Investor Presentation February 2017 Forward-looking statements - - PowerPoint PPT Presentation

investor presentation
SMART_READER_LITE
LIVE PREVIEW

Investor Presentation February 2017 Forward-looking statements - - PowerPoint PPT Presentation

Investor Presentation February 2017 Forward-looking statements This presentation may contain forward-looking statements and information that both represents management's current expectations or beliefs concerning future events and are subject


slide-1
SLIDE 1

Investor Presentation

February 2017

slide-2
SLIDE 2

Forward-looking statements

This presentation may contain forward-looking statements and information that both represents management's current expectations or beliefs concerning future events and are subject to known and unknown risks and uncertainties. A number of factors could cause actual results, performance or events to differ materially from those expressed or implied by these forward-looking statements.

February 2017 | P1

slide-3
SLIDE 3

Cost reductions delivered High operating efficiency Step change in production Continued portfolio upgrading Refinancing in progress

2016 highlights 1 2 3 4 5

2016 2017E 91% >90% 2015 2016 2016 Q4 58 kboepd 71.kboepd >80 kboepd E.ON acquisition case 2016 2H 15 kboepd 17 kboepd 2014 opex 2016 opex $18.5/boe $15.7/boe Drawn Debt Total Facilities (incl LCs) $3.4 bn $4 bn

Undrawn February 2017 | P2

slide-4
SLIDE 4

Indonesia

  • >90% operating efficiency
  • Strong demand (44% of GSA 1, record

GSA 2 delivery)

  • $10/boe opex
  • Increase demand post 2020

– Quick payback, high return projects – Bison, Iguana, Gajah Puteri

  • Longer term growth opportunities

– Tuna, 3rd party business

Asia – providing cash flow for the business

Vietnam

  • >90% operating efficiency
  • <$9/boe opex
  • Further cost reductions

– Renegotiation of vessel and helicopter contracts – Revised terms for FPSO agreed

  • High return, low cost projects include

infill drilling in 2017

Low cost, high return

  • pportunities to

maintain / grow production

February 2017 | P3

slide-5
SLIDE 5

UK North Sea – growth story

Wytch Farm (30.1%)

  • Long life field
  • Infill opportunities

Solan (100% op)

  • Production currently restricted at

10-13 kbopd

  • Cost reductions continue to be

secured UK overview

  • Improved uptime
  • UK drives production growth:
  • Strong operating base
  • Tax advantaged position

Babbage (47%)

  • High uptime
  • Moving to unmanned
  • Cobra potential tie-back

Elgin-Franklin (5.2%)

  • Long life field
  • Rates of >130 kboepd (gross)
  • On-going infill drilling and well

intervention programme Huntington (100% op)

  • Strong reservoir performance
  • 2016 production significantly

above budget Catcher (50% op)

  • On track for first oil 2017
  • 29% cost reduction secured

Tolmount (50% op)

  • Low cost, high return project
  • Significant area upside
  • Tolmount East +250 bcf
  • Tolmount Far East +150 bcf

February 2017 | P4

2015A 2016A 2017E 2018E

UK production

slide-6
SLIDE 6
  • Templates, flowline bundles, midwater

arches and gas export pipeline installed

  • Buoy and moorings system installed
  • Hook up of risers & umbilicals completed
  • Subsea programme

below budget

Subsea

  • 9 wells drilled with excellent operational

performance

  • Pre-drill predictions for reservoir

quality and flow rates at

  • r above prognosis
  • Drilling programme

below budget

Catcher – ahead of plan

Burgman BP3 producer well Tay reservoir

Drilling

February 2017| P5

slide-7
SLIDE 7

February 2017 | P6

Module lifts onto Catcher FPSO completed

  • Outfitting of FPSO progressing well
  • 13/13 modules lifted onto FPSO
  • ~2,000 people working on the vessel
  • On track for summer 2017 FPSO sailaway
slide-8
SLIDE 8

Catcher schedule

2017 2016 2H

  • Plateau rates of 50 kboepd (gross)
  • $1.6bn total project cost
  • Potential further savings from contingency

release and FX

  • Forward cost exposure reduced significantly

BP3 & BP 5 completed Drilling at Varadero (4 wells) Installation

  • f Buoy

and Mooring System Module Lifts Installation

  • f risers

Hull mated Onshore pre-comm and comm Drilling at Burgman (2 wells) FPSO transit to Catcher field FPSO buoy and hook-up

First oil

February 2017 | P7

Drilling at Catcher (4 wells)

