Fluxys Belgiums experience in REMIT Pilot Project 11/12/2014 ENTSOG Transparency Workshop CONTEXT Remit (Regulation on Energy Market Integrity and Transparency) Purpose: monitor wholesale energy markets to foster open and fair
Wholesale energy transaction including orders to trade Capacity & use of capacity Planned & unplanned maintenance
CONTEXT
Remit (Regulation on Energy Market Integrity and Transparency)
- Purpose: monitor wholesale energy markets to foster open and fair competition through reporting of any information
that may impact prices
- Applies to “Market participants”: Any person, including TSOs, who enters into transactions in wholesale energy markets
Prohibition of insider trading Market monitoring to detect & prevent market manipulation
- Obligation to publish of inside information
Transparency requirement according to reg. EC 715/2009 & Urgent Market Messages
Fundamental data Transactional data
- Implementing acts through comitology to fix data provision requirements to ACER
Basis for market monitoring
- f transactional data
2
20141211 – ENTSOG Transparency Workshop
3
HIGH LEVEL TIMELINE
2012 ACER
Commission
Remit’s entry into force
2013 2011 TSOs, SSOs, LSOs
Redaction of Implementing Acts
2014
Comitology meetings
Recommendation to Commission on Remit Records of Transactions
2015 Market participants 2016 2017
Implementing Acts (comitology) Inside information Prohibitions of insider dealing and market manipulation apply for market participants Obligation to publish inside information applies for market participants Transactional data Fundamental data
Implementing Acts published (entry into force after 20 days) Voted on 3rd of October
20141022 – Easeegas workshop
Expected beginning 2015
ENTSO-G
Remit Pilot Project
Publication of User Manual
4
FUNDAMENTAL DATA
TSO LSO SSO
Publication on Transparency Platform (Reg. EC 715/2009)
Shipper-related information
- Day-ahead & final nominations
- Provisional allocations
Aggregated Transparency information
- Technical, contracted and available capacity
- Daily send-out and inventory of the LNG facility
- Planned and unplanned unavailability
Terminal user information
- unloading and reloading of cargos
- planned usage of the LNG facility
for next month Storage user information
- Amount of gas in stock
Aggregated Transparency information
- Technical, contracted and available capacity
- Gas in stock, injections and withdrawals
- Planned and unplanned unavailability
Aggregated Transparency information
- Capacity and use of facilities for transmission of natural gas
- Planned and unplanned unavailability
20141022 – Easeegas workshop As soon as available on ENTSOG TP Following working day Following working day Following working day As soon as available One month in advance Following working day Following working day As soon as available
5
HIGH LEVEL TIMELINE
2012 ACER
Commission
Remit’s entry into force
2013 2011 TSOs, SSOs, LSOs
Redaction of Implementing Acts
2014
Comitology meetings
Recommendation to Commission on Remit Records of Transactions
2015 Market participants 2016 2017
Implementing Acts (comitology) Inside information Prohibitions of insider dealing and market manipulation apply for market participants Obligation to publish inside information applies for market participants Transactional data Fundamental data
Voted on 3rd of October After 9 months
Reporting of transparency data Reporting of market participant related and LSO, SSO fundamental data
After 15 months
20141022 – Easeegas workshop
Expected beginning 2015
ENTSO-G
Remit Pilot Project
Publication of User Manual Implementing Acts published (entry into force after 20 days)
6
TRANSACTIONAL DATA
Orders to trade
Transactions, including orders to trade
Supply (commodity) Transportation (contracts) Transactions on exchange platform Over-the-counter transactions
To be reported by the
- rganised market
place To be reported by the market participants themselves
20141211 – ENTSOG Transparency Workshop
7
HIGH LEVEL TIMELINE
2012 ACER
Commission
Remit’s entry into force
2013 2011 TSOs, SSOs, LSOs
Redaction of Implementing Acts
2014
Comitology meetings
Recommendation to Commission on Remit Records of Transactions
2015 Market participants 2016 2017
