Himachal Small Hydro Power Association Association
Draft Regulations on Tariff for Renewable Energy
Wednesday July 22nd, 2009
Himachal Small Hydro Power Association Association Draft - - PowerPoint PPT Presentation
Himachal Small Hydro Power Association Association Draft Regulations on Tariff for Renewable Energy Wednesday July 22 nd , 2009 BACKGROUND BACKGROUND India India has India has India has been has been been bestowed been bestowed
Wednesday July 22nd, 2009
BACKGROUND BACKGROUND
India has has been been bestowed bestowed with with huge huge Renewable Renewable Energy Energy Potential Potential
India has has been been bestowed bestowed with with huge huge Renewable Renewable Energy Energy Potential Potential particularly particularly the the small small hydro hydro potential potential is is to to the the tune tune of
15000 MW MW. .
However, the the present present scenario scenario of
generation from from Renewable Renewable , p g Sources Sources particularly particularly of
small hydro hydro sector sector is is not not very very encouraging encouraging. . In In the the last last 62 62 years years only
10% % of
the small small hydro hydro potential potential has has been been exploited exploited. .
This is is in in spite spite of
the fact fact that that Electricity Electricity Act, Act, 2003 2003 and and every every other
policy policy document document i i. .e e National National Electricity Electricity Policy, Policy, National National Tariff Tariff Policy Policy speaks speaks of
promoting Renewable Renewable Energy Energy. . The The Electricity Electricity Act Act enjoins enjoins upon upon the the Regulatory Regulatory Commissions Commissions to to take take effective effective steps steps for for the the upon upon the the Regulatory Regulatory Commissions Commissions to to take take effective effective steps steps for for the the promotion promotion of
Renewable Energy Energy. .
The proposed proposed Draft Draft Regulation Regulation is is further further going going to to discourage discourage and and p p p p g g g g g g demoralize demoralize the the developers developers of
small hydro hydro projects projects. . It It is is devoid devoid of
the ground ground realities, realities, problems problems and and the the non non supportive supportive environment environment being being faced faced by by the the developers developers. .
Himachal Small Hydro Power Association
2
BLEAK SCENARIO OF SMALL HYDRO SECTOR BLEAK SCENARIO OF SMALL HYDRO SECTOR
Major small small hydro hydro potential potential lies lies in in Himalayan Himalayan States States. . These These states states do do not not have have enough enough infrastructures infrastructures to to support support the the various various developmental developmental activities activities because because of
their terrain terrain and and inadequate inadequate resources resources with with them them. .
Small hydro hydro projects projects being being located located on
Tributaries or
the Tributaries Tributaries of
Tributaries Tributaries are are very very remote remote and and have have neither neither the the road road access access nor nor the the power power evacuation evacuation networks networks. . This This adds adds substantially substantially to to their their costs costs. .
Small Hydro Hydro projects projects do do not not enjoy enjoy economics economics of
scale, therefore therefore have have high high per per MW MW costs costs. .
Because of
their remote remote location location and and narrow narrow terrains terrains Small Small Hydro Hydro Projects Projects have have great great risks risks attached attached with with them, them, therefore therefore is is not not a a very very attractive attractive investment investment option
.
In the the past past Small Small Hydro Hydro Projects Projects were were located located on
lower elevations elevations and and on
the the confluence confluence of
tributaries and and main main rivers rivers. . However, However, in in future future Small Small Hydro Hydro Projects Projects are are going going to to be be remotely remotely located located on
higher elevations elevations. . As As a a lt lt th th t i i t tt t tt t i t t i t t il il
Himachal Small Hydro Power Association
result, result, they they are are not not going going to to attract attract investments investments easily easily.
3
In many many recent recent Tariff Tariff determination determination orders
the per per MW MW cost cost of
the project project has has been been taken taken based based on
historical data data This This has has acted acted as as project project has has been been taken taken based based on
historical data data. This This has has acted acted as as the the dampener dampener for for the the developers developers. .
The result result is is that that till till now now only
15% % of
the projects projects allotted allotted in in Himachal Himachal P d h P d h d Utt kh d Utt kh d h b i i d i i d Pradesh Pradesh and and Uttarakhand Uttarakhand have have been been commissioned commissioned.
The said said regulations regulations instead instead of
promoting Renewables Renewables intends intends to to regulate regulate these these sources sources. regulate regulate these these sources sources.
Himachal Small Hydro Power Association
4
Himachal Small Hydro Power Association
5
1.
REGULATION 3 & 4 (2): SCOPE & EXTENT OF APPLICATIONS
Section 79 79 a a & & b b of
the Electricity Electricity Act, Act, 2003 2003 provides provides that that it it is is the the function function of
the central central commission commission to to regulate regulate tariff tariff of
central generating generating companies companies or
those generating generating companies companies which which enter enter into into or
have a a composite composite scheme scheme for for generation generation and and sale sale p g
electricity in in more more than than one
state. .
As per per the the Draft Draft Regulations Regulations these these regulations regulations will will not not apply apply to to 1. . Those Those projects projects which which are are selling selling intrastate intrastate. . 2 Those Those State State and and self self identified identified projects projects which which are/will are/will be be going going in in
Those State State and and self self identified, identified, projects projects which which are/will are/will be be going going in in for for interstate interstate sale sale but but not not yet yet approved approved by by MNRE MNRE. .
Himachal Small Hydro Power Association
6
The regulation regulation proposes proposes calculation calculation of
levelised tariff tariff corresponding corresponding to to useful useful life life of
the project project i i. .e e. . 40 40 years years while while the the tariff tariff period period is is fixed fixed as as 13 13 years years in in the the Draft Draft Regulations Regulations and and thereafter thereafter Power Power Procurement Procurement from from renewable renewable sources sources is is expected expected on
competitive Procurement Procurement from from renewable renewable sources sources is is expected expected on
competitive basis basis. .
This is is highly highly unfair, unfair, unjustifiable unjustifiable and and against against the the concept concept of
l li d l li d t iff t iff I l li d l li d t iff t iff th th h l l i i i ffi i t i ffi i t i i levelised levelised tariff tariff. In In levelised levelised tariff tariff the the cash cash accrual accrual is is insufficient insufficient in in initial initial years years i i. .e e. . debt debt service service period period which which is is compensated compensated by by extra extra cash cash accrual accrual in in the the later later years years. .
This will will be be a a big big d disincentive isincentive and and no no financial financial closure closure will will be be achieved achieved if if this this regulations regulations is is finalised finalised. . Instead, Instead, the the Renewable Renewable Sources Sources should should be be provided provided with with front front loaded loaded tariff tariff so so as as to to generate generate significant significant cash cash in in the the initial initial years years to to service service the the debt debt easily
This will will significant significant cash cash in in the the initial initial years years to to service service the the debt debt easily
This will will help help in in achieving achieving faster faster financial financial closure closure and and thus thus speedy speedy implementation implementation of
the projects projects. .
Himachal Small Hydro Power Association
7
3. 3. REGULATION 11: SCHEDULING REGULATION 11: SCHEDULING
Exemption of
Small Hydro Hydro Projects Projects from from UI UI charges charges proposed proposed in in
Exemption of
Small Hydro Hydro Projects Projects from from UI UI charges charges proposed proposed in in Draft Draft Regulations Regulations is is very very supportive supportive to to promote promote the the Renewable Renewable Energy Energy projects projects. . Ho e er Ho e er the the proposal proposal of
Draft Reg lations Reg lations to to f rnish f rnish the the tentati e tentati e
However, the the proposal proposal of
Draft Regulations Regulations to to furnish furnish the the tentative tentative day day ahead ahead forecast forecast in in blocks blocks of
1. .5 5 hour hour duration duration for for the the energy energy availability availability on
the collective collective basis basis at at inter inter-
connection point point to to the the concerned concerned Load Load Dispatch Dispatch Centre, Centre, is is not not feasible feasible. .
It would would not not be be feasible feasible to to declare declare the the availability availability on
collective basis basis as as number number of
small projects projects with with different different Renewable Renewable Energy Energy Technologies Technologies and and at at different different voltage voltage levels levels would would be be connected connected to to Technologies Technologies and and at at different different voltage voltage levels levels would would be be connected connected to to the the grid grid with with each each having having its its own
inter-
connection point point. .
Also co co-
among various various generators generators would would be be practically practically impossible impossible impossible impossible.
Therefore, collective collective basis basis should should be be omitted
. Further, Further, CERC CERC should should ensure ensure that that in in the the garb garb of
exemption of
UI regime regime to to SHPs, SHPs,
Himachal Small Hydro Power Association
g p g , the the States States may may not not deny deny Open Open Access Access to to such such generators generators. .
8
D ft D ft R l ti R l ti ti ti it l it l t f SHP SHP
Draft Regulations Regulations proposes proposes normative normative capital capital cost cost of
SHPs as as Rs Rs. . 630 630. .00 00 Lacs/ Lacs/ MW MW for for Himachal Himachal Pradesh, Pradesh, Uttarakhand Uttarakhand & & North North Eastern Eastern States States and and Rs Rs. . 500 500. .00 00 Lacs Lacs for for other
States. .
These normative normative project project costs costs are are grossly grossly inadequate inadequate and and low low. . These These are are based based on
historical data data of
Projects funded funded by by IREDA IREDA and and Projects Projects registered registered with with UFCCC UFCCC. .
Even these these costs costs are are not not true true reflection reflection of
the project project cost cost incurred/ incurred/ being being incurred incurred for for the the development development of
SHPs on
account of
following reasons reasons: : a. . There There have have been been severe severe cost cost overruns
for the the projects projects funded funded by by IREDA IREDA. . These These have have not not been been taken taken into into account account. . b. . Secondly, Secondly, IREDA IREDA has has also also funded funded projects projects costing costing more more than than Rs Rs. . 700 700. .00 00 Lacs/MW Lacs/MW in in 2007 2007. . If If we we take take 6 6% % yearly yearly increase increase in in project project cost, cost, the the cost cost in in 2009 2009 works works out
to Rs Rs. . 786 786. .00 00 Lacs/MW Lacs/MW. .
Himachal Small Hydro Power Association
p j p j ,
9
The land land cost cost have have increased increased exponentially exponentially in in the the last last 2 2-
3 years years. . The The land land
have started started asking asking for for unrealistic unrealistic exorbitant exorbitant prices prices. . The The land land which which used used to to cost cost Rs Rs. . 60 60-
75 Lacs Lacs i i. .e e. . Rs Rs. . 12 12. .00 00 to to 15 15. .00 00 Lacs Lacs/MW /MW for for a a 5 5 MW MW Project Project 2 2-
3 years years back, back, now now costs costs Rs Rs. . 2 2. .00 00 to to 3 3. .00 00 Cores Cores i i. .e e. . Rs Rs. . 50 50. .00 00 to to 60 60. .00 00 Lacs Lacs/MW /MW. . The The projects projects cost cost on
this account account only
has increased increased by by Rs Rs 40 40 00 00 to to 50 50 00 00 Lacs Lacs/MW /MW Rs
40.00 00 to to 50 50.00 00 Lacs Lacs/MW /MW.
The various various State State Govt Govt. . over
the year year have have levied levied many many taxes taxes & & duties duties as as below below: below below: i i. . LADC LADC ( (1 1. .5 5% %) ). . ii ii. . Free Free Power/Royalty Power/Royalty
Period Period Upto 5 MW Upto 5 MW Above 5 MW Above 5 MW 1 to 12 years 1 to 12 years 6% (0) 6% (0) 15% (12) 15% (12) 13 13th
th to 30 years
to 30 years 14% (12) 14% (12) 21% (18) 21% (18) 31 31st
st to 40 years
to 40 years 24% (18) 24% (18) 33% (30) 33% (30)
Himachal Small Hydro Power Association
iii iii 15% release of water. 15% release of water. iv MAT (Increased from 10% to 15%) iv MAT (Increased from 10% to 15%) iv MAT (Increased from 10% to 15%) iv MAT (Increased from 10% to 15%)
HERC vide vide its its order
dated 15 15th
th May
May 2007 2007 has has considered considered project project t f R R 1025 1025 00 00 L /MW L /MW f l l b d b d SHP SHP i i H cost cost of
Rs. . 1025 1025.00 00 Lacs/MW Lacs/MW for for canal canal based based SHPs SHPs in in Haryana Haryana. .
MPERC vide vide its its order
dated 30 30th
th June
June 2008 2008 has has considered considered Rs Rs. .700 700. .00 00 Lacs/MW Lacs/MW for for SHPs SHPs.
HPERC vide vide its its order
dated 18 18th
th Dec
Dec. . 2007 2007 has has considered considered Rs Rs. . 650 650. .00 00 Lacs/MW Lacs/MW for for SHPs SHPs. . This This is is also also under under challenge challenge in in the the Appellate Appellate Tribunal Tribunal. .
Recently, Govt Govt. . of
Punjab has has invited invited EOI EOI for for 55 55. .5 5 MW MW Shahpur Shahpur Kandi Kandi Project Project. . The The capital capital cost cost estimated estimated in in the the DPR DPR is is Rs Rs. . 49883 49883. .00 00 Lacs Lacs based based on
Nov. . 2000 2000 prices prices which which works works out
to Rs Rs. .
Himachal Small Hydro Power Association
p 899 899. .00 00 Lacs/MW Lacs/MW. .
c. . HPSEB HPSEB has has granted granted TEC, TEC, for for many many projects projects costing costing in in the the range range of
Rs. . 750 750 Lacs Lacs to to Rs Rs. . 800 800. .00 00 Lacs/MW Lacs/MW in in the the recent recent g past past. . The The details details are are as as below below: :
Himachal Small Hydro Power Association
12
Project cost of the projects developed by HPSEB on their own is as below: Project cost of the projects developed by HPSEB on their own is as below:
SR. No. NAME OF PROEJCT CAPACITY (MW) TOTAL PROEJCT COST (IN CR ) PROJECT COST PER MW (IN CR ) DATE OF COMMISSIONING (IN CR.) (IN CR.)
1 Larjee 126 1294.0 10.26 2006.00 2 Khauli 12 126 3 10 52 Nov 2000 2 Khauli 12 126.3 10.52 Nov.2000 3 Ghanvi 22.5 166.3 7.39 March 2007 12 68 8 3 1996 4 Baner 12 68.8 5.73 1996 5 Gaj 10 75.5 7.55 1996 Thus Thus the the cost cost for for projects projects which which were were commissioned commissioned by by HPSEB HPSEB more more than than 3 3-
4 years years back back is is in in the the range range of
Rs. .739 739. .00 00 Lacs Lacs/MW /MW to to Rs Rs. . 1052 1052. .00 00 Lacs Lacs/ / MW MW.
Himachal Small Hydro Power Association
13
Therefore, it it is is not not justifiable justifiable to to compare compare the the set set of
projects based based on
historical historical data data and and considering considering the the value value in in between between for for determination determination historical historical data data and and considering considering the the value value in in between between for for determination determination
the cost cost. .
It is is also also worth worth highlighting highlighting that that in in the the past past SHPs SHPs have have been been developed developed l l l ti l ti hi h hi h h d h d d t i i t i i d th th
lower lower elevations elevations which which had had road, road, transmission transmission and and
infrastructure infrastructure available available nearby nearby. . But But in in future future such such projects projects are are going going to to be be remotely remotely located located on
higher elevations elevations. . Thus, Thus, the the per per MW MW cost cost is is likely likely to to increase increase substantially substantially. .
In case case these these normative normative project project costs costs are are adopted, adopted, then then all all those those projects projects with with higher higher cost cost will will not not be be taken taken up up for for construction construction and and the the SHP SHP potential potential to to that that extent extent will will remain remain unexploited unexploited. SHP SHP potential potential to to that that extent extent will will remain remain unexploited unexploited.
It is is humbly humbly requested requested to to reconsider reconsider these these normative normative costs costs and and the the HSHPA HSHPA strongly strongly feels feels that that either either the the normative normative cost cost should should be be fixed fixed at at R 800 800 L /MW L /MW ti ti t b fi d fi d d j t j t ifi ifi Rs Rs. . 800 800 Lacs/MW Lacs/MW or
no normative normative cost cost be be fixed fixed and and project project specific specific cost cost be be taken taken into into account account. .
Himachal Small Hydro Power Association
5. 5. REGULATION 14: EVACUATION INFRASTRUCTURE REGULATION 14: EVACUATION INFRASTRUCTURE D ft D ft R l ti R l ti j t j t d l d l t b ibl ibl f
Draft Regulations Regulations proposes proposes project project developer developer to to be be responsible responsible for for evacuation evacuation infrastructure infrastructure up up to to inter inter-
connection point point. . Such Such regulation regulation would would result result in in:
Such regulation regulation would would result result in in:
Need for for large large capital capital infusion infusion by by the the project project developers developers
Increased difficulty difficulty for for the the developers developers to to achieve achieve financial financial closure closure owing
to the the uncertainty uncertainty regarding regarding power power evacuation evacuation the the uncertainty uncertainty regarding regarding power power evacuation evacuation
Deterrent for for private private players players to to invest invest in in the the renewable renewable energy energy sector sector
Therefore the the respective respective distribution distribution utilities utilities should should be be responsible responsible for for
Therefore, the the respective respective distribution distribution utilities utilities should should be be responsible responsible for for the the development development of
evacuation infrastructure infrastructure. .
Himachal Small Hydro Power Association
15
6. 6. REGULATION 18: Return on Equity REGULATION 18: Return on Equity Draft Regulations proposes Return on Equity at 16% Draft Regulations proposes Return on Equity at 16%
Draft Regulations proposes Return on Equity at 16%.
The commissions commissions proposal proposal is is inadequate inadequate as as it it does does not not justify justify the the risks risks borne borne by by the the project project developers developers borne borne by by the the project project developers developers.
Small hydro hydro projects projects (SHP) (SHP) posses posses many many risks risks such such as as: :
Geological g
Hydrological
Technical
Moreover, long long gestation gestation periods periods ( (4 4 – – 5 5 years) years) associated associated with with SHPs SHPs results results in in a a much much lower lower effective effective rate rate of
return on
equity. . Above Above stated stated factors factors will will result result in in an an effective effective return return on
equity of
10%
Above stated stated factors factors will will result result in in an an effective effective return return on
equity of
10% which which is is equivalent equivalent to to the the return return on
a AAA AAA rated rated government government security security
Himachal Small Hydro Power Association
16
6. 6. REGULATION 18: Return on Equity REGULATION 18: Return on Equity Contd.
Contd.
In order
to encourage encourage private private developers developers to to investment investment in in renewable renewable energy energy sector, sector, the the rate rate of
return on
equity should should be be increased increased to to 20 20% % Post Post-
tax. .
Incentive based
availability, 1% Incentive on account of sale of Base return as per CERC for ti l account of sale of secondary energy, 1% Additional premium to cover conventional energy projects, 16% premium to cover risks specific to SHP, 2%
ROE for first 10 years – – 23% Pre 23% Pre-
tax
11th
th year onwards
year onwards – – 30% Pre 30% Pre-
tax
Himachal Small Hydro Power Association
17
7. 7. REGULATION 20 & 31: OPERATION & MAINTENACE EXPENSES REGULATION 20 & 31: OPERATION & MAINTENACE EXPENSES
Draft Regulations Regulations proposes proposes O O & & M M expenses expenses at at Rs Rs. . 12 12. .00 00 Lac/ Lac/ MW MW with with an an annual annual escalation escalation of
.72 72% % per per annum annum. .
These are are also also grossly grossly on
lower side side. . It It will will be be optimal
to go go into into the the individual individual elements elements of
cost and and price price them them at at their their correct correct value value to to arrive arrive at at a realistic realistic assessment assessment. The The costing costing exercise exercise for for a 1 MW MW arrive arrive at at a realistic realistic assessment assessment. The The costing costing exercise exercise for for a 1 MW MW project project under under operation
in state state of
Punjab is is as as below below:
Himachal Small Hydro Power Association
18
SR. NO. ITEMS RS. IN LAC I S l i & W (3 Shift ) 26 00 I Salaries & Wages (3 Shifts) 26.00 II Repair & Maintenance (Including consumables) 20.00 III L.C Charges opened by PSEB 0.20 g p y IV Admin., Audit & legal cost. 2.00 V Traveling & Conveyance 2.00 VI Housekeeping 0.50 VII Insurance 17.59 VIII Mill Channel compensation 7.67 VIII Mill Channel compensation 7.67 IX Contribution to NRSE fund/ Cess Charges 3.60 TOTAL: 79.56 Thus, Thus, the the fixation fixation of
O&M cost cost at at Rs Rs. . 12 12. .00 00 Lac/MW Lac/MW per per annum annum is is grossly grossly low low. . In In the the light light of
above it it is is humbly humbly requested requested that that O O & & M M cost cost should should be be
Himachal Small Hydro Power Association
g y q fixed fixed higher higher at at a a realistic realistic level level. .
Break Break-
up of
Salary & & Wages Wages : : S. NO DESCRIPTION RS. (LACS) a Plant Manager-1 No. @ Rs. 40000/-each 4.8 b Plant Shift Supervisor 4 Nos @ Rs 15000/ PSS/Month 7 2 b Plant Shift Supervisor- 4 Nos.@ Rs.15000/-PSS/Month 7.2 c Technical Assistants- 7 Nos. Rs. 6000/-each/month 5.0 d Maintenance Executive-1 Nos. @ Rs. 15000/- each/month. 1.8 Maintenance Staff Electricians/ Fitter 3 Nos e Maintenance Staff Electricians/ Fitter 3 Nos. @ Rs.10000/-each/month 3.6 f Finance,Commercial,Secretarial,HR-2 Nos. @Rs.15000/- h 3.6
Himachal Small Hydro Power Association
each 3 6
U f t t l U f t t l th th D ft D ft R l ti R l ti h l k d l k d t C b C b C dit C dit
Unfortunately, the the Draft Draft Regulations Regulations has has looked looked at at Carbon Carbon Credits Credits under under the the CDM CDM mechanism mechanism in in a a routine routine manner manner as as additional additional income income which which needs needs to to be be shared shared with with the the beneficiaries beneficiaries. . The The very very genesis genesis of
availability of
CDM benefits benefits is is that that these these are are given given to to t / t / t i t i b i b i f d f d b th th d l d l compensate/ compensate/ overcome
certain barriers barriers faced faced by by the the developers developers . .
The sharing sharing scheme scheme proposed proposed in in the the Draft Draft Regulations Regulations will will jeopardize jeopardize the the very very basis basis of
eligibility of
CDM benefits benefits jeopardize jeopardize the the very very basis basis of
eligibility of
CDM benefits benefits.
Beneficiaries are are not not bothered bothered about about the the challenges challenges or
risks associated associated with with the the development development of
projects. . The The income income from from C b C b C dit C dit i i t iti t iti t th th i k i k tt h d tt h d ith ith th i th i Carbon Carbon Credits Credits is is to to mitigate mitigate the the risks risks attached attached with with their their development development. .
Thus the the CDM CDM benefits benefits should should be be allowed allowed to to be be retained retained by by the the
Thus the the CDM CDM benefits benefits should should be be allowed allowed to to be be retained retained by by the the developers developers. .
Himachal Small Hydro Power Association
21
9. . REGULATION REGULATION 22 22: : SUBSIDY SUBSIDY AND AND INCENTIVES INCENTIVES BY BY THE THE CENTRAL/ CENTRAL/ STATE STATE GOVT GOVT. .
Draft Regulations Regulations specifies specifies that that Capital Capital Subsidy Subsidy or
incentive offered
by the the Central/State Central/State Govt Govt. . to to the the project project developers developers would would be be considered considered while while determining determining the the Tariff Tariff. .
The Govt Govt. . of
India through through MNRE MNRE provides provides capital capital subsidy subsidy mainly mainly on
account account of
following: : 1. . To To attract attract investments investments in in Renewable Renewable Energy Energy sector sector by by offering
reward reward to to the the developers developers for for taking taking up up the the projects projects in in difficult difficult and and harsh harsh environment environment. . 2. . To To compensate compensate the the risks risks and and costs costs associated associated with with the the development development of
SHPs.
The proposal proposal of
taking capital capital subsidy subsidy into into account account for for determination determination of
tariff tariff means means giving giving incentive incentive by by one
hand and and taking taking it it away away by by the the
.
Himachal Small Hydro Power Association
22
SHPs are are still still at at nascent nascent stage stage and and needs needs support support to to attract attract S s S s a e a e st st at at asce t asce t stage stage a d a d eeds eeds suppo t suppo t to to att act att act investment investment in in the the sector sector. .
Rather it it must must be be ensured ensured that that the the reimbursement reimbursement of
any additional additional
Rather it it must must be be ensured ensured that that the the reimbursement reimbursement of
any additional additional levy, levy, taxes/duties taxes/duties imposed imposed by by the the Central/State Central/State Govt Govt. . on
IPPs from from time time to to time time must must be be built built into into the the Tariff Tariff. .
Himachal Small Hydro Power Association
23
10 10. . REGULATION REGULATION 30 30: : AUXILIARY AUXILIARY CONSUMPTION CONSUMPTION Draft Draft Regulations Regulations proposes proposes that that the the normative normative auxiliary auxiliary
Draft Regulations Regulations proposes proposes that that the the normative normative auxiliary auxiliary consumption consumption for for SHPs SHPs to to be be 0 0. .5 5% %
Firstly, these these does does not not include include transformation transformation losses losses. . y, y, Transformation Transformation losses losses are are in in the the range range of
to 1 1. .5 5% %. .
Secondly, the the auxiliary auxiliary consumption consumption based based on
actual date date is is as as below below : below below : 1. 1. Operation Operation loads loads like like cooling cooling water water-
pumps, booster booster pumps, pumps, trash trash machine, machine, turbines turbines OPU, OPU, Gearbox Gearbox 1.0% 1.0% p p p p OPU OPU. . 2. 2. Lighting like tubes/HPSV lamps Lighting like tubes/HPSV lamps 0.3% 0.3% 3. 3. Ventilation equipment like exhaust fans. Ventilation equipment like exhaust fans. 0.3% 0.3% Total Auxiliary Consumption: Total Auxiliary Consumption: 1 6% 1 6%
Himachal Small Hydro Power Association
Total Auxiliary Consumption: Total Auxiliary Consumption: 1.6% 1.6%
24
For underground underground Power Power Houses Houses the the Auxiliary Auxiliary Consumption Consumption excluding excluding transformation transformation losses losses is is 2 2. .5 5 to to 3. .0 0 % %
In the light of this, the Auxiliary Consumption and transformation losses need to be reassessed and a detailed actuaL study may be losses need to be reassessed and a detailed actuaL study may be carried out in this regard. carried out in this regard. OTHER SUBMISSIONS: OTHER SUBMISSIONS:
It is pertinent to mention that many State Govts. are purchasing power from SHPs at very low Tariff like Rs. 2.50 to Rs.3.00 per unit power from SHPs at very low Tariff like Rs. 2.50 to Rs.3.00 per unit and selling their surplus power to other states at the rate of market and selling their surplus power to other states at the rate of market rates of Rs 7 00 to Rs 8 00 per unit They are making unjustified rates of Rs 7 00 to Rs 8 00 per unit They are making unjustified rates of Rs. 7.00 to Rs. 8.00 per unit. They are making unjustified rates of Rs. 7.00 to Rs. 8.00 per unit. They are making unjustified profits at the cost of SHPs. profits at the cost of SHPs.
The Draft Draft Regulations Regulations should should have have some some provisions provisions on
the profit profit g p p sharing sharing with with IPPs IPPs by by buyers buyers of
power of
SHPs who who further further trade trade their their power power. .
Himachal Small Hydro Power Association
25
Himachal Small Hydro Power Association
26