Hallfield Estate W104 Service Providers Proposal (SPP) Meeting Thursday 5 September 2019 Introducing Axis Bob Needham Contracts Manager Ownership Family Claire Walmer-Smith Turnover Established Values Led Pre-construction 150m 1986


slide-1
SLIDE 1

Hallfield Estate W104 Service Providers Proposal (SPP) Meeting Thursday 5 September 2019

slide-2
SLIDE 2

Established

1986

Ownership

Family

Turnover

£150m

Staff

850+

Offices

11

Credit Rating

AAAA

Values Led

8 Values

Fleet

350+

Introducing Axis

Bob Needham Contracts Manager Claire Walmer-Smith Pre-construction manager Kyla Fry Senior Resident Liaison Officer

slide-3
SLIDE 3

Works and Programme

slide-4
SLIDE 4

Proposed Works

Work Element Marlow House Taunton House Newbury House Scaffold and hoist

  • Communal Lighting
  • Extractor Fans *
  • Front door replacement*
  • Balcony door replacement

N/A

  • N/A

Soffit insulation to undercrofts including pram sheds

  • N/A

Decorations

  • External tile replacement
  • N/A

N/A Brickwork/Concrete/Asphalt repairs

  • Brickwork cleaning
  • Window Replacement
  • N/A

Metal work repairs

  • * Leasehold opt in available
slide-5
SLIDE 5

Replacement front doors

Timber hardwood door with glazed fanlight and door closer Designed to meet PAS23/24 Secured by design standards. Available for leaseholder opt in Five colour choices available: Red Green Black Blue Grey

slide-6
SLIDE 6

Replacement windows

Smart Alitherm Heritage windows Tested to BS6375:Part 1 Double glazed units Designed to fit within existing opening Front elevations to receive two large tilt and turn inward windows and an outward

  • pening fanlight.
slide-7
SLIDE 7

Tile replacement – Marlow House

Can the existing tiles be repaired? The below repair was built up using Sika products 610 and 615, once this had cured tinted stone restoration coatings were applied. The repair could not achieve a smooth enough finish to replicate the existing and would have required a redecoration cycle to be implemented to maintain; therefore replacement tiles were sought

slide-8
SLIDE 8

Tile replacement – Marlow House

Tile replacement – ‘Off the shelf’ Several ‘off the shelf’ tiles were sourced based on a small sample taken from Marlow House. Whilst these provided a close match it was not felt that they were close enough to be submitted to Westminster City Council for approval. A bespoke tile service was then sought.

Design works H&E Smith

slide-9
SLIDE 9

Tile replacement – Marlow House

Tile replacement – Bespoke The below shows bespoke tinted tiles produced by H&E Smith, these are predominately indoor tiles but are dip treated in a silicon solution to allow outside use. Two colours have been proposed and presented to Westminster Planning for final decision, these have been installed to the end of Caernarvon House.

slide-10
SLIDE 10

PROGRAMME

Axis propose carrying out the W104 project over 52 weeks It will take 30 days to erect scaffold to Marlow House and 20 days to Newbury and Taunton Houses Internal works programme is proposed to be up to 10 days per property

Duration per block

  • Marlow House – 25 weeks
  • Newbury House – 15 weeks
  • Taunton House – 14 weeks
slide-11
SLIDE 11

INTERNAL PROGRAMME

Day 1 Prepare and protect work areas fully

  • Remove internal reveals for window installation
  • Installation of fans to bathroom and kitchen

(leaseholder opt in) Day 2

  • Adjustment to plumbing pipework adjacent to

front door

  • Window installation to kitchen and bathroom

Day 3 Window installation to rear elevation Front door installation (leaseholder opt in) Boxing in to pipework around door Making good to bathroom and window surrounds (3 days) Day 4

  • Making good to rear elevation windows (1 day)

Day 5

  • Final decorations
  • Removal of protection and clean for weekend

Day 6 Prepare and protect work areas fully Complete tiling to kitchen and bathroom windows Day 7 – 10 Allowance for any defects found to be rectified and sign off by WCC.

slide-12
SLIDE 12

Proposed Site Set Up Location

slide-13
SLIDE 13

Delivering Excellence in Resident Liaison

slide-14
SLIDE 14

Dedicated Resident Liaison Officer (RLO)

  • n site who will be your first point of

contact. Structured liaison processes for residents and leaseholders RLOs based on site full-time to provide: Accessible liaison Regular updates Prompt resolution of issues 0800 contact numbers

slide-15
SLIDE 15

Continuous communications Survey Packs & Newsletters Resident Surgeries/Coffee Mornings Site Update Site-based RLO Complaints Resolution & Log for learning Engage with Resident Area Panels, Resident associations & Councillors. Code of Conduct & ‘My Mum’s House’

slide-16
SLIDE 16

Social Value

slide-17
SLIDE 17

Throughout the duration of the project Axis Europe will aim to carry out community projects within the local community. Axis have already built a positive relationship with Hallfield Primary School carrying out various fun events including, – bookmark making for world book day, pumpkin carving and Halloween picture hunt as part of the phase 1 project.

  • Axis contract staff will be given 1 volunteering

days to be used exclusively for WCC.

  • The Axis Foundation; Donated over

£1,000,000 to date

  • 2% of Axis’ profit is given to the Foundation

each year to fund the support it provides We have previously taken part in

  • Sports & Health inclusion schemes
  • Park Days to Improve green areas
  • School fun events

George Tappenden Wheelchair Donation Swale Gloves Amateur Boxing Club Social Value on Hallfield Estate

slide-18
SLIDE 18

Thank You

Any Questions?