Implementing Acts (comitology) Inside information Prohibitions of insider dealing and market manipulation apply for market participants Obligation to publish inside information applies for market participants Transactional data Fundamental data
Voted on 3rd of October After 9 months
Reporting of transparency data Reporting of transactions concluded on organised market places Reporting of transactions concluded outside
- rganised market places
After 9 months After 15 months
Reporting of market participant related and LSO, SSO fundamental data
After 15 months
20141022 – Easeegas workshop
Expected beginning 2015
ENTSO-G
The organised market place where the transaction was executed or order was placed shall at the request of themarket participant
- ffer a data reporting agreement
Remit Pilot Project
Publication of User Manual Implementing Acts published (entry into force after 20 days)
8
TRANSACTIONAL DATA
8
Orders to trade
Transactions, including orders to trade
Bids for auctions
Supply (commodity) Transportation (contracts)
TSO
Primary market Transactions on exchange platform Over-the-counter transactions Secondary market
Capacity offer for auctions
Secondary market transaction
Auction bids Capacity contracts (auctions & FCFS)
To be reported by the
- rganised market
place To be reported by the market participants themselves By TSO or third parties on their behalf To be reported by the market participants themselves
20141211 – ENTSOG Transparency Workshop
9
HIGH LEVEL TIMELINE
2012 ACER
Commission
Remit’s entry into force
2013 2011 TSOs, SSOs, LSOs
Redaction of Implementing Acts
2014
Comitology meetings
Recommendation to Commission on Remit Records of Transactions
2015 Market participants 2016 2017
Implementing Acts (comitology) Inside information Prohibitions of insider dealing and market manipulation apply for market participants Obligation to publish inside information applies for market participants Transactional data Fundamental data
Voted on 3rd of October After 9 months
Reporting of transparency data
Remit Pilot Project
Reporting of transactions concluded on organised market places Reporting of transactions concluded outside
- rganised market places
After 9 months After 15 months
Reporting of transportation contracts on primary market Reporting of market participant related and LSO, SSO fundamental data
After 15 months
Reporting of transportation contracts on secondary market concluded on organised market places
After 15 months
20141022 – Easeegas workshop
Expected beginning 2015
ENTSO-G
After 15 months
The organised market place where the transaction was executed or order was placed shall at the request of themarket participant
- ffer a data reporting agreement
Publication of User Manual Implementing Acts published (entry into force after 20 days)
10
CONTEXT REMIT PILOT PROJECT
2012 ACER
Commission
Remit’s entry into force
2013 2011
Redaction of Implementing Acts
2014
Comitology meetings
Recommendation to Commission on Remit Records of Transactions
2015 2016 2017
Implementing Acts (comitology) Inside information Prohibitions of insider dealing and market manipulation apply for market participants Obligation to publish inside information applies for market participants Transactional data Fundamental data
Voted on 3rd of October
Expected beginning 2015
Remit Pilot Project Phase I
Purpose Phase I
- To gather valuable input from parties that will be involved in data collection under REMIT
- To develop a working IT system prototype able to collect the data
- To collect sufficient amount of data for initial testing and customisation of Market Monitoring Solution
- To gradually improve and upgrade the prototype to become a fully functional ARIS system
- To identify open issues and problems in the early phase of ARIS implementation
Publication of User Manual Implementing Acts published (entry into force after 20 days)
20141211 – ENTSOG Transparency Workshop
REMIT PILOT PARTICIPANTS PHASE I
11
20141211 – ENTSOG Transparency Workshop
ACER REMIT PILOT PROJECT PHASE I - APPROACH
- Focus on fundamental data based on 2 documents
- Recommendation ACER
- ENTSOG’s proposal for disaggregated fundamental data
- Conf calls ENTSOG/Fluxys/GTS/ACER to discuss “what” will be provided for the purpose
- f the pilot project
- Agreement for scope of pilot project
