engagement to support:
Out of hours works
impacted residents
wider community
Tunnelling
properties Remaining D-wall work program
impacted residents
Hobsons Road car park usage
station entrance
Notifications and communications
Door knocks, meetings, briefings and events
Key issues raised during December and January Out of hours works
JJ Holland park flooding
Activity Feb Mar Apr May Jun Jul
TBM retrieval shaft construction Tunnelling – Arden to Kensington TBM retrieval Cross passage ground improvement reinstatement Cross passage construction (underground works) Diaphragm wall construction Capping beams Tunnel entrance propping/excavation/base slab Rail corridor works RIA tunnel entrance roof slab
Program is indicative and subject to change
TBM RETRIEVAL SHAFT WATERPROOFING
TBM RETRIEVAL SHAFT CONSTRUCTION
DIVIDING WALL AND RECEPTION SEAL
BARRIER REALIGNMENT PREPARATION
Why doesn’t the Western Portal site have an acoustic shed?
Vibration Impact Assessment (CNVIA)
What has CYP put in place to limit noise impacts?
North Melbourne to Kensington TBM Joan
TBM Meg
1. TBM Modelling – Vibration
EPR NV8 criteria
Monitored Modelled
EPR NV13 criteria
10 20 30 40 50 60 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
Distance from TBM1 to VIB10 Vibration
TBM1 Surface PPV
Distance ppv_vert 30 per. Mov. Avg. (Distance) 30 per. Mov. Avg. (ppv_vert)
Preparatory works
Retrieval works
retrieval shaft
Retrieval site layout
Indicative only
Dismantling layout plan
Indicative only
Indicative only
Communications to potentially impacted properties
Tunnelling information sessions – North Melbourne to Kensington (second round)
D-walls Capping beams Excavation, drainage and concreting works
Program is indicative and subject to change
D-walls Capping beams Excavation, drainage and concreting works Install temporary propping
Program is indicative and subject to change
D-walls Capping beams Excavation, drainage and concreting works Install permanent propping
Program is indicative and subject to change
TEMPORARY PROPPING EASTERN PORTAL