jonathan revtai senior thesis presentation
play

Jonathan Revtai - Senior Thesis Presentation 6425 Penn Avenue - PowerPoint PPT Presentation

Jonathan Revtai - Senior Thesis Presentation 6425 Penn Avenue Option: Construction Management Pittsburgh, PA Advisor: Dr. Riley Introduction Lightweight Mezzanine Analysis General Project Overview Pile Cap Redesign Green


  1. Jonathan Revtai - Senior Thesis Presentation 6425 Penn Avenue Option: Construction Management Pittsburgh, PA Advisor: Dr. Riley

  2.  Introduction  Lightweight Mezzanine Analysis  General Project Overview  Pile Cap Redesign  Green Gym Analysis  Summary & Conclusion  Acknowledgements • M.A.E Research

  3.  Bakery Square  Retail – 42,000 sq. ft. • 5 Buildings Onsite • 1st Floor  Fitness Center - 59,500 sq. ft.  Building 1 • 2 nd – 3 rd Floor • $24 Million GMP • 378,000 sq. ft.  Parking Garage – 276,500 sq. ft. • Multi-use Facility • 1st – 6 th Floor • 850 Spaces

  4. • Located in East Liberty Bakery Square • Corner of Penn Ave. & East Liberty Blvd. • Building 1 Footprint Designated by Green

  5. Bakery Square • Limited utility lines within Building 1 footprint • Building 1 is situated on existing asphalt parking • Underground railway tracks are present in • Building 1 Footprint Designated by Green unknown locations • Blue Areas Required Demolition

  6.  Parking Garage  Retail  Fitness Center • Auger Cast Pile Foundation • Auger Cast Pile Foundation • Hanging Steel Mezzanine Level • 6 Story Precast Concrete Structure • Slab-on-Grade Floor • Precast Concrete Shell • Fluorescent Lighting • Rooftop Unit Mechanical System • Cast-In-Place Elevated Pool

  7.  Research Goal  Gym’s Energy Needs • Incorporate “green” technology and • Lighting system mainly fluorescent materials to create a more lights with some incandescent bulbs sustainable fitness center • Calculations based on ASHRAE 90.1  Sustainable Design • Electric Generating Bicycle • Fitness Center uses 42,000 watts • Piezoelectric Floor Tiles • Bamboo Flooring

  8.  Bicycle Generator • Transforms mechanical energy to electrical energy Description Cost per Unit Units Cost Equipment $500 25 $12,500 • Energy produced by average Inverter $500 1 $500 bicyclist: Installation $3,000 1 $3,000 ▪ 150 watts for extended periods ▪ 275 watts peak Total $16,000

  9.  Bicycle Generator  Piezoelectric Floor Tiles • $100 per square foot • Transforms mechanical energy to • Used in Taiwan subway station and electrical energy London dance club • 3,000 square feet of track • Energy produced by average • Calculations based on: • Reduces energy load by 14% bicyclist: ▪ 132 pound walker ▪ 150 watts for extended periods ▪ 140 steps per minute ▪ 275 watts peak • Walking induced vibrations transformed into electrical energy

  10.  Bamboo Flooring  Plyboo Sport • Use more sustainable materials • 6,000 square feet of area • Bamboo has a shorter harvest cycle • $7.75 per square foot for material than standard maple floors and installation costs • Compared to maple floor System Cost/ SF Area Total Cost Maple Concord II $10.50 6,000 $63,000 Plyboo Sport $7.75 6,000 $46,500

  11. Description Daily Power Yearly % of System Cost/ SF Area Total Cost (WH) Cost Load Maple Concord II $10.50 6,000 $63,000 Bike Room 5,736 $209 - Plyboo Sport $7.75 6,000 $46,500 Fitness 504,000 $18,396 -  Based on $0.10 per KW-Hr Center Bicycles – 20,280 $740 4.0%  Energy prices will double soon 50% Bicycles – 30,360 $1,108 6.0%  Efficiencies and material costs 75% should improve Bicycles – 40,500 $1,478 8.0% 100% Piezoelectric 69,300 $2,529 13.8%

  12.  Background  System Information • Expanded research on sustainable • Replace fluorescent lights with LED design which are more efficient and last longer • Focused on Parking Garage • Motion sensing equipment used to lower and raise lighting levels • Adoption of a LED Bi-level lighting depending on use system in place of fluorescent lights

  13.  UC Davis Case Study  Bakery Square Application  LED Bi-level System Savings • Fluorescent lights Description Daily Daily Yearly % of Load • Lighting Load = 81,000 watts Design Outcome Power Cost Cost (WH) Light Quality CRI 22 to CRI 80 • Assumed lights are on 12 hours per Parking Garage 977,000 $97.70 $35,672 - LED Energy Savings 40% less energy day year round Bi-Level LED 586,400 $58.64 $21,403 60% Bi-Level Energy Savings 30% less energy Maintenance Savings 6 times longer lifespan

  14.  Existing Structure  Goals • Structural Steel with Composite • Reduce costs Decking • Reduce schedule  Lightweight Alternatives • Wire Rope • Maintain mezzanine layout and aesthetic appeal • Precast Concrete • Steel Joist

  15.  Wire Rope  Precast Concrete • Open space design • Easily attached with superstructure • Requires many precast concrete • Cheap alternative embeds • Alters floor plan and aesthetic look • Concerns of floor vibrations, especially around the track • Requires more crane time

  16.  Steel Joist System  Assumptions • Eliminates need for precast crane • Live load = 100 psf • Dead load = 57 psf + joists • Easily attached to superstructure • Typical bay size = 34’ x 62’ • Retains open floor plan • Dead Space in floor plan may be eliminated

  17. Member Count Weight (Ton) Unit Cost Total Cost  Steel Joist Members Joists 60 73.2 $2,898 $212,100 • Joist – 44LH17 Girders 12 25.5 $2,249 $57,300 ▪ 62’ span Total 72 98.7 - $269,400 ▪ 83.2 kip load  Cost Comparison • Girder – 36G6N83.2 • Structural Steel - $341,500 ▪ 34’ span ▪ 505 kip load • Steel Joist - $269,400

  18.  Schedule Comparison  Summary • Reduces precast crane time by 4 • Reduce mezzanine structure costs by days 21% • Allows construction of mezzanine to • Reduce schedule by 4 days start earlier • Maintain aesthetic appeal from original design

  19.  Mechanical Breadth • Relocate mechanical system to open southern façade in fitness center • Required redesign of mechanical system • Resulted in a higher upfront cost, but reduced operational costs and created better aesthetics

  20.  Research Background • Triangular pile caps had a significantly lower production rate • Redesign of the pile cap should reduce costs and schedule length • Used as a structural breadth

  21.  Load Requirements  Assumptions & Calculations • Live Load = 106 kips • Dead Load = 412 kips Description Load (PSF) Floor Live Load 100 • Pile diameter = 18” Garage Live Load 40 Stairs & Lobby Live Load 100 • f’c = 3,000 psi Roof Live Load 30 Snow Load 25 • Column Dimension = 30” x 42”

  22.  Pile Cap Design  Pile Cap Comparison • 6’ - 6” x 6’ - 6” Description Triangular Square • 42” deep Formwork $744 $564 Concrete Material $769 $608 • #11 bars spaced 12” o.c. Concrete Placing $80 $63 Rebar $318 $393 Total $1,911 $1,628

  23.  Schedule Comparison  Redesign Results • Productivity of Formwork ▪ Triangular – 140 sq. ft. / day ▪ Square – 176 sq. ft. / day Comparison Results Cost Savings Per Pile Cap $283 • Multiplied by 31 type PC3 pile caps Total Cost Savings $8,773 Schedule Reduction 5 Days • Reduces schedule by 5 days

  24.  Green Gym Analysis  Lightweight Mezzanine Analysis  Pile Cap Analysis • Increased costs • Reduces construction costs by 21% • Reduces costs by $8,773 • Reduction in operational costs • Reduces schedule by 4 days • Reduces schedule by 5 days • Successfully incorporates “green” • Maintains open floor plan and technologies and materials aesthetic appeal from original design

  25. • Shane Allison • Michael Koza • Dino Bagatelas • Kevin Parfitt • Anthony Dolan • Eric Pascucci • Dave Fields • Gregg Perelman • Colin Fink • Bill Porter • Darryl Fink • Todd Reidbord • Linda Hanagan • David Riley • Robert Holland • Steven Schrader • Michael Horman • Justin Jones • Friends and Family

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend