HINS Status and Strategy/Plans with Respect to Project X Bob Webber - - PowerPoint PPT Presentation

hins status and strategy plans with respect to project x
SMART_READER_LITE
LIVE PREVIEW

HINS Status and Strategy/Plans with Respect to Project X Bob Webber - - PowerPoint PPT Presentation

HINS Status and Strategy/Plans with Respect to Project X Bob Webber AAC Meeting November 16-17, 2009 AAC Charge Vis--vis HINS Review and offer comments and recommendations relative to: the current status of the HINS program the


slide-1
SLIDE 1

HINS Status and Strategy/Plans with Respect to Project X

Bob Webber AAC Meeting November 16-17, 2009

slide-2
SLIDE 2

AAC Charge Vis-à-vis HINS

  • Review and offer comments and recommendations relative to:

– the current status of the HINS program – the strategy for achieving alignment of the HINS and Project X

  • More specifically:

– Are the technical goals of the HINS program well aligned with the needs

  • f Project X?

– What are the primary technical risks within Project X that can and should be addressed within the HINS program? – Does the execution strategy of HINS mesh with the requirements of Project X? – What modifications to the HINS program would be effective in aligning with either ICD-1 or ICD-2? – Are there other approaches, beyond those being explored in the HINS program, that should be investigated as the front end of the Project X facility?

AAC, November 16-17, 2009 – Bob Webber Page 2

slide-3
SLIDE 3

Outline

  • HINS traditional technical objectives
  • Current status of the HINS program
  • Re-evaluation of the traditional objectives in Project X world
  • Current strategy for achieving alignment of the HINS and Project X
  • The Big Questions
  • What HINS can do
  • What HINS is not well positioned to do
  • Conclusions

AAC, November 16-17, 2009 – Bob Webber Page 3

slide-4
SLIDE 4

HINS Program Traditional Goals

  • Stated Mission - To address accelerator physics and technology

questions for a new concept, low-energy, high intensity, long-pulse H- superconducting Linac; in particular, to demonstrate:

– beam acceleration using superconducting spoke-type cavity structures starting at a beam energy of 10 MeV – multiple high power RF vector modulators controlling RF cavities driven – multiple high power RF vector modulators controlling RF cavities driven by a single high power klystron for acceleration of a non-relativistic beam – beam halo and emittance growth control by the use of solenoid focusing

  • ptics

– a fast, 325 MHz bunch-by-bunch, beam chopper

  • Remember that HINS has been the bridge to Project X for the

past nearly four years and that it brings unique and important assets even as it loses its identity within the project

Page 4 AAC, November 16-17, 2009 – Bob Webber

slide-5
SLIDE 5

Current Scope of HINS

  • The current scope of effort to achieve the traditional HINS program

goals comprises design, development, fabrication, assembly and

  • peration of a ‘first-of-a-kind’ pulsed superconducting H- linac
  • The components include:

– 50 keV ion source – 2.5 MeV RFQ – MEBT with fast beam chopper system – 10 MeV “room temperature (RT)” linac composed of copper CH-type spoke accelerating cavities and superconducting (SC) solenoid magnets – One or two 9-cavity modules of 325 MHz, = 0.2 SC spoke resonator (SSR1) cavities and SC solenoids for final 20 or 30 MeV beam energy – Two pulsed 2.5 MW klystrons to power the entire machine – A suite of beam diagnostics to characterize machine performance

  • SSR2 = 0.4 has been dropped from the program

Page 5 AAC, November 16-17, 2009 – Bob Webber

slide-6
SLIDE 6

Current Status

  • Proton ion source is operational; H- source has been prototyped
  • RFQ is RF conditioned to nominal peak operating field
  • Mating of ion source to RFQ begins today
  • Warm cavities are being RF conditioned to nominal power
  • Warm section SC solenoid cryostats are being assembled
  • First SSR1 cavity is welded into helium jacket
  • Order for 10 SSR1 niobium cavities is in final bid evaluation stage
  • Test cryostat for full pulsed-power spoke resonator testing is being

installed

  • SSR1 cryomodule design is just in its infancy
  • Concrete block shielding enclosure for the linac is under construction

AAC, November 16-17, 2009 – Bob Webber Page 6

slide-7
SLIDE 7

HINS Progress in 2009

  • RFQ problem:

– Discovered Feb 19 – At ACCSYS for repair June thru Sept – Now conditioned to nominal peak, but low average, power

  • Received and conditioned to nominal RF power two buncher cavities

manufactured with LBL effort manufactured with LBL effort

  • Measured proton ion source beam parameters
  • Studied beam transport characteristics of the solenoid focusing

