FY2019

Initial Budget Presentation August 13, 2018

slide-2
SLIDE 2

The Budget Process

FY 2019 Budget Present at ion 2

  • 1. The Mayor considers

staff recommendations as he prepares his Budget

  • 3. Council holds Public

Hearings on the proposed Budget (08/ 27/ 18 and 09/ 17/ 18)

  • 4. Mayor and Council

adopt a final Budget (09/ 17/ 18)

  • 2. The Mayor presents

his Budget proposal to the City Council (08/ 13/ 18)

slide-3
SLIDE 3

Executive Summary

S ix S trategic Goal Areas form basis of budget

 Transportation, Recreation & Parks, Economic Development, Government

Efficiency, Public S afety, and Quality of Life

Examine operating expenditures and revenues

 Close review of departmental expenditures to control growth and ensure

balanced budget

Continued use of Accruals

 Updated data to ensure adequate levels for the future  Added new Equipment Accrual

Five Themes throughout budget

 Transparency, budget maturity, promise made – promise kept, reflecting true

cost of service, year of stormwater

FY 2019 Budget Present at ion 3

slide-4
SLIDE 4

MAJOR BUDGET THEMES

slide-5
SLIDE 5

Five Major Budget Themes

  • 1. Transparency

 Detailing moves / shifts within the Budget  Detailing one-time and non-recurring expenditures

  • 2. Budget Maturity

 Adding Equipment Accrual  S

hifting Repairs and Maintenance out of Operations

  • 3. Promise Made / Promise Kept

 Fire S

tation #64 Construction

 Abbotts Bridge S

  • und Abatement

FY 2019 Budget Present at ion 5

slide-6
SLIDE 6

Five Themes with Budget

  • 4. Reflecting True Cost of Service

 Adj usting based on known costs  Meeting defined service level

expectations

  • 5. Year of Stormwater

 Inventory / Assessment of S

ystem

 End Y

ear with a long term maintenance plan and options for funding mechanisms

FY 2019 Budget Present at ion 6

slide-7
SLIDE 7

GENERAL FUND: S

UMMAR Y OVER VIEW

FY 2019 Budget Present at ion

slide-8
SLIDE 8

General Fund Revenue Trends (‘ 16-‘ 19)

20.0 15.2 4.8 2.5 1.7 1.3 1.1 0.8 0.9 0.7 4.9 20.2 5.9 5.1 2.5 1.8 1.4 1.1 0.8 0.6 0.7 28.1 20.0 17.3 4.8 2.2 1.8 1.3 1.1 0.8 0.7 0.7 3.7 0.7

20.9 18.4 5.1 2.3 1.8 1.2 1.0 0.8 0.8 0.7 3.7 3.3 $- $5.0 $10.0 $15.0 $20.0 $25.0 $30.0

Total Amount Collected/ Budgeted (in millions) FY 2016 FY 2017 FY 2018 Revised FY 2019 Proposed

slide-9
SLIDE 9

General Fund Revenue: $59,963,891

FY 2019 Budget Present at ion 9

Local Option Sales Tax 35% Property Taxes Current Year 30%

Real Property Prior Year, 1% Insurance Premium Tax, 9% Electric Franchise Fees, 4% Business & Occupation Tax, 3% Municipal Court Fees, 2% Television Cable … Alcohol Beverage Excise, 1% Building Residential, 1% Gas Franchise Fees, 1% All Other Revenues, 6%

slide-10
SLIDE 10

Top 10 Revenue Comparison (‘ 18 to ‘ 19)

FY 2019 Budget Present at ion

Local Option Sales Tax: $20.0 Local Option Sales Tax: $20.9

Property Taxes (Current Year): $16.7 Property Taxes (Current Year): $17.7

Propert y Taxes (Prior Year): $0.6 Propert y Taxes (Prior Year): $0.7

Insurance Premium Tax:$4.8 Insurance Premium Tax:$5.1

Elect ric Franchise Fees: $2.2 Elect ric Franchise Fees: $2.3 Business & Occupat ion Tax: $1.8 Business & Occupat ion Tax: $1.8 Municipal Court Fees: $1.3 Municipal Court Fees: $1.2 Television Cable Franchise … Television Cable Franchise … Alcohol Beverage Excise:$0.8 Alcohol Beverage Excise:$0.8 Building Resident ial: $0.7 Building Resident ial: $0.8 Gas Franchise Fees: $0.7 Gas Franchise Fees: $0.7 All Ot her Revenues:$3.7 All Ot her Revenues:$3.7 Use of Reserves: $0.7 Use of Reserves: $3.3

$0 $10 $20 $30 $40 $50 $60

FY 2018 Revised FY 2019 Proposed Total Revenue Amount (in millions)

slide-11
SLIDE 11

Revenue Variance Analysis (‘ 18 to ‘ 19)

11 Local Opt ion S ales Tax Propert y Taxes (Current Year) Propert y Taxes (Prior Year) Insurance Premium Tax Elect ric Franchise Fees Business & Occupat i

  • n Tax

Municipal Court Fees Televisio n Cable Franchise Fees Alcohol Beverage Excise Building Resident i al Gas Franchise Fees All Other Revenues Use of Reserves FY18 t o FY19 Variance 4.3% 5.6% 18.6% 5.9% 4.3% 0.0%

  • 7.4%
  • 7.3%

1.8% 11.4% 0.7%

  • 0.9%

77.9%

4.3% 5.6% 18.6% 5.9% 4.3% 0.0%

  • 7.4%
  • 7.3%

1.8% 11.4% 0.7%

  • 0.9%

77.9%

  • 20.0%
  • 10.0%

0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0%

% Change between Fiscal Y ears

slide-12
SLIDE 12

Revenue Trends (‘ 17 to ‘ 19)

12

$20.2 $20.0 $20.9 $20.9

$3.9 $16.7 $17.7 $17.7

$2.0 $0.6

$13.4

$0.7

$5.1 $4.8 $5.1 $5.1

$2.5 $2.2 $2.3 $2.3 $1.8 $1.8 $1.7 $1.8 $1.4 $1.3 $1.2 $1.2

$28.1

$3.7 $4.0 $3.7 $0.7 $0.0 $3.3

$0 $10 $20 $30 $40 $50 $60 $70

FY 2017 FY 2018 Revised FY 2018 Annualized FY 2019 Proposed

Total Revenue Amount (in millions)

Use of Reserves All Ot her Revenues Gas Franchise Fees Building Residential Alcohol Beverage Excise Television Cable Franchise Fees Municipal Court Fees Business & Occupation Tax Elect ric Franchise Fees Insurance Premium Tax Property Taxes (Prior Year) Property Taxes (Current Year) Local Option S ales Tax

slide-13
SLIDE 13

General Fund Expenditures

FY 2019 Budget Present at ion 13

E911 Supplement, 0.2% Capital Projects Fund, 9.0% Infrastructure Maintenance Accrual, 14.2% Equipment Accrual, 1.2% Vehicle Replacement Accrual, 1.7% Positions and Associated Vehicles/Equipment, 0.7% City Hall Debt Service, 3.4%

Base Operations Personnel 43.3% Base Operations Operations 26.2%

slide-14
SLIDE 14

Expenditure Comparison (‘ 18 to ‘ 19)

FY 2019 Budget Present at ion E911 S upplement , $0.1 E911 S upplement , $0.1

Capital Projects Fund, $2.9 Capital Projects Fund, $5.5 Infrastructure Maintenance Accrual: $6.6 Infrastructure Maintenance Accrual: $8.5

Equipment Accrual, $0.7 Vehicle Replacement Accrual, … Vehicle Replacement Accrual, $1.0 Posit ions and Associat ed …

City Hall Debt Service, $2.0

Base Operations

  • Personnel:

$25.4 Base Operations

  • Personnel:

$26.0

Base Operations - Operations, $18.6 Base Operations - Operations, $15.7

$0 $10 $20 $30 $40 $50 $60

Total Expenditure Amount (in millions)

Expenditure Categories by Fiscal Year

slide-15
SLIDE 15

Expenditure Variance Analysis (‘ 18 to ‘ 19)

15 E911 S upplement Capit al Proj ect s Fund Infrastructure Maint enance Accrual Equipment Accrual Vehicle Replacement Accrual Posit ions and Associat ed Vehicles/ Equi pment Cit y Hall Debt S ervice Base Operat ions - Personnel Base Operat ions - Operat ions FY18 t o FY19 Variance 0.0% 46.6% 22.6% 100.0% 1.5% 100.0% 72.2% 2.3%

  • 18.3%

0.0% 46.6% 22.6% 100.0% 1.5% 100.0% 72.2% 2.3%

  • 18.3%
  • 25.0%
  • 5.0%

15.0% 35.0% 55.0% 75.0% 95.0% % Change between Fiscal Y ears

slide-16
SLIDE 16

Expenditure Trend (‘ 16 – ’ 19)

FY 2019 Budget Present at ion 16 $0.5 $0.4 $0.1 $0.1

$26.4 $2.9 $5.5 $7.6 $6.6 $8.5

$0.7 $1.7 $1.0 $1.0 $0.4 $2.0

$21.9 $22.6 $25.4 $26.0 $19.4 $20.2 $18.6 $15.7

$- $10.0 $20.0 $30.0 $40.0 $50.0 $60.0 $70.0 $80.0

Actuals Revised Proposed FY 2016 FY 2017 FY 2018 FY 2019

Total Expenditure Amount (in milions)

Base Operat ions - Operat ions Base Operat ions - Personnel Cit y Hall Debt S ervice Posit ions and Associated Vehicles/ Equipment Vehicle Replacement Accrual Equipment Accrual Infrast ruct ure Maint enance Accrual Capital Proj ect s Fund E911 S upplement

slide-17
SLIDE 17

GENERAL FUND: BAS

E OPERATIONS OVER VIEW

FY 2019 Budget Present at ion

slide-18
SLIDE 18

Base Operations

18

City Clerk 1% City Council 1% City Manager 3% Communications 1% Community Development 5% Facilities 4% Finance 3%

Fire 26%

Human Resources 3% IT/GIS 5% Legal 1% Municipal Court 2%

Police 26%

Public Works 14%

Parks 5%

slide-19
SLIDE 19
  • Dept. Expenditures Trends (‘ 16-‘ 19)

FY 2019 Budget Present at ion 19

0.6 0.3 1.2 0.7 2.7 1.7 1.1 $10.5 0.6 2.1 0.3 0.6 9.4 7.3 2.1 0.4 0.3 1.3 0.5 2.4 1.9 1.0 11.2 0.8 1.9 0.3 0.6 9.8 8.2 2.2 0.7 0.4 1.2 0.6 2.4 1.5 1.3 11.2 1.0 2.0 0.5 0.7 11.0 7.3 2.3

0.4 0.3 1.1 0.6 2.2 1.5 1.3 11.0 1.1 1.9 0.4 0.7 11.0 6.0 2.0

$- $2.0 $4.0 $6.0 $8.0 $10.0 $12.0

Total Expenditure Amount (in millions)

FY 2016 FY 2017 FY 2018 Revised FY 2019 Proposed

slide-20
SLIDE 20

Personnel v. Operations (‘ 16 to ’ 19)

20 Rec & Parks Rec & Parks Rec & Parks Rec & Parks

PW

PW

PW

PW

PW

PW

PW

PW

Police Police Police Police Police Police Police Police

IT/GIS IT/GIS IT/GIS IT/GIS IT/GIS IT/GIS IT/GIS IT/GIS HR HR HR HR HR HR HR HR

Fire Fire Fire Fire Fire Fire Fire Fire

Finance Finance Finance Finance Finance Finance Finance Finance Facilit ies Facilit ies Facilit ies Facilit ies Facilit ies Facilit ies Facilit ies Facilit ies

Comm Dev Comm Dev Comm Dev Comm Dev Comm Dev Comm Dev Comm Dev Comm Dev

CM CM CM CM CM CM CM CM

  • 5.0

10.0 15.0 20.0 25.0 30.0

Persons Ops Persons Ops Persons Ops Persons Ops FY 2016 FY 2017 FY 2018 Revised FY 2019 Proposed

Total Expenditure Amount

(in millions)

Clerk Council CM Comm Comm Dev Court Facilities Finance Fire HR IT/GIS Legal Police PW Rec & Parks

slide-21
SLIDE 21

Personnel Costs Changes (‘ 16 to ‘ 19)

FY 2018 Budget Book Present at ion 21

$21.9 $22.6 $25.4 $26.0

$- $5.0 $10.0 $15.0 $20.0 $25.0 FY 2016 FY 2017 FY 2018 Revised FY 2019 Proposed

Total Expenditures (in millions)

slide-22
SLIDE 22

Personnel Cost – % Change Over Time

FY 2019 Budget Present at ion 22

2% 3% 11% 2% 0% 6% 12%

FY 2016 FY 2017 FY 2018 Revised FY 2019 Proposed

Total Expenditure % Change from Previous FY

slide-23
SLIDE 23

Operations Cost Changes (‘ 16 to ‘ 19)

FY 2019 Budget Present at ion 23

$19.4 $20.2 $18.6 $15.7

$- $5.0 $10.0 $15.0 $20.0 $25.0

FY 2016 FY 2017 FY 2018 Revised FY 2019 Proposed

Total Expenditures (in millions)

slide-24
SLIDE 24

Operation Cost - % Change Over Time

FY 2019 Budget Present at ion 24

  • 16%

4%

  • 9%
  • 18%
  • 20%
  • 14%
  • 8%
  • 2%

4% 10% 16%

FY 2016 FY 2017 FY 2018 Revised FY 2019 Proposed

Tot al Expendit ure % Change from Previous FY

slide-25
SLIDE 25

ACCRUAL FUNDS: OVER

VIEW

FY 2019 Budget Present at ion

slide-26
SLIDE 26

Accrual Funds

Embracing the concept of paying oneself first, the City sets aside funds from the current year to cover infrastructure maintenance, vehicle and equipment replacements

FY2019 adds a new accrual for equipment (radios / computers / S CBA, etc.)

FY 2019 contributions:

 Infrastructure Maintenance: $8,514,684  Vehicle Replacement: $994,939  Equipment Replacement: $696,802

The accruals total $10,206,424

FY 2018 Budget Book Present at ion 26

slide-27
SLIDE 27

Accruals: 17.1%

  • f General Fund

FY 2019 Budget Present at ion 27

Infrastructure Maintenance Accrual, 14.2% Equipment Accrual, 1.2% Vehicle Replacement Accrual, 1.7%

$10,206,424

slide-28
SLIDE 28

Infrastructure Maintenance Accrual

FY 2019 Budget Present at ion 28

Maintenance Accruals Contributions Projects Balance Roads and (new) Right-of-Way $4,426,026 $3,975,000 $451,026 S idewalks and Trails $489,465 $200,000 $289,465 S tormwater S ystem $308,700 $300,000 $8,700 Traffic S ignals $1,108,420 $1,230,000 ($121,580) Bridges and Tunnels $276,572 $0 $276,572 Parks $1,036,650 $1,000,000 $36,650 Fire S tations $257,250 $204,630 $52,620 City Hall $411,600 $20,000 $391,600 Land Acquisition $200,000 $0 $200,000 Total $8,514,684 $6,929,630 $1,585,054 Beginning Balance: $4,446,959 Ending Balance: $6,032,013

slide-29
SLIDE 29

Maintenance – Project Highlights

FY 2019 Budget Present at ion 29

 Roads and Right-of-Way

 Resurfacing - $2.7M continued effort  Patching - $525K – moved in from Operations and increased by $100K  Pavement Markings - $100K – moved in from Operations  Right-of-Way and Median Refreshes - $250K – moved in from Operations, increased by $100K  S

ign Materials - $100K – moved in from Operations, increased by $50K

slide-30
SLIDE 30

Maintenance – Project Highlights

FY 2019 Budget Present at ion 30

S idewalk Repair and Maintenance – total of $200K

S tormwater Maintenance and Drainage Rehabilitations – total of $300K

Traffic S ignal Proj ects

 S

ignal Detection Replacements - $200K

 Traffic S

ignal Mast Arm Replacements - $500K

 S

chool Flasher S ystem Replacement - $350K

 S

ignal Monitoring Replacements - $80K

 Traffic S

ignal Materials - $100K

slide-31
SLIDE 31

Maintenance – Project Highlights

FY 2019 Budget Present at ion 31

Park Proj ects

 Parks Maintenance Materials - $500K – moves

from operations and increase by $75K

 Autrey Mill Refresh - $50K  Newtown Park Refresh - $130K  Newtown Park Bathroom Refurbishment - $60K  Ocee Park Refresh - $120K  Ocee Park Bathroom Refurbishment - $40K  S

hakerag Park Refresh - $100K

slide-32
SLIDE 32

Maintenance – Project Highlights

FY 2019 Budget Present at ion 32

Fire S tation Proj ects

 S

tation #61 Refresh - $25K

 S

tation #62 Refresh - $25K

 S

tation #63 Refresh - $25K

 Facility Repairs and Maintenance – $50K – move in from

  • perations and increase by $17,730

 S

tation #62 –Apparatus Bay Lighting Replacement - $5,078

 S

tation #61 – Driveway Replacement - $64,500

 S

tation #61 – HV AC Zoning (Office Area) - $3,792

 S

tation #61 and #63 – Wall Cabinet Replacements - $4,760

 S

tation #61, #62, and #63 – Window Blinds and Tint - $1,500

slide-33
SLIDE 33

Vehicle Replacement Accrual

FY 2019 Budget Present at ion 33

Vehicle Accruals Contributions Projects Balance Police $464,025 $492,000 ($27,975) Fire $473,364 $0 $473,364 City Hall $57,551 $40,000 $17,551 Total $994,939 $532,000 $462,939 Beginning Balance: $1,579,360 Ending Balance: $2,042,299

2019 Proj ects

Police: $492,000

 10 vehicles (4 patrol, 2 K9, 2 UC, 2 admin)

City Hall: $40,000

 1 Truck Replacements (2007 2WD Ranger with 4WD F150)

slide-34
SLIDE 34

(new) Equipment Accrual

FY 2019 Budget Present at ion 34

Equipment Accrual Contributions Projects Balance Police Equipment $296,929 $94,700 $202,229 Fire Equipment $191,253 $54,600 $136,653 Information Technology Equipment $208,621 $81,400 $127,221 Total $696,802 $230,700 $466,102 Beginning Balance: $0 Ending Balance: $466,102

slide-35
SLIDE 35

Equipment – Project Highlights

FY 2019 Budget Present at ion 35

 Police: $94,700

 AEDs, Ballistic S

hields, Ballistic Vests – S WAT , Body Armor, Gas Masks and Filters, In- Car Cameras, Lasers, and Radar Units

 Fire: $54,600

 Hoses, S

mall Hardware and Tools, Bunker Gear and Boots, Helmet Fronts, Water Rescue Gear, S wift Water Rescue Wet S uits / PDFs, and S CBA Face Pieces

 Information Technology: $81,400

 Desktop Computers and Printers, In-Car Camera (server side), Laptop Computers,

MCT - Police

slide-36
SLIDE 36

POS

ITION REQUES TS

FY 2019 Budget Present at ion

slide-37
SLIDE 37

Position Requests: 0.7%

  • f General Fund

FY 2019 Budget Present at ion 37

Positions and Associated Vehicles/Equipment, 0.7%

$441,079

slide-38
SLIDE 38

Position / Position-Related Additions

S tormwater Engineer - $117,351 (salary + benefits)

Police Officer Referral Bonus - $5,000 (10 at $500)

S WAT Incentive - $15,000 (6 at $2,500)

Part-Time Retired Officers Program - $103,728 (4 PT Officers)

Traffic Engineer (Contracted) - $200K

Other Requests Not Funded:

 Planner II, Arborist, S

tormwater Inspectors (2), GCIC Clerks (4), and Bike Patrol Officers (2)

