gearbox muncie
play

GearBox: Muncie An Entrepreneurial Initiative of Sustainable Muncie - PowerPoint PPT Presentation

GearBox: Muncie An Entrepreneurial Initiative of Sustainable Muncie Corporation Michael Wolfe: President Ontario Systems Todd Donati: Vice President Muncie Redevelopment Commission Sherri Contos: Treasurer Muncie Arts


  1. GearBox: Muncie An Entrepreneurial Initiative of Sustainable Muncie Corporation

  2. — Michael Wolfe: President ◦ Ontario Systems — Todd Donati: Vice President ◦ Muncie Redevelopment Commission — Sherri Contos: Treasurer ◦ Muncie Arts and Culture Council — Kirsten Smith: Secretary ◦ Ball State University Officers of the Board of Directors

  3. — Jeff Bird IU Health — Andy Bowne Ivy Tech — Linn Crull Whitinger — Gary Dannar Dannar USA — Trent Dowling Star Financial — Julie Halbig Ball State University — Steve Moore First Merchants Bank — Nick Tokar DeFur Voran — Dennis Tyler City of Muncie Members of the Board of Directors

  4. — John Fallon, Executive Director — Scott Truex, Director of Facilities and Programming — Brian Hollars, Principal, s3 Architects — Mike Tschour, Principal, Pridemark Construction Company Staff and Other Key Personnel

  5. — October 2014: Committee Appointed — January 2015: Sustainable Muncie Corporation Formed — March 2015: Cintas Building Purchased — July 2015: Staff Engaged — August 2015: Prospective Tenants Identified — December 2015: Project Ribbon Cutting Completed — December 2015: Hope House Committed — December 2015: Construction Plan Developed Brief History of the Initiative

  6. With GearBox: Muncie as the linchpin initiative, Sustainable Muncie Corporation is pursuing several elements of its vision. — Hope House — Live/Work Spaces — Curb/Street Modifications — Other Facilities/Properties — Verge Community — Positioning Muncie as a “Smart City” Vision

  7. — Ball State University/Foundation: $320,000 — City of Muncie: $284,500 — Ball Brothers Foundation: $190,000 — Community Foundation: $30,000 — Muncie Redevelopment Commission: $90,500 — Mutual Bank: $6,100 — Pending Proposals: $230,000 — Other Prospects: $340,000 Funding Committed and Pledged

  8. — Coffee Roaster/Production Bakery — Brewery: 2 — Robotics Organizations and Programs — Arts Advocacy Organization — Fabrication Lab (BSU) — Food Hub (BSU) — Speech and Hearing Clinic (BSU) — Restaurant/Butchery — Various Metal/Wood Workers — Fitness Operation Prospective Tenants

  9. — Cornerstone Center for the Arts ◦ Commitment toward Collaborative Strategic Partnership ◦ Cooperative Planning — Muncie Arts and Culture Council ◦ Arts-Related Events ◦ Direct Connection to Arts Community Special Partnerships

  10. — Architectural Drawings to State 1/15/16 — Interior Demolition/Prep Begins 1/22/16 — Final Bid Packet Released 1/29/16 — Bids Due 2/19/16 — State Approval ~2/22/16 — Construction Begins ~3/1/16 — Tenant Build-Outs Commence ~3/1/16 — Construction Completed 5/15/16 General Construction Timetable

  11. GearBox: Muncie Site Plan

  12. GearBox: Muncie Exterior

  13. GearBox: Muncie Interior

  14. GearBox: Muncie Interior

  15. GearBox: Muncie Interior

  16. GearBox: Muncie Interior

  17. GearBox: Muncie Interior

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend