Georgia IM CULV(25) 502 Public Hearing December 17, 2014 1 - - PowerPoint PPT Presentation

georgia im culv 25 502 public hearing
SMART_READER_LITE
LIVE PREVIEW

Georgia IM CULV(25) 502 Public Hearing December 17, 2014 1 - - PowerPoint PPT Presentation

12/16/2014 Replacement of I-89 Culverts 83-1 N&S Georgia IM CULV(25) 502 Public Hearing December 17, 2014 1 12/16/2014 Introductions: VTrans Project Management Team Mahendra Thilliyar Todd Sumner VHB Engineering Team Aaron Guyette


slide-1
SLIDE 1

12/16/2014 1 Replacement of I-89 Culverts 83-1 N&S

Georgia IM CULV(25) 502 Public Hearing

December 17, 2014

slide-2
SLIDE 2

12/16/2014 2

Introductions:

VTrans Project Management Team Mahendra Thilliyar Todd Sumner VHB Engineering Team Aaron Guyette Scott Burbank

slide-3
SLIDE 3

12/16/2014 3

Presentation Overview

  • Existing Conditions
  • Project Development
  • Base Technical Concept
  • Construction Methods
  • Project Schedule
  • Questions/Comments
slide-4
SLIDE 4

12/16/2014 4

Location Map: 83-1 N&S

83-1N 83-1S

slide-5
SLIDE 5

12/16/2014 5

Existing Conditions: 83-1 Culverts

  • Interstate Construction in 1967
  • Galvanized Steel Plate Culverts
  • Approximately 50 Years of Service
  • End of Useful Service Life
slide-6
SLIDE 6

12/16/2014 6

Existing Conditions: 83-1 N

  • Unnamed Tributary under I-89 Northbound
  • 176-FT Long
  • 6-FT Span
  • 25º Skew
  • Current Culvert Rating: 3 – Serious Condition
  • Yearly Inspection Frequency
slide-7
SLIDE 7

12/16/2014 7

slide-8
SLIDE 8

12/16/2014 8

Existing Conditions: 83-1 S

  • Unnamed Tributary under I-89 Northbound
  • 214-FT Long
  • 6-FT Span
  • 25º Skew
  • Current Culvert Rating: 3 – Serious Condition
  • Yearly Inspection Frequency
slide-9
SLIDE 9

12/16/2014 9

slide-10
SLIDE 10

12/16/2014 10

Project Development

  • Design-Bid-Build Overview
  • Design-Build Overview
  • Regional Outreach
  • Regional Considerations
slide-11
SLIDE 11

12/16/2014 11

Project Development: Traditional Design-Bid-Build (D-B-B)

Phase A: Project Definition (1-2 years)

  • Data Collection, Survey, Environmental Resource ID, Scoping
  • Alternatives Study, Preferred Alternative Selection, Conceptual Plans

Phase B: Project Design (1-3 years)

  • Design Milestones – Preliminary, Semi-Final, Final, Contract Plans
  • Engineering, Permitting, ROW, Construction Bid Documents

Phase C: Construction (1-3 years)

  • Advertisement and Bidding, Selection of Contractor
  • Construction
slide-12
SLIDE 12

12/16/2014 12

Design-Build (D-B) Overview

What is “Design-Build”?

  • Single contract with D-B Team engineering/construction
  • Saves time, saves cost, promotes innovation
  • Design & construction integrated and concurrent

Two-Step Procurement

  • Step 1: Request for Qualifications (RFQ)
  • Shortlist Qualified Teams
  • Step 2: Request for Proposals (RFP)
slide-13
SLIDE 13

12/16/2014 13

Project Development: Design-Build

Phase A: Project Definition, Procurement (6-12 months)

  • Data Collection, Survey, Environmental Resource ID
  • Scoping, NEPA Permitting, Public Outreach
  • Bast Technical Concept (BTC) Design, D-B Procurement Documents

Phase B & C: Design & Construction

  • Concurrent Design, Permitting, Construction by D-B Team
slide-14
SLIDE 14

12/16/2014 14

Project Development

Regional Outreach

  • Regional Stakeholders
  • Regional Planning Commission
  • Municipalities/Selectboards
  • Emergency Services
  • Schools
  • Public Transit
slide-15
SLIDE 15

12/16/2014 15

Project Development

Regional Considerations

  • Foliage Season
  • Ski Season
  • Summer Tourism/Lake Champlain
  • Holidays
  • Local and Regional Events
slide-16
SLIDE 16

12/16/2014 16

Base Technical Concept

Base Technical Concept (BTC)

  • Conceptual Design
  • Minimum Design and Construction Parameters
  • Specific vs. Non-Specific

Alternative Technical Concepts (ATC)

  • Submitted and Vetted during Procurement
  • Allows for Innovation and Added Value
  • Review and Approve Approach Prior to Proposal

Submission

slide-17
SLIDE 17

12/16/2014 17

Base Technical Concept

  • Base Technical Concept Plans
  • Structure Concept
  • Roadway Geometry
  • Traffic Control
  • Critical Path Schedule
  • Utility All Clear
  • ROW All Clear
  • NEPA Document
slide-18
SLIDE 18

12/16/2014 18

Base Technical Concept

Utility Coordination

  • Existing Utility Identification
  • Concept Development and Existing Utility Impacts
  • New Utility Considerations
  • Utility All Clear

ROW Coordination

  • Existing ROW documentation
  • Concept Development and Review of Potential ROW Impacts
  • ROW Aquisition
  • ROW All Clear
slide-19
SLIDE 19

12/16/2014 19

Base Technical Concept

Environmental Coordination/NEPA Documentation

  • Biological, Historical, Archaeological Resource Reports
  • Concept Development and Limits of Disturbance
  • Concept Review with Regulators (USACE, Stream Alt, Fisheries,

Wetlands, Storm Water)

  • NEPA Documentation
slide-20
SLIDE 20

12/16/2014 20

Construction Methods

Structure Typical Section

Structure Concept – Concrete Box Culvert

  • Hydraulics
  • Aquatic Organism Passage (AOP)
  • 100 Year Service Life
slide-21
SLIDE 21

12/16/2014 21

Construction Methods

Traffic Control

  • DHV ~ 1900 VPH
  • Two Lanes During Peak Hours
  • SB in AM
  • NB in PM
  • No Crossovers
  • Trenchless Construction
  • Limited Short-Term Lane

Closures during Off-Peak Hours

slide-22
SLIDE 22

12/16/2014 22

Construction Methods

Trenchless Construction

slide-23
SLIDE 23

12/16/2014 23

Construction Methods

Trenchless Construction

  • Jacking with “Hand Excavation”
  • Jack Upstream
  • Two Jacking Pits (Inlet and Median)
  • Two Receiving Pits (Median and Outlet)
  • Traffic will be Maintained During Jacking
slide-24
SLIDE 24

12/16/2014 24

Construction Methods

Trenchless Construction

slide-25
SLIDE 25

12/16/2014 25

Construction Methods

Roadway Surface Treatment

  • Cold Plane and re-pave

Interstate Typical Section

slide-26
SLIDE 26

12/16/2014 26

Construction Methods

Traffic Control

  • Maintain Two Lanes of Traffic

During Peak Hours

  • Reduce Speed to 55 MPH
  • Transportation Management Plan
  • Smart Work Zone
slide-27
SLIDE 27

12/16/2014 27

Schedule

  • Project Definition
  • Project Procurement
  • Design and Construction
slide-28
SLIDE 28

12/16/2014 28

Schedule: Project Definition

Design-Build Scoping Process

  • Environmental Resource Identification & Review – Completed
  • Ground Survey & Utility Identification – Completed
  • Public Informational Meeting – Completed
  • NEPA – National Environmental Policy Act Permitting – Spring 2014
  • D-B Procurement Documents – in progress
  • Base Technical Concept – in progress
  • ROW and Utility Clearances – Winter 2015
  • Procurement Process – Spring/Summer/Fall 2015
slide-29
SLIDE 29

12/16/2014 29

Schedule: Project Procurement

Design-Build Procurement Process

  • Advertised RFQ – Spring 2014
  • Developed Shortlist – Summer 2014
  • Develop RFP – Winter 2014 - 2015
  • Release RFP to Shortlist – Spring 2015
  • Determine Best Value D-B Team – Summer 2015
slide-30
SLIDE 30

12/16/2014 30

Schedule: Design & Construction

Design & Construction Process

  • Contract Award – Summer/Fall 2015
  • Permitting and Design – Fall/Winter 2015
  • Construction – 2015-2016
slide-31
SLIDE 31

12/16/2014 31

22 offices throughout the east coast www.vhb.com

Questions/Comments

Mahendra Thilliyar – VTrans mahendra.thilliyar@state.vt.us Aaron Guyette – VHB aguyette@vhb.com

Questions/Comments