estate renewal schemes in enfield
play

ESTATE RENEWAL SCHEMES IN ENFIELD UPDATE Striving for excellence - PowerPoint PPT Presentation

ESTATE RENEWAL SCHEMES IN ENFIELD UPDATE Striving for excellence www.enfield.gov.uk LADDERSWOOD Construction commenced 17 th March 2014 - delay caused by completion of section 106 agreement. Pub site will be the first phase


  1. ESTATE RENEWAL SCHEMES IN ENFIELD UPDATE Striving for excellence www.enfield.gov.uk

  2. LADDERSWOOD • Construction commenced 17 th March 2014 - delay caused by completion of section 106 agreement. • Pub site will be the first phase providing 40 new homes. • Tenants and remaining leaseholders in the process of selecting homes on the new scheme. • 10 remaining residents in Curtis House being double decanted into Betspath House to enable early demolition of the tower.

  3. Ladderswood Estate

  4. HIGHMEAD • Scheme ahead of build schedule likely to be completed by March 2015. • As raised at an earlier Scrutiny meeting Developers have agreed to include a satellite receiver dish which will enable residents to receive foreign TV channels. • Community Facility to be managed by Enfield Homes – use of the hall is in the process of being finalised.

  5. Highmead

  6. SMALL SITES • Planning consent achieved for 94 new homes across 7 sites including 37 council owned affordable homes. • Mayors Covenant funding received for £700k to support the scheme. • Delegated member approval to appoint developer March 2014. • Cabinet approved funding structure that will return net cash flow to LBE. • Start on site by late June 2014 with practical completion of all 94 homes by August 2015.

  7. SMALL SITES – Parsonage Lane

  8. NEW AVENUE • HCA Partner Framework used to procure a developer. • Following a number of Direction of Travel meetings 2 developers submitted tenders to develop the scheme. • One of the submissions included 22 properties outside the estate boundary not all owned by the local authority.

  9. NEW AVENUE • Following individual consultations with those affected by the proposal and a wider drop in event to discuss both submissions it was agreed to defer the decision on the developer selection to allow further work on the scheme. • Whilst this decision will delay the project it was felt that design of the new homes and layout of the scheme would improve the overall development.

  10. DUJARDIN MEWS • Durkans appointed as housebuilder in February 2014. • Start on site due June 2014 • Mayors covenant funding of £500k received to support the Leaseholder home ownership options. • Negotiations ongoing with Viridian HA to allow LBE to access the site via their Robbins Hall scheme

  11. Dujardin Mews

  12. ALMA ESTATE • Countryside appointed as developers with Newlon HT as RP partner delivering the Intermediate Housing • Phase 1 decanting ongoing - 29 tenants to be decanted, 25 of these require a double decant to remain on the estate. • Guardian firm, Ad Hoc, appointed to rent the void units in phase 1. • Neighbourhood design panels arranged to work with residents on the design of the new scheme.

  13. ALMA ESTATE • Development agreement agreed between developers and local authority awaiting exchange. • Local lettings plan booklet drafted for the scheme • Phase 2a decanting has now commenced. 32 tenants are now live for bidding.

  14. ALMA ESTATE

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend