hkgbc act shop concept and progress
play

HKGBC ACT-Shop Concept and Progress 24 JAN 2017 1 Content 1. - PowerPoint PPT Presentation

HKGBC ACT-Shop Concept and Progress 24 JAN 2017 1 Content 1. Concept and Objective of ACT-Shop 2. Progress Update a) Case Sharing b) Survey Findings 3. Way Forward & Timeline 2 Idea of ACT-Shop Knowledge-based Buildings as


  1. HKGBC ACT-Shop Concept and Progress 24 JAN 2017 1

  2. Content 1. Concept and Objective of ACT-Shop 2. Progress Update a) Case Sharing b) Survey Findings 3. Way Forward & Timeline 2

  3. Idea of ACT-Shop Knowledge-based • Buildings as living laboratories • HKGBC as facilitator • Learning from peers • Building up in-house competence • Together 3

  4. Objectives • Actively supporting HK gov’s Climate Ready@HK • Building up the competence for the industry on retro- commissioning through • developing the data/knowledge base • developing a systematic approach for retro-commissioning • demonstrating the value of retro-commissioning • transferring the knowledge and skills to the industry • establishing a practical operation & management system • Promoting the adoption of best practices to the industry 4

  5. PROGRESS UPDATE CASE SHARING Modifica- Screening Re-tuning Retrofit tion 5

  6. Modifica- Case Sharing Screening Re-tuning Retrofit tion On-site screening Data screening Malfunctioned plants Data inconsistency Sequencing Profile 100.0 Poor 80.0 % of FLA 60.0 40.0 20.0 Good 0.0 0.0 1000.0 2000.0 3000.0 System Cooling Load (kW) Fault readings from control panel PAU Coil Valve Status Profile 1 Chiller 2 Chiller 3 Chiller (Aug 15-20) Valve Opening % 100 50 Data availability 0 0 2 4 6 8 10 12 14 16 18 20 22 24 Daily Hour System COP vs Outdoor Temp. 15/F 12.0 10.0 8.0 COP 6.0 4.0 2.0 0.0 10.0 20.0 30.0 40.0 Outdoor Air Temperature ( o C) 6

  7. Modifica- Case Sharing Screening Re-tuning Retrofit tion Poor Poor Good Action: Good Operate 3 chillers within 25%-50% loading range Air-Cooled Chiller Before After Verified Results: 5 4.5 Annual energy saving 4 3.5 226,000 kWh (4.75%) 3 COP 2.5 2 8.2% 1.5 1 0.5 0 30% 40% 50% 60% 70% 80% 90% 100% Cooling Load Average COP: 3.39 Average COP: 3.67 7

  8. Modifica- Case Sharing Screening Re-tuning Retrofit tion Cooling Load Profile (15-Aug) 120 5000 Chilled Water Flow Rate (L/s) Cooling Load (kW) 100 4000 80 3000 60 2000 40 Action: 1000 20 Installation of pressure 0 0 0 2 4 6 8 10 12 14 16 18 20 22 24 sensor at critical path Daily Hour Progress: for pump flowrate Chilled Water Flow Cooling Load Installation of pressure sensors control in progress Differential Temperature of water variation Potential Saving: with demand Annual pump power saving = 7.0 VSD desirable range 6.0 70,000 kWh (40%) Temperature (°C) 5.0 4.0 3.0 2.0 1.0 0.0 0.0 500.0 1000.0 1500.0 2000.0 2500.0 Cooling Load (kW) VSD non- desirable 15-Aug range 8

  9. Modifica- Case Sharing Screening Re-tuning Retrofit tion Estimated Cooling Load Profile 5000 40 Cooling Load (kW) Outdoor Air Temperature ( o C) Action: 4000 30 3000 Sequencing Profile 20 Evaluate 2000 Poor 10 1000 100% options for Full Load Ampere 0 0 80% chiller 60% replacement 40% Cooling Load per day Outdoor Temperature 20% Good 0% 0 1,000 2,000 3,000 4,000 5,000 6,000 Original Option 1 Option 2 Option 3 Cooling Load (kW) Chiller 4 x 400 TR 3 x 400 TR 2 x 400 TR 2 x 450 TR 1 Chiller 2 Chiller 3 Chiller 4 Chiller Air-cooled Air-cooled Air-cooled Air-cooled (VSD) (VSD) (VSD) (VSD) Estimated 9-10 years 8 years 6 years 5.5-6 years Payback Annual Saving 1,365,000 1,365,000 1,210,000 1,490,000 Unable to meet chilled water (kWh) ROI @10 th year supply temperature set-point 10% 32% 74% 79% IRR @10 th year 3% 7% 13% 13% P.s. Variable Speed Drive (VSD) 9

  10. Saving Summary of Re-tuning/Modification Suggested Re-tuning Work Bld A Bld B Bld C Bld D Bld E Chillers Reduce chiller operation (N-1) to achieve higher 5-6% 3-5% 3-5% <1 year 3-5 year <1 year overall COP 1-3% 1-3% 1-3% Increase Tcws <1 year <1 year <1 year 0-1% 1-3% 0-1% 1-2% 0-1% Max. demand shedding <1 year <1 year <1 year <1 year <1 year Pumps (chilled water flow) 1-3% 1-3% 1-3% Re-tune bypass valve setting <1 year <1 year <1 year Install differential pressure sensors at the critical 1-3% 1-3% <1 year <1 year path 3-5% 3-5% Install VSD on the existing chilled water pumps N/A N/A 3-5 year 3-5 year Cooling towers 1-3% 1-3% Reactive cooling tower (CT) optimisation N/A N/A N/A <1 year <1 year 10

  11. Feedback to Designers Provide a separate system for data centre/24-hour A/C • premises Plant sizing making reference to existing buildings • Plant & equipment design for part-load efficiency • Adequate instrumentation (Industrial grade) • Capability of BMS to suit operators’ need • 11

  12. PROGRESS UPDATE SURVEY FINDINGS 12

  13. Survey Findings Knowledge Gain on Retro-Commissioning: 4.5 4 3.5 3 2.5 2 1.5 1 0.5 0 Regular re-tuning Evaluation of system Regular calibration of Data logging Continuous BMS application performance instrument improvement Before ACT-Shop (average) After ACT-Shop (average) 13

  14. Survey Findings (con’t) Time spent: Suggested ACT-Shop Programme Period Extra Time Spent in ACT-Shop 3 months 6 months <10% 20% 30% >40% 1 year more than 1 year Most participant spent less Participants prefer lasting for than 10 % of time one year or longer. 14

  15. Survey Findings (con’t) Future Training Programme: Suggested Training Items Suggested Training Sessions 5 5 4 4 3 3 2 2 1 1 0 System Performance Analysis System 0 Optimisation Evaluation Tool Performance 1 2 3 4 or above At least 3 training sessions All training items are important are required 15

  16. WAY FORWARD & TIMELINE 16

  17. ACT-Shop Series (Short & Medium Terms) Building up knowledge & competence for ACT-Shop • participating building operators/services providers Target • At least one building of the 20+ large commercial • building owners + a few other pilots On-going knowledge up-dating • Reinforcement and Extending to Industry Active Training • Forums Continuous • Sharing Experience sharing with EMSD & Industry • Best Practice Notes • 17

  18. Active Training Target Participants • Individual involves in managing / operating a building • Service providers / equipment / system providers / contractors • Encourage operator/building manager to come with services provider • Mode of training • Semi-ACT-Shop • Gone through the essential process of retro-commissioning • Exercise using data from participants’ buildings • Pilot project on an energy saving project from participants • Participants expected to be able to: • Have in-depth knowledge and know how on proper retro-commissioning • lead in-house team or service provider to carry out proper retro-commissioning • Specify requirements to service providers when contract out the process • 18

  19. Programme Timeline – ACT-Shop Series Jul 2016 Feb 2017 Jul 2017 Feb 2018 Jul 2018 Mar 2017 Nov 2016 Oct 2017 2nd Batch Registration 3rd Batch Registration 4th Batch Registration 1 st Batch 5 2 nd Batch 5 + 1 3 rd Batch 5 + 1 4 th Batch 5 + 1 Preparation Work Preparation Work Preparation Work Active Training Class (Session 1) Active Training Class (Session 2) Continuous Sharing

  20. e-O&M Manual + Benchmarking Purposed e-O&M Manual: Building Level System Level Air-Cooled Chiller 5 4 3 COP 2 1 Equipment Level Chiller Sequencing Control 0 30% 50% 70% 90% Cooling Load

  21. 21

  22. Active Training (Q&A) Module Structure • Theory • Basic theories on HVAC relating to energy efficiency • Basic mathematical and analytical methods used during the training • Knowledge based retro-commissioning based on real case and data • Data collections, screening and data analysis, • Identifying opportunities • Saving estimates and evaluation • Practical methods on implementing improvements • Measurement and verification • Exercises with participants’ data • Technology sharing by suppliers • Performance characteristics of major equipment/BMS/services/design • New technologies • Industry updates • Government, other institutions or other speakers • Group or individual project (optional) • An energy saving project report demonstrating what has learnt (saving • estimation, implementation, measurement & verification) Future modules on knowledge based energy management • 22

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend