Indonesia - Gajah Baru development update 23 June 2010 Forward - - PowerPoint PPT Presentation

indonesia gajah baru development update 23 june 2010
SMART_READER_LITE
LIVE PREVIEW

Indonesia - Gajah Baru development update 23 June 2010 Forward - - PowerPoint PPT Presentation

Indonesia - Gajah Baru development update 23 June 2010 Forward looking statements This presentation may contain forward-looking statements and information that both represents management's current expectations or beliefs concerning future


slide-1
SLIDE 1

23 June 2010 Indonesia - Gajah Baru development update

slide-2
SLIDE 2

June 2010 | Page 1

Forward looking statements

This presentation may contain forward-looking statements and information that both represents management's current expectations or beliefs concerning future events and are subject to known and unknown risks and uncertainties. A number of factors could cause actual results, performance or events to differ materially from those expressed or implied by these forward-looking statements.

slide-3
SLIDE 3

June 2010 | Page 2

Gajah Baru project update

Contents

  • Natuna Sea Block A development overview
  • Gajah Baru development
  • Project Metrics
  • Accomplishments and Key Achievements
  • Key Dates and Overall Level 1 Schedule
  • Execution highlights
  • Project Graphics & Progress Photographs
  • Project Management Team (PMT)
  • Key Events for 2H 2010
slide-4
SLIDE 4

June 2010 | Page 3

Natuna A Block development plan

Anoa / AGX Complex Gajah Baru Hub Domestic Gas Delivery – Batam (GSA3&4) International Gas Delivery – Singapore (GSA2) Gajah Puteri (future) Pelikan, Naga, Iguana & Bison (future)

slide-5
SLIDE 5

June 2010 | Page 4

Gajah Baru development overview

slide-6
SLIDE 6

June 2010 | Page 5

EPCI summary and split in scope of work

Engineer, Procure, Construct & Install (EPCI) Contract is a joint venture between Saipem* and SMOE

  • Saipem responsible for:
  • Engineering and procurement of materials and packaged equipment
  • Load out, transportation and installation of all components
  • SMOE responsible for:
  • CPP Topsides, living quarters, flare boom & bridge
  • Offshore hook-up of all components and pre-commissioning
  • Nippon Steel Batam (NSB) responsible for:
  • Wellhead Deck
  • Wellhead Jacket, Piles & Conductors
  • CPP Jacket & Piles
  • Premier Oil responsible for commissioning with Contractor’s assistance

* Saipem consortium leader

slide-7
SLIDE 7

June 2010 | Page 6

Project metrics

  • Design Life – 20 years for Facilities, 50 Years for Pipeline
  • Integrated Float-over Deck design, minimal Hook-Up
  • Fabrication Durations
  • CPP Topsides = 18 months
  • Living Quarters = 13 months
  • Component Weight
  • CPP Topsides – 8,000 tonnes (including 800 tonne LQ module)
  • Design Output
  • 2 Turbocompressor packages supplied each with initially HP stage only and plinth for

future supplied LP stage – Initial HP stage sized to export MR at 1750 psia ( i.e. 2x100% versus MR).

– Between 2012 / 2015 LP Stage added to plinth and capacity of combined HP/LP train reduced to 50% of MR

  • 1 No. Turbocompressor package supplied initially with both HP and LP stages and

train sized to export 50% of MR at 1750 psia from a suction pressure of 255 psia

slide-8
SLIDE 8

June 2010 | Page 7

Key schedule dates

KEY MILESTONES CONTRACTUAL MILESTONES

2009 2010 2011

Install WHP Jacket & Deck 3Q Delivery of CPP Compressors 2Q Install Export Pipeline 2Q Install CPP Jacket & Deck 2Q Delivery of CPP Vessels 1Q 4Q 4Q 3Q FIRST GAS 01 Oct 2011 WHP Facility Ready for Drilling 01 Oct 2010 Mechanical Acceptance 15 Sep 2011

slide-9
SLIDE 9

June 2010 | Page 8

Execution plan highlights

  • Long Lead Item (LLI) procurement
  • Premier pre-purchased and then transferred nine orders including WHP Steel and CPP Compressors and Generators

and large Pressure Vessels

  • Initially bid project at peak steel price and an overheated market
  • Re-bid as prices in excess of AFE limit, relaxed single yard requirement
  • Revised final price ~US$ 100 million lower
  • Managing delay of award of contract
  • Maintained engineering with short listed bidders through final negotiations
  • Close Government liaison on project approvals
  • GOI maintains certification process, bi-annual work plan & budget reviews, quarterly progress meetings at yards
  • Highest local content – new benchmark >30%
  • Independent verification body audits underway
  • Early installation of Wellhead Platform to allow early development drilling
  • Premier has extensive experience working with NSB yard, viz.

– AGX Compression Platform (2000-2001) and West Lobe WHP (2005-2006) – Both facilities delivered and installed on schedule

slide-10
SLIDE 10

June 2010 | Page 9

Execution plan highlights

  • Export Pipeline Tie-In to WNTS
  • To be undertaken to avoid interruption of gas export from Anoa
  • PMT influenced EPCI contractors’ decision to proceed with Integrated Deck Float-over

design as opposed to conventional module design

  • Maximizes onshore pre-commissioning and consequently greatly reduces offshore Hook-Up duration
  • PMT actively involved in initial equipment layout concepts
  • Including positioning of major pieces of equipment on Cellar and Mezzanine Decks
  • PMT planning efforts have included the following:
  • Sequence of equipment erection including early identification of critical pieces required to be delivered before stacking
  • f deck panels
  • Thorough reviews of planned construction and outfitting of Technical Buildings
  • Providing assistance in defining pipe spool erection sequence on an area basis
  • Premier stationed a Living Quarters specialist in Singapore to liaise with SM0E on 60 man

LQ design

  • Also reviewed procurement recommendations and
  • Ensured clash free interfaces between LQ and CPP Topsides
slide-11
SLIDE 11

June 2010 | Page 10

Wellhead platform (WHP) 3D CADD model

Cellar Deck Main Deck Wellhead Control Panel Well Bay

slide-12
SLIDE 12

June 2010 | Page 11

Wellhead platform (WHP) 3D CADD model

Well Bay Area (Plan) Well Bay Area (Elevation looking South)

slide-13
SLIDE 13

June 2010 | Page 12

Gajah Baru – Wellhead platform (WHP)

Wellhead Deck ~800 tonnes Wellhead Jacket ~1,500 tonnes Piles & Conductors ~1,200 tonnes

slide-14
SLIDE 14

June 2010 | Page 13

Gajah Baru – Central processing platform (CPP)

CPP Topsides - ~8,000 tonnes

  • 3 x MAN Turbo Gas Compressors c/w Solar

Turbine drivers (GTCs)

  • 2 x Solar Gas Turbine Generators (GTGs)
  • 60 man Living Quarters
  • Bridge linked to Wellhead Platform

Cellar Deck Main Deck Flare Boom Bridge to WHP GTGs GTCs ACHEs

slide-15
SLIDE 15

June 2010 | Page 14

Gajah Baru – Central processing platform (CPP)

Main Deck frame (to be stacked on Cellar Deck July 2010) CPP Topsides ~8,000 tonnes Cellar Deck frame and support columns

slide-16
SLIDE 16

June 2010 | Page 15

Gajah Baru – Central processing platform (CPP)

CPP Jacket ~4,800 tonnes Piles ~1,200 tonnes

slide-17
SLIDE 17

June 2010 | Page 16

Gajah Baru – Central processing platform (CPP)

60 man living quarters

slide-18
SLIDE 18

June 2010 | Page 17

Gajah Baru – Central processing platform (CPP)

60 man living quarters (~800 tonnes)

slide-19
SLIDE 19

June 2010 | Page 18

Asian Hercules II heavy lift derrick barge

Lifting Capacity: 3,200 tonnes

slide-20
SLIDE 20

June 2010 | Page 19

“West Callisto” drill rig in Keppel FELS, Singapore

slide-21
SLIDE 21

June 2010 | Page 20

Jack-Up rig drilling through wellhead platform

slide-22
SLIDE 22

June 2010 | Page 21

Onshore receiving facilities (ORF) modifications status

  • COPI supervised FEED with PT. WorleyParsons Indonesia (WPI)

complete

  • Long Lead Item (LLI) procurement orders ready to place
  • Two sole source vendors, Cameron & Mokveld for various valve & control

requirements (on hold - pending to results of SDP discussion)

  • EPCI Execution
  • EPCI contract for the implementation of the ORF modification has been

awarded to Punj Lloyd

  • Surveillance Plan
  • Premier Oil has established a surveillance team to over view COPI progress,

cost control and schedule

slide-23
SLIDE 23

June 2010 | Page 22

Incoming gas

slide-24
SLIDE 24

June 2010 | Page 23

Overall ORF process facility

slide-25
SLIDE 25

June 2010 | Page 24

Key events on Gajah Baru for 2H 2010

  • Engineering will reach 90% in August
  • Procurement
  • All WHP equipment & materials to be delivered by end of June
  • Majority of CPP major equipment will be delivered by July/August
  • Fabrication
  • WHP Jacket will load out in July and sail away early September
  • WHP Deck will load out in August and sail away mid September
  • CPP Jacket fabrication – start Elevation Panel assembly/erection 25 June
  • CPP Topsides Main Deck stack 01 July
  • Transport and stacking of 60 man LQ on 15 December
  • Installation
  • WHP Jacket installed 10 September and piled with conductors by 24 September
  • WHP Deck installed and ready for drilling 30 September
  • Drilling – West Callisto drill rig mobilizing to field in October
  • Development drilling of five wells will take place over the monsoon season
slide-26
SLIDE 26

June 2010 | Page 25 www.premier-oil.com

June 2010