12/15/2017 Greater Beloit Community & Economic Development Update December 13, 2017 GBEDC Annual Investors Meeting Featured Economic Development Project 2 1 12/15/2017 NEW Operations Center 525 Third Street, Suite 300 | IronWorks


  1. 12/15/2017 Greater Beloit Community & Economic Development Update December 13, 2017 GBEDC Annual Investors Meeting Featured Economic Development Project 2 1

  2. 12/15/2017 NEW Operations Center 525 Third Street, Suite 300 | IronWorks Campus Summer 2018 22,000 sq/ft  90-95 employees  $4.5 million  City Center/Redevelopment Activity 2

  3. 12/15/2017 Hotel Goodwin  419 Pleasant Street  34 Room Boutique Hotel  Velvet Buffalo Café  Rooftop Meeting Space  35,000 SF Renovation  $5.2 Million Project  Summer 2018 - Completion 5 Vision Beloit Office Renovation - 10 year lease extension 6 3

  4. 12/15/2017 The Power of the Powerhouse Beloit College’s New Campus Activity Center • Planning and fundraising phases complete • Official demo/building phase began June 9 th • $38 Million Dollar Project • Complete by 2019 Continued Redevelopment of the Ironworks  Stateline Family YMCA - Open  First National Bank & Trust - Operations Center Expansion  Golf Lab – Open  CareerTek – Open  Planned Irontek Expansion – 8,000 SF  Several Pending Project Announcements  Received Real Estate Redevelopment Award from WEDA 4

  5. 12/15/2017 Ironworks Pedestrian Bridge and Ken Hendricks Plaza  Span between Ironworks Campus and Ironworks Hotel/Heritage View  HCP designed, built and funded $1.2M Project  HCP will dedicate the structure to the City of Beloit 228’ Long Single Warren Truss Span 10 5

  6. 12/15/2017 CELEB (Center for Entrepreneurship in Liberal Education Beloit)  Complete renovation/modernization  Houston Building 437 East Grand  Hulburt Building 439 East Grand  Roof Replacement/New skylights  Façade renovations including window replacements  Renovation of 6,000 SF into a new maker space (innovation design and prototyping)  Expansion of Gallery ABBA  High-tech pitch space – think “Shark Tank”  New elevator State Collection Services  Relocation and expansion to Eclipse Center  42,000 SF in-bound and out-bound call center  Adding 250 new positions over next 3 years (500+/- total)  $1.9M Investment 6

  7. 12/15/2017 Industrial Development Pratt Industries  Off-site expansion  43,000 SF  4732 Prairie Hill Road – South Beloit  Warehousing for material 14 7

  8. 12/15/2017 Riverside Energy Center Alliant Energy proposed natural gas-fueled generating station- Town of Beloit Riverside Energy Center  700 Megawatt  $750 Million investment  200-300 Construction jobs over 2 years  Additional long-term operational positions  Steel erection underway  Fully operational early 2019 or 2020 HENDRICKS COMMERCIAL PROPERTIES SPEC BUILDING PROJECT PHASE II (State Line Industrial Park) 8

  9. 12/15/2017  PHASE I (Leased)  Initial 105,000 SF building - Fully Operational  PHASE II (Adjacent to Willowbrook Road)  105,000 SF building construction to begin Spring 2018  $6 million capital investment  PHASE III and Beyond  Addition of up to 210,000 SF of building space  $12 million in additional private capital investment STAPLES ORDER FULLFILLMENT CENTER OFF-SITE EXPANSION  Leasing 142,000 square feet at One Reynolds Drive (former Alcoa Building)  Expansion of warehouse/distribution capacity- (large office furniture items)  Long-term lease  8 Jobs  One Reynolds Drive nearly 100% occupied 9

  10. 12/15/2017 TRU ASEPTICS INGREDIENTS  New start-up food processing company Purchased former ADM/Wild Aseptics Building at 2924 Wyetta Drive  Will produce aseptic juices and ingredients  $9.4 million dollar project  Create 40+ new jobs  GBEDC provided a $100,000 loan to support the project Westran Thermal Processing  483 Gardner Street- South Beloit  Produces custom ovens for thermo processing applications  37 employees 20 10

  11. 12/15/2017 COMMERCIAL/RETAIL ACTIVITY G5 Brewing Company • Craft micro brewery-restaurant/bar/beer garden • Employ 50-70 full and part-time workers • 9,750 square foot facility • Closed on Gateway site on March 3 rd • Construction underway • Spring opening 22 11

  12. 12/15/2017 KDN Hospitality • Proposed Holiday Inn Express • 6 story hotel/84K SF • 124 rooms • 3022 Ford Street (former Wickes Lumber site) • Outlot Development Opportunities • Spring Construction Beloit Hotel Group LLC  Hilton Home 2 (Extended Stay Hotel)  102 Rooms/64K SF  Adjacent to the Hampton Inn (Cranston/Milwaukee Road)  Outlot Development Opportunities  Under construction 24 12

  13. 12/15/2017 Milwaukee Corridor Retail 2787 Milwaukee Rd. • Dunkin Donuts • Firehouse Subs Beloit Wal-Mart Supercenter  Complete interior/exterior renovation  $700,000+ 13

  14. 12/15/2017 Residential Development Willowick Assisted Living Elderly Care Facility • Assisted Living • 1971 Cranston Road • 13,750 SF • $2M Investment • 26 Beds • Construction Complete 14

  15. 12/15/2017 Single Family Eagles Ridge Subdivision (Gateway) • Building permits for new homes (and sales) increasing since great recession • Raven Court Complete – 6 Lots • New home values range from $154,000 to $206,000 • Construction on the Phase III (22 Lots) expected to begin spring 2018 Hawk’s Ridge Apartments  1 new building  58 units  $11.4M Assessed Value  Construction underway 15

  16. 12/15/2017 Kadlec Condos  4 Building  18 Units (Multi-Family)  28,500 SF  Under Construction 31 Major Infrastructure Projects 16

  17. 12/15/2017 Town Hall Substati tation • Rock County Cooperative Infrastructure Upgrade • Colley Road Town Hall intersection • 10 MVA Capacity • $2,000,000 Investment • Site work complete • Energized by end of year • Station will support expansion of Gateway Business Park Town Hall Road Reconstr truc ucti tion • Gateway Blvd (N) to UP Rail Road (S) • Complete Reconstruction • Curb/Gutter • Surface • Lighting • Construction start Spring 2018 17

  18. 12/15/2017 I-39/90 Expansion  Funded and under construction! (Work through December restart Spring)  Complete 2022? 35 Strategic Initiatives 18

  19. 12/15/2017 Retail Leakage Analysis - Complete Nature at the Confluence • Dedicated June 15th • GBEDC supported through the 2013 Connections Plan 19

  20. 12/15/2017 Beloit Casino Project  Project back on track  2 lobbying trips to Washington  Anticipate publication in the Federal Register first quarter - 2018  Public hearing second quarter - 2018 39 BMHS Master Plan- Phase I Welcome Center Approved • $5.5 Million Dollar Project • Construction scheduled to be completed by 12/1/18 40 20

  21. 12/15/2017 Rock County Entrepreneurial Business Development Program 42 21

  22. 12/15/2017 Metrics 43 Workforce Development 22

  23. 12/15/2017 Community Concierge Program Provides a link between employers looking to hire professionals and prospects looking for employment and a community to live. Customized services include: • Community Tours • Neighborhood and Home previews • School Tours • Community Orientations • Meet & Greets Funded into 2018 45 2017 Data & Statistics gathered by Maggie Littlefield 46 23

  24. 12/15/2017 Anaerobic Digester Project Feasibility Study Transform bio-waste into bio-gas 47 Marketing Activity 48 24

  25. 12/15/2017 Marketing Print Campaign targeting Chicago Market continues…  Chicago Industrial Properties  Stateline Business Journal 49 Replacement and installation of new Gateway Real Estate Marketing Signs Cost shared between City (TID#10) and GBEDC 50 25

  26. 12/15/2017 Earned Media Badger Institute Magazine MSNBC Internet Video Clip 51 GBEDC Programming Updates 26

  27. 12/15/2017 RLF Update • Loan Portfolio Update • 3 loans active • $128,393 lent out • Funds Available • $67,530.84 Investors Update  Paid Investors YTD: 74  New Investors YTD: 3  Budgeted Income: $70,000  Income YTD: $74,446.43 27

  28. 12/15/2017 Business Retention and Expansion Program 279 Interviews in Rock County conducted to date Economic Indicators 28

  29. 12/15/2017 57 Unemployment for the City of Beloit Month/Year Rate Rank October 2016 4.9% 3 November 2016 4.6% 5 December 2016 4.4% 6 January 2017 5.6% 31 February 2017 6.2% 31 March 2017 5.7% 32 April 2017 4.8% 32 May 2017 4.7% 32 June 2017 5.2% 31 July 2017 4.6% 30 August 2017 5.1% 30 September 2017 3.9% 29 October 2017 3.6% 29 *Source: Wisconsin Department of Workforce Development, Bureau of Workforce Training – Labor Market Information Section 29

  30. 12/15/2017 Economic Development Activity Summary of Current Economic Development Activity New Number of Jobs Square Feet Value Total 332 361,899 $894,613,400 Summary of Economic Development Activity Since 1999 New Number of Jobs Square Feet Value Total 3,921 4,701,303 $1,575,641,595 Questions/Comments? Thank you! http://www.msnbc.com/your- business/watch/beloit-wi-transforms-its- main-street-1093081155967 30

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend