Feedback + feed-forward plans Philip Burrows John Adams Institute - - PowerPoint PPT Presentation

feedback feed forward plans
SMART_READER_LITE
LIVE PREVIEW

Feedback + feed-forward plans Philip Burrows John Adams Institute - - PowerPoint PPT Presentation

Feedback + feed-forward plans Philip Burrows John Adams Institute Oxford University Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 1 Outline The UK


slide-1
SLIDE 1

Feedback + feed-forward plans

Philip Burrows

John Adams Institute Oxford University

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 1

slide-2
SLIDE 2

Outline

  • The UK team
  • Main-beam IP feedback
  • Drive-beam phase stability feed-forward
  • Summary

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 2

slide-3
SLIDE 3

Feedback On Nanosecond Timescales

Beam-based FB/FF R&D for future Linear Colliders

Philip Burrows Glenn Christian Javier Resta Lopez Colin Perry Graduate students: Ben Constance Robert Apsimon Douglas Bett Alexander Gerbershagen Michael Davis Neven Blaskovic

Valencia, CERN, DESY, KEK, SLAC

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 3

slide-4
SLIDE 4

IP intra-train feedback system - concept

Last line of defence against relative beam misalignment Measure vertical position of outgoing beam and hence beam-beam kick angle Use fast amplifier and kicker to correct vertical position of beam incoming to IR

FONT – Feedback On Nanosecond Timescales

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 4

slide-5
SLIDE 5

Philip Burrows ALCPG11, Eugene 21/03/11 5

CLIC IP FB system

  • Prototype IP FB hardware has been developed since 2000
slide-6
SLIDE 6

FONT2 results – NLCTA (2001)

Feedback on Beam flattener on Beam starting positions Delay loop on

beam start beam end

1 2 3 4

slide-7
SLIDE 7

Philip Burrows ALCPG11, Eugene 21/03/11 7

CLIC IP FB system

  • Prototype IP FB hardware has been developed since 2000
  • CLIC IP FB luminosity simulations (EuroTeV, EUCARD)
  • For past 18 months have been working with MDI team

(Lau Gatignon et al) on realisation of an IP intra-train FB system engineered for CLIC

  • Approved as baseline at CTC - February 2010
  • Interactions on mechanical integration with Alain Herve

et al February – June 2010

  • Agreed on baseline conceptual engineering design

– July 2010

  • Documented in draft sections for CDR – October 2010
  • Ready to provide any modifications to CDR text
slide-8
SLIDE 8

Philip Burrows ALCPG11, Eugene 21/03/11 8

CLIC Final Doublet region

Elsner

slide-9
SLIDE 9

Philip Burrows ALCPG11, Eugene 21/03/11 9

Technical issues for TDR phase

  • Engineering of real hardware optimised for tight spatial

environment: BPM, kicker, cables …

  • Large (and spatially-varying) B-field  operation of

ferrite components in kicker amplifier?!

  • Further studies of radiation environment for FB system:

was studied for ILC, so far preliminary for CLIC; where to put electronics? need to be rad hard? shielded?

  • EM interference:

beam  FB electronics kicker  detector

slide-10
SLIDE 10

Philip Burrows ALCPG11, Eugene 21/03/11 10

Draft work programme

  • Simulation, design and prototyping of IP feedback

system for luminosity stabilisation and optimisation

  • Integration of components within Machine Detector

Interface (MDI) design

  • Completion of the ATF2 prototype systems as part of the

ATF2 collaboration goals of 37nm beam size and nanometer-level beam stabilisation

  • Bench testing of relevant component prototypes, and

exploration of the possibility of beam tests at CTF3

  • Provision of feedback system parameters for modeling

the integrated performance of feedback and feed-forward systems in the global CLIC design

slide-11
SLIDE 11

FONT5 location

slide-12
SLIDE 12

FONT5 layout

QD10X QF11X QD12X QD14X QF13X QF15X K1 K2 P2 P3 P1 To dump FB board DAQ

P2  K1 (‘position’) P3  K2 (‘angle’) P3  K1

slide-13
SLIDE 13

FONT5 beamline hardware

3 new BPMs and 2 new kickers installed in new ATF2 extraction line February 2009; BPM movers installed 2010

slide-14
SLIDE 14

14

Kicker BPM Digital feedback Analogue BPM processor Drive amplifier

e-

Each FONT5 system loop

300ns train of bunches separated by 150ns

slide-15
SLIDE 15

Kicker BPM 1 Analogue BPM processor BPM 2 BPM 3

e-

FONT3 ‘CLIC’ prototype at KEK/ATF

(2004-5)

56ns train of bunches separated by 2.8ns FB loop closed with electronics latency 13ns

slide-16
SLIDE 16

P2  K1 loop jitter reduction

Bunch 1 Bunch 2 Bunch 3 13 um  5 um  3 um

slide-17
SLIDE 17

P2  K1 loop jitter reduction

Bunch 1 Bunch 2 2.1 um  0.4 um Factor of 5 jitter reduction

slide-18
SLIDE 18

18

CLIC drive beam phase FF system

  • For past 20 months have been working with

Daniel Schulte, Frank Stulle et al on concept for a drive-beam phase stability FF system

  • Meetings to map out requirements for amplifier

system needed to provide phase correction – August 2009 – August 2010

  • Preliminary design presented – October 2010
  • Documented in draft sections for CDR –

November 2010

  • Ready to provide any modifications to CDR text
slide-19
SLIDE 19

Reminder of phase feed-forward concept

slide-20
SLIDE 20

Requirements & Assumptions - 1

Based on discussion in August 2009, we assumed: Speed: 10ns

  • we shared the bandwidth limitation equally between kicker and amplifier
  • kicker active length is limited to 1.1m
  • split amplifier bandwidth equally between amplifier modules and

combining system

  • each needs a 70MHz bandwidth

Kickers: stripline kickers, 20mm clear aperture, 1m long

  • ~120 ohm impedance, balanced
  • each connected to amplifier with pair of coaxial cables
  • fit maximum possible total length of kickers for minimum total power

required

  • this means 4 at each bend (3, slightly longer, might be better)
slide-21
SLIDE 21

Requirements & Assumptions - 2

Deflection: +/-720μrad at each bend

  • divided over 4 kickers = +/-180μrad at each

Amplifier architecture: modular, MOSFET

  • standard solution for fast, high-power amplifiers
  • output from many low power modules have to be combined
  • output voltage has to be stepped-up to provide the kV

needed by the kicker

  • the very low duty factor required (0.002%) is very unusual
  • it allows extremely high power densities and (relatively) low

cost

  • note: MOSFETs have almost entirely superceded bipolar

transistors in this role

slide-22
SLIDE 22

A Preliminary System Concept 1

  • 4 kickers at each bend
  • 250kW peak power amplifier to each kicker
  • 256 amplifier modules in each amplifier
  • 1.2kW output each amplifier module (1kW after

losses in combining etc)

dipole magnet 1m kicker 250kW amp

8m 5m 8m

NOT TO SCALE

slide-23
SLIDE 23

A Preliminary System Concept 2

  • amplifier size: 60 x 60 x 30cm (=100 litres) min (double that

is more comfortable)

  • amplifier cost: £75K per 250kW amplifier (£300 per kW

delivered to kicker) *** This is all very very approximate ***

  • it makes no allowance for technological progress
  • no single dominant cost, so estimates very rough until

details worked out

  • very dependent on high-volume costs: we have no sound

basis for these

  • 16 amplifiers & kickers / drive beam, 768 amplifiers total,

200MW total peak power

  • SYSTEM COST: £60M (perhaps +/-£30M)
slide-24
SLIDE 24

Modified Design (Feb 2010)

  • required kick angle at each bend was reduced to +/-375 μrad
  • this would have reduced power per kicker to 66kW peak
  • much more reasonable than the previous 250kW
  • but energy spread of beam & dispersion of chicane increased kicker

aperture

  • 0.5% rms energy spread, 1m dispersion
  • adds 5mm rms spread to beam width in middle section
  • to accept up to 4σ in energy, extra 40mm aperture needed
  • allowing for beam deflection and a finite beam size, need 50mm

aperture

  • brings power back up to 410kW peak
  • allowing any sort of margin brings this to 600kW
  • eg for a slightly higher energy spread than assumed

Later it was indicated that full kick would not be essential at full bandwidth - this may prove a useful dispensation

slide-25
SLIDE 25

Amplifier Modules

Module power is a matter of cost and size

  • sweet spot looks today to be 1 to 2kW

peak for 100MHz module bandwidth

  • we are forced to low voltage, low

impedance operation, and transforming the output  2kW peak output 10ns amplifier module  typical fast, high voltage MOSFETs (DE150-501N)

slide-26
SLIDE 26

Engineering validation for CLIC

amplifier output stage:

  • can we actually get the predicted performance?

combining system:

  • can we do this reliably?
  • can we do it at the final power levels needed?
  • can we get adequate frequency response?

transformers and associated ferrites:

  • will they work well enough?
  • what are the detailed properties of the ferrites?
  • how big and how expensive will they end up?

size and cost:

  • push an amplifier module to a more-or-less finished design
  • that would set an upper bound on size and cost
  • amplifier module will dominate system cost

system concepts:

  • functional test of a small-scale system would be an appropriate next stage
  • eg: 16 amplifier modules and one combining stage, driving a kicker
slide-27
SLIDE 27

27

Timescale

This is a serious project for 1 FTE fully-dedicated engineer! Basic feasibility study  conceptual design 2-3 years Build + test prototype unit 1-2 years

slide-28
SLIDE 28

28

Prototype tests at CTF3?

Amplifier power multiplier

  • Beam energy: 120-150 MeV (10X less)

1/100

  • Kick angle ~ 1 mrad (3X more)

10

  • Kicker gap: 40mm (similar)

1

  • Kicker length: 375mm (3X less)

3

  • 2 kickers (2X less)

2  similar power per amplifier as CLIC (?) Similar bandwidth, latency and pulse duration (?)

slide-29
SLIDE 29

29

Discussion

  • Piotr Skowronski suggested a 4kV pulse is

required to provide a 1mrad deflection via the kicker being designed by Fabio Marcellini

  • This looks like a 320kW amplifier (consistent

with the previous estimate)

  • Equivalent to 1 of 768 amplifiers needed for CLIC
  • Can CTF3 requirements be relaxed?
  • eg. 0.3mrad  10X less power, i.e. 30kW
  • Commercial amplifiers:

Amplifier Research: 25kW = $800k (!)

slide-30
SLIDE 30

Extra material follows

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 30

slide-31
SLIDE 31

CLIC-relevant: all-analogue systems

  • NLCTA (SLAC): 65 MeV beam, 170ns train, 87ps bunch spacing

FONT1 (2001-2): First demonstration of closed-loop FB: latency 67ns 10/1 beam position correction FONT2 (2003-4): Improved demonstration of FB: latency 54ns real time charge normalisation with logarithmic amplifiers beam flattener to straighten train profile solid-state amplifier

  • ATF (KEK): 1.3 GeV beam, 56ns train, 2.8ns bunch spacing

FONT3 (2004-5): Ultra-fast demonstration of FB: latency 23 ns 3 stripline BPMs high-power solid-state amplifier

Brief prototype history: CLIC

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 31

slide-32
SLIDE 32

Kicker BPM 1 Analogu e feedback Analogue BPM processor Drive amplifier BPM 2 BPM 3

e-

Generic prototype layout: CLIC

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 32

slide-33
SLIDE 33

FONT2 beamline installation at SLAC NLCTA

(65 MeV 170ns-long train @ 87ns spacing)

Dipole and kickers BPMs

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 33

slide-34
SLIDE 34

FONT: kicker driver amplifiers

FONT1 3-stage tube amplifier FONT3 PCB amplifer + FB Same drive power as needed for CLIC

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 34

slide-35
SLIDE 35

FONT2 results

Feedback on Beam flattener on Beam starting positions Delay loop on

beam start beam end

1 2 3 4

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 35

slide-36
SLIDE 36

FONT3: latency budget

  • Time of flight kicker – BPM:

4ns

  • Signal return time BPM – kicker: 6ns

Irreducible latency: 10ns

  • BPM processor: 5ns
  • Amplifier + FB: 5ns

Electronics latency: 10ns

  • Total latency budget: 20ns

Allows 56/20 = 2.8 periods during bunchtrain

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 36

slide-37
SLIDE 37

FONT3: BPM processor + amplifier/feedback installation in ATF beamline

BPM processor board Amplifier/FB board FEATHER kicker

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 37

slide-38
SLIDE 38

FONT3: Beamline Installation

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 38

slide-39
SLIDE 39

Fast analogue signal processors

2005 2007 2006

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 39

slide-40
SLIDE 40

FONT3: Results (June 3 2005):

Delay-loop feedback w. latency 23 ns

56ns bunchtrain FB on FB + delay loop on 23ns 200um

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 40

slide-41
SLIDE 41

CLIC prototype: Summary

67 ns 54 ns 23 ns

Basic principle demonstrated. More work needed to optimise Design + system performance.

Philip Burrows UK-CLIC kickoff meeting, CERN 13/4/11 41