* Assumes $1.25/£ to end 2017, then $1.3/£ and 20 wells drilled

Topsides integration

Capex - 29% reduction in costs secured * $mm

50 100 150 200 250 300 350 2014 2015 2016 2017

Sanctioned budget Actual/current forecast

slide-9
SLIDE 9

Tolmount – next phase of growth

Indicative metrics (gross)

  • 450 Bcf
  • Capex <$600m
  • Opex: c.$7/boe
  • Peak production : 200 mcfd
  • First gas 2020

High return project in a low gas price environment

Timetable to sanction

  • Concept select Q1

– Standalone, normally unmanned or subsea tie-back to nearby facilities

  • Project optimisation

– Capex reducing – Potential 3rd party funding

  • FID targeted for 2017/early

2018

  • Partial sales process underway

February 2017 | P8

slide-10
SLIDE 10

Southern Gas Basin: portfolio of opportunities

Babbage (47% op)

  • Infill opportunities

Ravenspurn Deep (5% carried interest)

  • BP/Perenco long-reach well planned

for late 2016 Newton (50% op) Cobra (50% op)

  • 250 Bcf gas discovery
  • Potential tie back to Babbage

30km radii

Portfolio of opportunities which are economic at <30p/therm

February 2017 | P9

Minerva

Tolmount (50% op)

  • Discovered Oct 2011
  • 2 appraisal wells in 2013
  • 450 bcf of resource
  • Largest UK gas discovery since Breagh in 1997
  • Significant upside (E.Tolmount, Malin)
slide-11
SLIDE 11

February 2017 | P10

  • Licence extended to 2020
  • Good progress on FEED in 2016

– Facilities capex and opex cost estimate reductions from FEED contractors’ collaboration – Logistics and drilling cost estimate reductions following extensive market engagement – $45/bbl current estimated breakeven price

  • Forward focus on commercial and fiscal work

streams & securing a financing solution for the development

Estimated capex to first oil now $1.5bn

Sea Lion Phase 1 – reducing breakeven price

slide-12
SLIDE 12
  • Sureste Basin is a prolific

hydrocarbon province (62 bn bbls of proven oil)

  • Exercised option to increase to

25% in Block 7 − Shallow water (<150m) − Same salt flanks and sub- salt plays as the US Gulf of Mexico − Large Zama well to spud early Q2

Mexico – potential for material value creation

2017 - 2018 2016 2H

Delivery of reprocessed 3D seismic across 2 blocks Confirm final drilling candidates Tender for a moored, semi- sub rig for Block 7 First exploration well on Block 7 First exploration well on Block 2 February 2017 | P11

Flat Spot

Zama Prospect

slide-13
SLIDE 13

Net debt & refinancing update

February 2017 | P12

Debt type Description Facility size Maturity Bank debt RCF & LC US$2.5bn 2019 Bank debt Term Loan US$300m

  • Dec. 2017

US Bonds Private Placement US$380m No maturity before 2018 German Bonds Schuldschein US$130m 2018 & 2020 UK Bonds Convertible US$245m 2018 UK Bonds Retail bond GBP150m 2020

Private lenders Publically traded debt

  • Long form term sheet agreed and circulate to lenders for formal credit committee

approval

− Preservation of the full amount of existing facilities including undrawn amounts − Alignment of all maturities to 2021 or later − Amendment of the group’s financial covenants − Provision of a comprehensive security package to lenders − Enhanced economics to lenders − Certain governance controls

  • Aim to have creditors locked up to the final terms during February
  • Negotiations with convertible bondholders ongoing

Net debt of $2.8bn, marginally down from Q3 Cash and undrawn facilities of

  • c. $600m
slide-14
SLIDE 14

2016 2018 Infills Tolmount Sea Lion $2.25bn $1.6bn Sanctioned budget Forecast

Maintain competitive cost base Continuing production growth Catcher delivery Select highest return projects for sanction Deliver debt reduction

Outlook 1 2 3 4 5

20% >50% 30% 2016 Solan Catcher $15.7/boe 5.2x 3x $12/boe $20/boe

February 2017 | P13

2016 2017 2018 IRR Net debt/ EBITDAX

slide-15
SLIDE 15

Premier Oil Plc 23 Lower Belgrave Street London SW1W 0NR Tel: +44 (0)20 7730 1111 Fax: +44 (0)20 7730 4696 Email: premier@premier-oil.com www.premier-oil.com February 2017