Facilities Update (as required by Policy 4:150 Facility Management - - PowerPoint PPT Presentation
Facilities Update (as required by Policy 4:150 Facility Management - - PowerPoint PPT Presentation
Facilities Update (as required by Policy 4:150 Facility Management and Building Programs) March 19, 2018 Presentation Overview Our Buildings Another Year Older Review of the Operations & Maintenance Budget FY18 Major
Presentation Overview
2
- Our Buildings – Another Year Older
- Review of the Operations & Maintenance Budget
- FY18 Major Projects
- FY19 Bidding/Construction Timeline
- Facility Issues
- Deferred Project Cost Estimates
- Roofing
- Elementary Air Conditioning Update
- Energy Management Initiatives
- Next Steps
Another Year Older
3
Review of Operations & Maintenance budget $28,071,105
4
Salary & Benefits, $832,172 , 3% Purchased Services, $14,376,658 , 51% Supplies & Materials, $6,779,352 , 24% Capital Outlay, $6,073,858 , 22% Other Objects, $9,065 , 0%
Unplanned Expenses
5
- Fischer wall
settlement issue.
- WVHS pool sump
rerouting.
- CEC server room
HVAC failure.
Spending Per Student IPSD vs. Benchmark Districts
6
$1,864 $1,232 $1,210
$1,131
$1,082 $939 $805 Average is $1,262
Expenses - Purchased Services
7
$- $100,000 $200,000 $300,000 $400,000 $500,000 $600,000 $700,000 $800,000 $900,000 Kitchen Equipt. Building Electrical Fire Protection HVAC Plumbing Grounds Security Water/ Sewer Sanitation Services Aramark Overtime FY15 FY16 FY17
Expenses - Supplies & Materials
8
$- $500,000 $1,000,000 $1,500,000 $2,000,000 $2,500,000 $3,000,000 $3,500,000 $4,000,000 Maintenance Grounds Swimming Natural Gas Electric Telecom FY15 FY16 FY17
Historical view of our Capital Improvement Budget
9
$4,213,474 $3,970,166 $2,631,709 $1,541,591 $2,267,588 $2,480,888 $5,626,922 $3,500,000 $6,936,692 $4,073,860 $6,073,858 $8,483,711
$0 $1,000,000 $2,000,000 $3,000,000 $4,000,000 $5,000,000 $6,000,000 $7,000,000 $8,000,000 $9,000,000 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 EMG Yearly Ave.
Aesthetics (replace as needed) Asphalt/Concrete: HVAC Vinyl Tile Replacement @ WVHS Concrete repairs where needed %Asphalt projects @ Granger, NVHS and NV-Birkett #Asphalt projects replace where needed %Phase III – Elementary A.C. Project *Phase IV – Elementary A.C. Project Boiler Repair & Installation @ NVHS Building Envelope Site Projects Security Audit Recommendations %Masonry Restoration @ Cowlishaw McCarty, Welch, Fischer, Scullen, NVHS #Masonry Restoration @ Georgetown, Steck, Fischer #Track Repair @ MVHS & WVHS *Installation of cabling and security cameras @ NVHS and WVHS. ADA Modification: %Band & Chorus Rooms @ WVHS Flat Roof Replacement #Graham Slope Roof Replacement %Kendall
FY 18 Major Projects # Bidding Phase * In Progress %Began in FY17
10
Music Room Modifications at WVHS
Removal of Existing Concrete Framing and Pouring new steps
11
Asphalt Projects
Removing Existing At Granger New Curbs At NVHS
12
Roof Retrofit at Kendall
Installing Roof Panels Masonry & Roof Prep Work
13
Elementary A.C Project - New Electrical Service at Gombert
14
Projects Documents Available Board Approval Substantial Completion
Phase IV – Elementary A. C. Proactive 8/11/17 9/18/17 8/10/18 Flat Roof Replacement @ Graham Reactive 3/19/18 4/16/18 8/10/18 Masonry Restoration @ 3 Schools Reactive 3/19/18 4/16/18 8/10/18 Hardscape Projects TBD Reactive 4/16/18 5/21/18 8/10/18
FY 19 Bidding/Construction Timeline
15
Deferred Project Cost Estimates
16
- Approximately $8 million estimated for masonry
and roof repairs
- $7 million to complete elementary air
conditioning
- $2 million to replace obsolete heating and
cooling controls
- $2 million to upgrade locks and intercoms
Estimates do not include ALL deferred projects
Roof Expenses
17
$705,200 $592,500 $399,869 $641,200 $786,459 $1,478,800 $424,686 $1,811,868 $137,894 $223,620 $127,911 $102,214 $205,455 $126,867
$0 $200,000 $400,000 $600,000 $800,000 $1,000,000 $1,200,000 $1,400,000 $1,600,000 $1,800,000 $2,000,000 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 EMG YEARLY AVE.
Roof Repairs Roofing Replacement
Elementary Air Conditioning Update
18
- Began installing air conditioning in phases 4 years
ago.
- Funding from delayed state payments and deficit
spending.
- By August 2018 the project will have installed air
conditioning in 67% of our elementary classrooms.
- $7 million needed to complete finish the project
(remaining classrooms & LMC area)
Energy Management Initiatives
- 1st year participation in the EnerNOC Demand Response
Incentive Program. Will receive approximately $45,000 this year. Expected to earn $345,000 over 5 years (Fischer, Granger, MVHS, Still, WVHS)
- ComEd will be performing a free energy audit in all 14
schools within their territory.
19
Next Steps
- Prioritize Capital improvement and other district needs based
- n the following hierarchy:
1. Safety Related Items 2. Approved Curriculum Related needs 3. Necessary Repairs 4. State required Life Safety Projects (building code changes) 5. Aesthetic
- Explore grant and other cost savings opportunities.
20