LEBT

  • Tested prototype H- ion source (20 mA, 1 msec, 2.5 Hz) successfully
  • Tested second SSR1 spoke cavity in VTS with outstanding results
  • Completed fabrication of test cryostat for high pulsed power testing

SSR1 cavities

AAC, November 16-17, 2009 – Bob Webber Page 7

slide-8
SLIDE 8

HINS Progress in 2009

  • Completed preliminary measurements of prototype SSR solenoid

stray fields

  • Integrated BPMs into RT-CH solenoid cryostat design
  • Tested RT-CH cavities #1-5 and 9 to design RF power; fabrication

problem left vacuum leaks in others (found in factory vacuum tests)

  • Ran LLRF system with feedback for RFQ and RT-CH cavity
  • Ran LLRF system with feedback for RFQ and RT-CH cavity
  • Received and tested four wide-bandwidth, programmable vector

modulator bias supplies

  • Tested several SSR cavity input power couplers to HINS peak

pulsed power level and to equivalent Project X IC-2 average power level

AAC, November 16-17, 2009 – Bob Webber Page 8

slide-9
SLIDE 9

RFQ and 2.5 MeV Beamline

AAC, November 16-17, 2009 – Bob Webber Page 9

slide-10
SLIDE 10

Typical Emittance Scan Data

Ib = 4 mA Horizontal Vertical 50 keV beam from HINS proton ion source

AAC, November 16-17, 2009 – Bob Webber

Ib = 12 mA

Page 10

Plots by Wai-Ming Tam

slide-11
SLIDE 11

50 keV Proton Beam Emittance Measurement Results

  • 0.3

0.4 0.5 0.6 emittance, normalized mmmrad

  • Solenoid y
  • Solenoid x
  • Slit y
  • Slit x

Results from two methods:

Profile measurements while scanning solenoid strengths Slit-wire method Beam current is total current including H2+ AAC, November 16-17, 2009 – Bob Webber

  • 5

10 15 20 0.0 0.1 0.2 0.3 Beam Current mA RMS emittance Εn,rms mm

including H2+ Profile method is subject to beam model assumptions Slit-wire method is subject to a geometric factor We have yet to reconcile systematic difference between results from the two methods Page 11

Plot by Wai-Ming Tam

slide-12
SLIDE 12

Room Temp Linac Section

Cryogenic Line Solenoids (19)

AAC, November 16-17, 2009 – Bob Webber Page 12

Cryogenic Line Chopper RT CH Cavities (16) Buncher Cavities (2)

slide-13
SLIDE 13

Linac Enclosure Under Construction Around Room Temp Section Girder

AAC, November 16-17, 2009 – Bob Webber Page 13

slide-14
SLIDE 14

Tested RT-CH and Buncher Cavities

AAC, November 16-17, 2009 – Bob Webber Page 14

slide-15
SLIDE 15

Room Temp Section Solenoid & Cryostat

Page 15 AAC, November 16-17, 2009 – Bob Webber

slide-16
SLIDE 16

SSR1 Cavity – Bare and with Helium Vessel and Tuner

AAC, November 16-17, 2009 – Bob Webber Page 16

slide-17
SLIDE 17

Spoke Cavity Test Cryostat

In MDB awaiting installation into

AAC, November 16-17, 2009 – Bob Webber Page 17

installation into test cavity cave

slide-18
SLIDE 18

SSR1 Cryomodule Model

  • Present conception of SSR1 Cryomodules

– Contain 9 SSR1 cavities and 9 solenoids – Project X expects that these designs could be extended to SSR0 and SSR2 requirements

Page 18 AAC, November 16-17, 2009 – Bob Webber

slide-19
SLIDE 19

Current Look at HINS Goals from Project X Perspective

  • Beam acceleration with superconducting spoke-type cavity structures

– Development of 325 MHz SC spoke cavities and associated infrastructure must be preserved and expanded for either C-1 and IC-2

  • Fabrication and processing procedures
  • Cavity test cryostat
  • 325 MHz RF power

– How important is the beam demonstration?

  • 325 MHz high power RF vector modulators
  • 325 MHz high power RF vector modulators

– Of the initial HINS goals, this is the earliest achievable (six-cavity test) – Critical to IC-1 if one klystron/many cavity option is followed – Not applicable to CW IC-2 where each cavity will have its own amplifier – Associated 325 MHz LLRF developments are directly applicable to Project X

  • Solenoid focusing optics

– Importance to Project X to be determined – Project X linac beam focusing design is not final

  • Fast, 325 MHz bunch-by-bunch, beam chopper

– Development of chopper and beam preparation is crucial to Project X – IC-2 chopper requirements are far beyond current HINS scope

Page 19 AAC, November 16-17, 2009 – Bob Webber

slide-20
SLIDE 20

RFQ RT Section Solenoids & Cryostat RT-CH Cavities Buncher Cavities Vector Modulators 2.5 MeV Beam Line 2.5 MeV Beam !! Proton Ion Source & LEBT H- Ion Source & LEBT 10 MeV Beam !! Solenoidal Six-cavity Test with Beam !! Vector Modulator Demonstration !! Chopper Chopper Demonstration !! Chopper Test Facility LLRF Beam Instrumentation and Controls Quad Magnets H- Instrumentation Test Facility

HINS Strategy Roadmap

AAC, November 16-17, 2009 – Bob Webber 20

325 MHz Test Cryostat Test Cryo. Dist. System SSR1 Cavities & Cryostat RT Solenoid PS/Quench Protection Modulators Vector Modulator Power Supplies Solenoidal Focusing Demonstration !! Superconducting Spoke Cavity Beam Acceleration Demonstration !! First 325 MHz Superconducting Spoke Cavity Pulsed Power Test Test Cryostat System Integration Quad Magnet PS SSR1 Tuners SSR1 Section Solenoids SSR1 Cryomodule Design Linac Cave Cryo Distribution SSR1 Cryomodule Fabrication HINS Linac Cave Design, Approval, and Construction 325 MHz Superconducting Spoke Cavity Test Facility RT-CH Cavities

  • Green boxes are

happy destinations

  • Blue text are HINS

goals

  • Red boxes/lines are

critical paths

slide-21
SLIDE 21

HINS Strategy

  • Construct H- linac to at least 10 MeV in pursuit of original HINS goals

that remain relevant

  • Build a beam facility for chopper testing and beam instrumentation

development

  • Continue SSR1 spoke cavity and cryomodule development activities

with design considerations taken for CW and 2°K operation in direct with design considerations taken for CW and 2°K operation in direct support of Project X

  • Achieve world-first beam acceleration through at least one SSR1

cryomodule operating at 4°K

  • Continue SC solenoid design work in support of above objectives

AAC, November 16-17, 2009 – Bob Webber Page 21

slide-22
SLIDE 22

The Plan – Near Term

  • Achieve beam from RFQ
  • Install spoke cavity test cryostat and test cavity at full pulsed power
  • Continue RT section SC solenoid and cryostat assembly work
  • Procure an additional ten SSR1 niobium cavities
  • Complete HINS Linac shielding enclosure

– Initially sized to contain 10 MeV Linac, beam diagnostics line and absorber – Designed for easy extension to house up to two SSR1 cryomodules

  • Complete full safety documentation
  • Complete the “Six-cavity Test” for first vector modulator

demonstration with beam

  • Specify and design cryogenics distribution system for HINS linac

AAC, November 16-17, 2009 – Bob Webber Page 22

slide-23
SLIDE 23

The Six-Cavity Test

  • Purpose: early demonstration of beam acceleration with vector

modulator control (before availability of cryogenics distribution system)

  • Warm quadrupole magnets substituting for SC solenoids
  • ~3.0 MeV protons
  • Diagnostic line for beam evaluation

AAC, November 16-17, 2009 – Vic Scarpine Page 23

Beam Diagnostics Beam line RFQ

slide-24
SLIDE 24

A Word on SSR Cryomodules

  • SSR cryomodule design efforts are not yet begun in earnest
  • The present concept is a cryomodule with nine cavities and nine

solenoid magnets

– It’s not clear that solenoids are the focusing element of choice for a low current CW Linac – Grouping cavities by nine might not be optimal – Numerous uncertainties, including tuner design, magnetic shielding, beam instrumentation and alignment considerations, suggest that constructing a prototype cryostat with fewer elements and maybe for first spoke cavity beam tests is advisable

  • Considerations are already being given to incorporating 2°

K

  • peration into the initial cryomodule design
  • At either 4°

K or 2° K, cryomodule design will be a major task

  • HINS is currently steward of all the technologies and developments

necessary to lead to a realizable 325 MHz cryomodule design

AAC, November 16-17, 2009 – Bob Webber Page 24

slide-25
SLIDE 25

Possibility to Modify 325 MHz Test Cryostat for 2K Operation

  • Estimated cryostat modification costs

– New internal piping assembly: $17,000 (based on original system) – 4K to 2K heat exchanger: $15,000 (based on a similar exchanger purchased in the LHC program) – Control valve to heat exchanger: $6,000 (based on a similar valve purchased in the LHC program) – Misc: $2,000 – Misc: $2,000 – Total: $40,000 – EDIA: 6 FTE-months (combined engineering and drafting)

  • There would also need to be a major modification/addition to the

cryogenics supply system, feedbox, and transfer line.

– No cost estimate yet for that but likely several times the cryostat modification costs

  • Cryogenics plant, shared with elliptical cavity HTS, might also be

strained to support large additional heat load for CW elliptical cavity testing

AAC, November 16-17, 2009 – Bob Webber Page 25

slide-26
SLIDE 26

The Big Questions

  • At what point in Project X development and/or at what HINS beam

energy does it make no sense to further pursue 325 MHz pulsed Linac construction, especially if CW Project X option is taken?

  • How important is beam demonstration of spoke cavities?
  • How valuable to Project X or other is a flexible low energy beam

facility?

  • At what manpower cost? Will people be available?
  • At what financial cost? Will funding remain available?
  • What technical risks can be tolerated in the program?

– 325 MHz klystron failure w/o spare?; it is required for any beam from the HINS warm front-end – RFQ failure to accelerate beam?; we should have answer to this in a few months

  • What are we missing?

AAC, November 16-17, 2009 – Bob Webber Page 26

slide-27
SLIDE 27

The Unique Position of HINS for Project X - Pulsed or CW

  • The Project X requirement for 325 MHz infrastructure is not negotiable

unless it should opt for an unforeseen frequency change

  • HINS comprises the 325 MHz spoke cavity design and development

experience

  • HINS provides a 325 MHz spoke cavity test cryostat

– VTS in IB1 will not fit a jacketed spoke cavity – Cryostat is upgradeable for 2°K operation – Cryostat is upgradeable for 2°K operation

  • Albeit pulsed, HINS offers the only source of high power 325 MHz RF
  • HINS drives 325 MHz LLRF and beam diagnostics development
  • HINS can offer beam for

– Chopper development and performance testing – H- beam instrumentation development and testing

  • Even pulsed beam through a cryomodule powered by CW RF would be

an important demonstration that might be possible at Meson Detector Building

AAC, November 16-17, 2009 – Bob Webber Page 27

slide-28
SLIDE 28

What is Clearly Beyond Current HINS Scope

  • Spoke cavity or cryomodule development beyond SSR1

– There is reason to believe that SSR1 is fast track to SSR0 and SSR2, but not necessarily to TSR

  • CW ion source development
  • CW RFQ development
  • CW RF power system development
  • CW RF power system development
  • SSR cryomodule operation at 2°K – the MDB cryogenics facility

cannot support this

AAC, November 16-17, 2009 – Bob Webber Page 28

slide-29
SLIDE 29

The Other HINS Talks

  • Two talks report in details on status of important HINS technology

development work

– Terechkine – superconducting solenoid magnets – Wagner – superconducting spoke cavities

  • Two talks suggest how an operating HINS beam could serve as an
  • Two talks suggest how an operating HINS beam could serve as an

important and unique Project X technology development facility

– Madrak – beam chopper performance testing – Scarpine – H- beam instrumentation testing

AAC, November 16-17, 2009 – Bob Webber Page 29

slide-30
SLIDE 30

Conclusions

  • Great progress has been made and there currently is excellent

momentum towards constructing and commissioning the HINS Linac

  • Some years of work and considerable expense remain to achieve

traditional goals

  • Certain aspects of HINS, especially 325 MHz SC spoke cavity

development, are mainstream and vital to Project X IC-1 and IC-2

  • There are issues accompanying a CW machine HINS is not well

positioned to address in it present scope

  • Achieving beam, even pulsed and well below the 30 MeV goal,

HINS will offer a unique beam facility for studying multiple issues of great importance to Project X including chopper performance and H- beam instrumentation

  • There will be difficult decisions and new opportunities that determine

the future of the traditional HINS program as it melds into Project X

AAC, November 16-17, 2009 – Bob Webber Page 30

slide-31
SLIDE 31

RFQ in Vacuum Tank

Page 31 AAC, November 16-17, 2009 – Bob Webber

slide-32
SLIDE 32

RFQ Close-up

Note RF joint seal

Page 32 AAC, November 16-17, 2009 – Bob Webber

slide-33
SLIDE 33

RFQ RF Joint Failure

RF joint seal buckled buckled RF joint seal buckled

Page 33 AAC, November 16-17, 2009 – Bob Webber