HKGBC ACT-Shop Concept and Progress
24 JAN 2017
1
HKGBC ACT-Shop Concept and Progress 24 JAN 2017 1 Content 1. - - PowerPoint PPT Presentation
HKGBC ACT-Shop Concept and Progress 24 JAN 2017 1 Content 1. Concept and Objective of ACT-Shop 2. Progress Update a) Case Sharing b) Survey Findings 3. Way Forward & Timeline 2 Idea of ACT-Shop Knowledge-based Buildings as
24 JAN 2017
1
a) Case Sharing b) Survey Findings
2
3
4
Screening Re-tuning Modifica- tion Retrofit
5
Screening Re-tuning Modifica- tion Retrofit
Malfunctioned plants
On-site screening Data screening
50 100 2 4 6 8 10 12 14 16 18 20 22 24 Valve Opening % Daily Hour PAU Coil Valve Status Profile (Aug 15-20) 15/F 0.0 20.0 40.0 60.0 80.0 100.0 0.0 1000.0 2000.0 3000.0 % of FLA System Cooling Load (kW)
Sequencing Profile
1 Chiller 2 Chiller 3 Chiller
Poor Good
0.0 2.0 4.0 6.0 8.0 10.0 12.0 10.0 20.0 30.0 40.0 COP Outdoor Air Temperature (oC)
System COP vs Outdoor Temp.
Data inconsistency Data availability Fault readings from control panel
6
0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 30% 40% 50% 60% 70% 80% 90% 100%
COP
Cooling Load
Air-Cooled Chiller
Action: Operate 3 chillers within 25%-50% loading range Verified Results: Annual energy saving 226,000 kWh (4.75%)
Before After Average COP: 3.39 Average COP: 3.67
Poor Good Poor Good
8.2%
Screening Re-tuning Modifica- tion Retrofit
7
Action: Installation of pressure sensor at critical path for pump flowrate control
1000 2000 3000 4000 5000 20 40 60 80 100 120 2 4 6 8 10 12 14 16 18 20 22 24 Cooling Load (kW) Chilled Water Flow Rate (L/s) Daily Hour
Cooling Load Profile (15-Aug)
Chilled Water Flow Cooling Load
Potential Saving: Annual pump power saving = 70,000 kWh (40%) Progress: Installation of pressure sensors in progress
0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 0.0 500.0 1000.0 1500.0 2000.0 2500.0 Temperature (°C) Cooling Load (kW)
Differential Temperature of water variation with demand
15-Aug
VSD desirable range VSD non- desirable range
Screening Re-tuning Modifica- tion Retrofit
8
Original Option 1 Option 2 Option 3 Chiller 4 x 400 TR Air-cooled (VSD) 3 x 400 TR Air-cooled (VSD) 2 x 400 TR Air-cooled (VSD) 2 x 450 TR Air-cooled (VSD) Estimated Payback 9-10 years 8 years 6 years 5.5-6 years Annual Saving (kWh) 1,365,000 1,365,000 1,210,000 1,490,000 ROI @10th year 10% 32% 74% 79% IRR @10th year 3% 7% 13% 13%
Action: Evaluate
chiller replacement
P.s. Variable Speed Drive (VSD)
10 20 30 40 1000 2000 3000 4000 5000 Outdoor Air Temperature (oC) Cooling Load (kW)
Estimated Cooling Load Profile
Cooling Load per day Outdoor Temperature
0% 20% 40% 60% 80% 100% 1,000 2,000 3,000 4,000 5,000 6,000 Full Load Ampere Cooling Load (kW)
Sequencing Profile
1 Chiller 2 Chiller 3 Chiller 4 Chiller Poor Good
Unable to meet chilled water supply temperature set-point
Screening Re-tuning Modifica- tion Retrofit
9
Suggested Re-tuning Work Bld A Bld B Bld C Bld D Bld E Chillers Reduce chiller operation (N-1) to achieve higher
5-6% <1 year 3-5% 3-5 year 3-5% <1 year
Increase Tcws
1-3% <1 year 1-3% <1 year 1-3% <1 year
0-1% <1 year 1-3% <1 year 0-1% <1 year 1-2% <1 year 0-1% <1 year
Pumps (chilled water flow) Re-tune bypass valve setting
1-3% <1 year 1-3% <1 year 1-3% <1 year
Install differential pressure sensors at the critical path
1-3% <1 year 1-3% <1 year
Install VSD on the existing chilled water pumps
N/A 3-5% 3-5 year 3-5% 3-5 year N/A
Cooling towers Reactive cooling tower (CT) optimisation
N/A N/A
1-3% <1 year
N/A
1-3% <1 year
10
11
12
0.5 1 1.5 2 2.5 3 3.5 4 4.5 Regular re-tuning Evaluation of system performance Regular calibration of instrument Data logging Continuous improvement BMS application
Before ACT-Shop (average) After ACT-Shop (average)
13
Extra Time Spent in ACT-Shop <10% 20% 30% >40% Suggested ACT-Shop Programme Period 3 months 6 months 1 year more than 1 year
Most participant spent less than 10 % of time Participants prefer lasting for
14
1 2 3 4 5 1 2 3 4 or above
Suggested Training Sessions
1 2 3 4 5 System Optimisation Performance Evaluation Tool Analysis System Performance
Suggested Training Items
At least 3 training sessions are required All training items are important
15
16
ACT-Shop
participating building operators/services providers
building owners + a few other pilots
Active Training
Continuous Sharing
17
18
2nd Batch Registration
Feb 2017 5 + 1 2nd Batch Jul 2016
3rd Batch Registration
Jul 2017 1st Batch 5 5 + 1
4th Batch Registration
Feb 2018 5 + 1 Jul 2018
Active Training Class (Session 1)
Mar 2017 Oct 2017 Continuous Sharing
Preparation Work Preparation Work
Active Training Class (Session 2)
3rd Batch 4th Batch Nov 2016
Preparation Work
Chiller Sequencing Control
Purposed e-O&M Manual:
Building Level System Level Equipment Level
1 2 3 4 5 30% 50% 70% 90%
COP
Cooling Load
Air-Cooled Chiller
21
estimation, implementation, measurement & verification)
22