- Provisional allocations, Day-ahead and final nominations
- Final contracted position
- Technical and available capacity
- Physical flows
- Focus on IPs, LNG terminals, Storage and production points
- Supply points aggregated per shipper for Industry
- Data of december 2012
- In kWh
- Requests to Edigas-experts of GTS and Fluxys
- Design of a set of Market monitoring messages which can be used for market
monitoring by any regulator
20141211 – ENTSOG Transparency Workshop
13
CONTEXT REMIT PILOT PROJECT
2012 ACER
Commission
Remit’s entry into force
2013 2011
Redaction of Implementing Acts
2014
Comitology meetings
Recommendation to Commission on Remit Records of Transactions
2015 2016 2017
Implementing Acts (comitology) Inside information Prohibitions of insider dealing and market manipulation apply for market participants Obligation to publish inside information applies for market participants Transactional data Fundamental data
Voted on 3rd of October
Expected beginning 2015
Remit Pilot Project Phase I Phase II
Purpose Phase II
- To collect as much data as possible
- To define the scope of the first production release of ARIS (e.g. formats, data to be collected,
interfaces supported)
- To provide a basic data sharing solution for NRAs
- To provide a plan for ARIS go-live
- To get estimates on key system requirements (e.g. number of users, number of transactions)
- To define validation procedures and controls
Publication of User Manual Implementing Acts published (entry into force after 20 days)
20141211 – ENTSOG Transparency Workshop
REMIT PILOT PARTICIPANTS PHASE II
14
Participant names Roles ENTSO-E Association electricity TSOs (including up to 5 TSO members), candidate-member, pending NDA process Fluxys Belgium Gas TSO, focus at fundamental data Plinovodi Gas TSO, focus at fundamental data Trayport potential RRM Efetnet potential RRM EEX Energy exchange, focus on transactional and fundamental data Epex Spot Energy exchange APX Energy exchange NPS Energy exchange OMIE Energy exchange Opcom Energy exchange HUPX Zrt. Energy exchange, candidate-member, pending NDA process POLPX Energy exchange, candidate-member, pending NDA process ICE Endex/ICE Trade Vault Europe Limited Energy exchange; reporting derivatives as Trade repository; candidate-member, pending NDA process Regis-TR Trade repository, member LSE - UnaVista Trade repository, candidate-member, pending NDA process DTCC Trade repository, observer ENTSO-G Association gas TSOs, observer
20141211 – ENTSOG Transparency Workshop
ACER REMIT PILOT PROJECT PHASE II - APPROACH
- Discussion within ENTSOG on data fields to be provided for
- Transportation contracts & auction results
- Day-ahead nominations, final nominations & provisional allocations
- Workshop (28/1/2014 & 5/2/2014) with ACER to agree on required data fields (to be
included in the implementing acts) for
- Transactional data: Transportation contracts
- Fundamental data: Transparency information &Day-ahead nominations, final nominations & provisional
allocations
- Draft XSD-schemes provided to ACER (to be finalised end of 2014)
- Transparency information Edigas message under development for providing data of Transparency
platform provided by ENTSOG to ACER
- Day-ahead nominations, final nominations & provisional allocations Easeegas redesigned the initial xsd
to match the agreed data fields
- Transportation contracts & auction rounds almost finalised the Edigas message
20141211 – ENTSOG Transparency Workshop
FLUXYS BELGIUM’S EXPERIENCE IN REMIT PILOT PROJECT
- Participation with real data was helpfull in identifying where the Edigas-
messages still needed changes to cover concerns of TSOs within ENTSOG
- Main concern remaining: offered interfaces for data collection do not include
AS2/AS4, which are part of the Network code interoperability
- Very constructive cooperation with Market Monitoring Team of ACER
− Open for suggestions/arguments why certain information was better for market monitoring than others (eg. Allocations instead of confirmations) − Impression that Cooperation and feedback from market participants was really appreciated by ACER
SPECIAL THANKS TO EASEEGAS FOR MAKING XML COMPREHENSIVE FOR ENTSOG AND ACER
17
20141211 – ENTSOG Transparency Workshop
18
THANK YOU FOR YOUR ATTENTION!
20140522 – End User’s meeting