FY 2019 Budget Present at ion

slide-39
SLIDE 39

CAPITAL PROJECTS: OVER

VIEW

FY 2019 Budget Present at ion

slide-40
SLIDE 40

Capital Projects: 9%

  • f General Fund

FY 2019 Budget Present at ion 40

$5,478,700

slide-41
SLIDE 41

Capital – Project Highlights

FY 2019 Budget Present at ion 41

S tormwater

 S

tormwater S ystem Assessment - $250K

 S

tream Gauge S ystem - $80K 

Fire Proj ects

 Fire S

tation #64 - $2.6M

 Fuel Pump for Fire S

tation #64 - $19K

 Rescue Lift Bags - $3,510  Headset S

ystem for Rescue Boat - $10,800

 Rapid Intervention Bags - $6,425

slide-42
SLIDE 42

Capital – Project Highlights

FY 2019 Budget Present at ion 42

Information Technology

 ERP –Adding Com Dev to Implementation - $350K  Electronic Plan Review - $40K  Website Content Management S

ystem - $20K 

Police Proj ects

 Polygraph, Chair, and Components - $8,325  Automated License Plate Recognition - $55K  Drone for Accident Reconstruction - $8,500  Body Worn Cameras - $400K

slide-43
SLIDE 43

Capital – Project Highlights

FY 2019 Budget Present at ion 43

Public Works

 S

idewalk / Trail Additions - $500K

 Roundabout Priority S

tudy - $100K

 Buice Road Traffic Calming - $250K  Abbotts Bridge S

  • und Abatement - $750K

Parks

 The Wall That Heals Install Plan - $2,500  Newtown Park – Pickle Ball Courts - $25K

slide-44
SLIDE 44

Capital – Projects Not Funded

FY 2019 Budget Present at ion 44

Additional Capital Requests – Not Funded in FY2019

 Fire: Wireless Headsets for F

AOs, Portable Two-Way Radio S pares, Know Key S ecure Device Replacement

 Police: Video Throw Phone and Crime S

cene 3D S canner

 Public Works: Collector Road Improvements; Traffic S

ignal Addition at Old Alabama and Falls of Autry Mill; Pedestrian Improvements on Taylor Road, Queensbury, and Tech Park; Roundabout S tudies and Engineering; Enhanced S ignal Monitoring and Emergency Preemption; Traffic S ignal Addition at Old Alabama and S pruill Road; Brumbelow / Tuckerbrook Roundabout; and Long Indian Creek S idewalks

 Parks: Newtown Park Pedestrian Bridge; Ocee Park Infield Artificial Turf; S

hakerag Park Cricket Cages; and Ticketed Concert Event 

Unfunded Requests total additional $4,395,500

slide-45
SLIDE 45

TS PLOS T, P

ARKS BOND, CITY HALL AND OTHER FUNDS

FY 2018 Budget Book Present at ion

slide-46
SLIDE 46

TSPLOST, City Hall, and Parks Bond

 Budget forwards Council’s current practice of individually authorizing

proj ects and expenditures for TS PLOS T and the Parks Bond

 TS

PLOS T - revenue is shown as unallocated expenditure less the $500K annual minimum contract with Jacobs/ CH2M for professional management

 Parks Bond - revenue / expenditure is only shown for $150K annual

minimum professional management with Jacobs/ CH2M

 City Hall Fund shows the transfer in / transfer out related to the

$2,045,048 COPS payment to meet debt service obligation

 Expenditures in each of these funds will need to be acted upon by

Council as Budget Amendments in FY2019

FY 2019 Budget Present at ion 46

slide-47
SLIDE 47

Other Funds - Balanced

Fund Revenues Expenditures S eized/ Forfeited Asset Fund 175,650 175,650 E911 Fund 1,790,000 1,790,000 Hotel/ Motel Tax Fund 490,196 490,196 Debt S ervice Fund 533,928 533,928 Debt S ervice Parks Bond Fund 2,093,138 2,093,138

FY 2019 Budget Present at ion 47

slide-48
SLIDE 48

NEXT S

TEPS

FY 2019 Budget Present at ion

First Public Hearing: 08/27/18 Continued Discussion: 09/17/18 S econd Public Hearing: 09/17/18 Adoption: 09/17/18