Government Office Center
Mid-Atlantic U.S.
Penn State AE Senior Thesis Project
Alexander Ward | Construction Management
James Faust | CM Advisor
Government Office Center Mid-Atlantic U.S. Penn State AE Senior - - PowerPoint PPT Presentation
Government Office Center Mid-Atlantic U.S. Penn State AE Senior Thesis Project Alexander Ward | Construction Management James Faust | CM Advisor Government Office Center Mid-Atlantic U.S. Presentation Outline: I. Project Background II.
Mid-Atlantic U.S.
Penn State AE Senior Thesis Project
Alexander Ward | Construction Management
James Faust | CM Advisor
Mid-Atlantic U.S.
Penn State AE Senior Thesis Project
Alexander Ward | Construction Management
James Faust | CM Advisor
Presentation Outline:
I. Project Background
A. Engaged Owner
A. Renewable Energy/Electrical Breadth
A. Facilities Management
V. Analysis #4: Progressive Collapse
A. Structural Breadth
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Slide 3
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Problem Identification:
Research Goal:
Slide 4
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
An Engaged Owner is:
process
construction strategies when feasible
…improved delivery through schedule acceleration…
Slide 5
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
An Engaged Owner is:
considered by the project team
design options
phase
…improved delivery through schedule acceleration… …faster and more refined decision making…
Slide 6
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
An Engaged Owner is:
development process
meet the previously defined program requirements
needed and what it will accomplish
…improved delivery through schedule acceleration… …faster and more refined decision making… …reduced frequency and degree of changes…
Slide 7
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Problem Identification:
activities
Research Goal:
Slide 8
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Activities:
Slide 9
North Area in Red – South Area in Blue
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Existing Schedule:
2013 (101 weeks)
North and South
days (North finishes)
Slide 10
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Slide 11
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Slide 12
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Slide 13
Feasibility: +$404,200 for PV marginal cost –$382,500 for sunshades deduction =$21,700 net marginal cost ~$13,000 per year in energy savings
Need to consider heat gain, constructability, etc.
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Problem Identification:
future needs Research Goal:
facilities management uses
Slide 14
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Slide 15
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Slide 16
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Problem Identification:
federal requirements Research Goal:
adding this scope of work in three scenarios
Slide 17
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Freyrom Anchor Section
Slide 18
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
The Balfour Beatty Construction Team Industry Professionals Penn State AE Department My Family and Friends
Slide 19
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions VII.Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
McDonough + Partners
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Traditional SIPS: Non-Traditional SIPS:
Presentation Outline:
I. Project Background
Wall Activities
BIM
Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.