Energy Storage and Distributed Energy Resources Phase 3 (ESDER 3) - - PowerPoint PPT Presentation

energy storage and distributed energy resources phase 3
SMART_READER_LITE
LIVE PREVIEW

Energy Storage and Distributed Energy Resources Phase 3 (ESDER 3) - - PowerPoint PPT Presentation

Energy Storage and Distributed Energy Resources Phase 3 (ESDER 3) Straw Proposal Stakeholder Conference Call February 21, 2018 1 p.m. 4 p.m. (Pacific Standard Time) CAISO Public CAISO Public Agenda Time Item Speaker 1:00 - 1:10


slide-1
SLIDE 1

CAISO Public CAISO Public

Energy Storage and Distributed Energy Resources Phase 3 (ESDER 3)

Straw Proposal

Stakeholder Conference Call February 21, 2018 1 p.m. – 4 p.m. (Pacific Standard Time)

slide-2
SLIDE 2

CAISO Public

Agenda

Page 2

Time Item Speaker

1:00 - 1:10 Stakeholder Process and Schedule James Bishara 1:10 - 1:15 Introductions Eric Kim 1:15 - 1:30 Background and Scope 1:30 - 2:00 Proposal for Demand Response 2:00 - 2:30 Proposal for Multiple-Use Applications 2:30 - 3:50 Proposal for Non-Generator Resource 3:50 - 4:00 Next Steps James Bishara

slide-3
SLIDE 3

CAISO Public

STAKEHOLDER PROCESS

slide-4
SLIDE 4

CAISO Public

CAISO Policy Initiative Stakeholder Process

POLICY AND PLAN DEVELOPMENT

Issue Paper

Board

Stakeholder Input

We are here

Straw Proposal Draft Final Proposal

Page 4

slide-5
SLIDE 5

CAISO Public

Background/Scope

slide-6
SLIDE 6

CAISO Public

ESDER’s goal is to lower barriers and enhance the ability

  • f storage and DER to participate in the ISO market
  • ESDER Phase 1 was completed in 2016

– Introduced a new baseline methodology for meter generator output and developed statistical sampling – Improved accuracy of state of charge (SOC) for day- ahead optimization and allowed an option for SOC self- management

  • ESDER Phase 2 was approved by ISO Board in July 2017

– Planned implementation for spring 2017 – New baseline methodologies, changes to net benefits test, and tariff clarification of station power definition

Page 6

slide-7
SLIDE 7

CAISO Public

The CAISO proposes the following scope for ESDER 3

  • New bidding and real-time dispatch options for demand

response (DR)

  • Removal of the single load serving entity (LSE) aggregation

requirement and the need for application of a default load adjustment (DLA)

  • Load shift product for behind the meter (BTM) storage
  • Measurement of behind the meter electric vehicle supply

equipment (EVSE) load curtailment

  • Assessment of multiple-use application (MUA) tariff and

market design changes

  • Develop a process to qualify NGRs for use-limited status
  • Identify policy developed for commitment costs that apply to

NGRs

Page 7

slide-8
SLIDE 8

CAISO Public

DEMAND RESPONSE PROPOSALS

slide-9
SLIDE 9

CAISO Public

New bidding and real-time dispatch options for DR

  • 1. Inform stakeholders of the status of Commitment Cost

and Default Energy Bid Enhancements (CCDEBE) – Allows resources with a 0 MW minimum operating level to reflect minimum load and start-up costs – Clarifies definition of startup costs – Proposal will help market participants clearly define commitment costs and be appropriately valued and

  • ptimized within the residual unit

commitment (RUC) process

Page 9

Other RA DR with RA RUC “stack” today RUC “stack” tomorrow with proposed changes Non-RA Non-RA

slide-10
SLIDE 10

CAISO Public

Illustration of a DR resource with a Pmin of 0 MW committed in Residual Unit Commitment (RUC)

Page 10

2.5 min notification

5-min interval

Minimum Run Time MW 1 2 Start up Time

slide-11
SLIDE 11

CAISO Public

New bidding and real-time dispatch options for DR

  • 2. Introduce three new bidding options

(1) Hourly block – Self-schedules fixed for the hour that is communicated to resource at 52.5 minutes before the flow of energy

  • Resource is a price taker for the full hour

(2) Hourly block with single change – Submits self- schedule for the hour but has the option to change schedule once per hour

  • Binding schedule is communicated 22.5 minutes

prior to flow

  • If economic over remainder of the hour, receives a

binding schedule at FMM price in binding interval, advisory for remaining intervals

Page 11

slide-12
SLIDE 12

CAISO Public

New bidding and real-time dispatch options for DR (cont’d)

(3) 15 minute dispatchable – Bids submitted, committed at FMM price, and communicated 22.5 minutes before flow of energy

  • Eligible for bid cost recovery

Page 12

slide-13
SLIDE 13

CAISO Public

Illustration of a DR resource with a Pmin of 0 MW committed in RUC utilizing the hourly block bidding

  • ption

Page 13

HE 1 HE 3

MW 1 2 Minimum Run Time at Pmin (0 MW) Start up Time

HE 2

52.5 min notification

  • Minimum run time maintained at Pmin
  • Ample notification time prior to real-time dispatch and resource

response

  • Response time held for one or more hours
slide-14
SLIDE 14

CAISO Public

Next steps and requested feedback under proposal

  • The CAISO will consider how the Day Ahead Market

Enhancements initiative and FERC Order 841 might impact details of the proposal

  • Are there other considerations the CAISO needs to

address in this proposal to ensure resources can feasibly respond to dispatches in real-time?

Page 14

slide-15
SLIDE 15

CAISO Public

Removal of the single LSE aggregation requirement and application of the DLA

  • The CAISO proposes to

– Remove the requirement of a PDR or RDRR resource aggregation to be limited to one LSE – Develop a SIBR rule to only accept bids above the Net Benefits Test threshold price for these resources

  • Eliminates need for the default load adjustment

settlement mechanism tied to the resource’s LSE

Page 15

slide-16
SLIDE 16

CAISO Public

Support for removing the application of the DLA

Page 16

0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 20 40 60 80 100 120 140 160 180 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

$ (Thousands) MW

2017 Monthly DLA Impact

Total MWs Allocated Total Costs Allocated

slide-17
SLIDE 17

CAISO Public

Next steps and requested feedback under proposal

  • SIBR rules to be developed in more detail
  • Is there general consensus for the removal of the DLA to

enable multi-LSE aggregations?

Page 17

slide-18
SLIDE 18

CAISO Public

Load shift product for behind the meter storage

  • The load shift product will enhance the PDR model to

allow for BTM storage participation to provide grid services during oversupply conditions

  • Key features

– Load shift is not RA capacity – It is a non-exporting product – Only resources that can be directly metered – Ability to bid a negative cost for energy services – Resource pays full retail rate for all charging energy

Page 18

slide-19
SLIDE 19

CAISO Public

Next steps and requested feedback under proposal

  • Will continue developing product features through a

working group to – Incorporate NGR functionality into the PDR participation model – Evaluate and determine applicability of NBT to demand responding to negative price signals for consumption

  • Are there any CPUC regulations that require updating to

accommodate load shift functionality (i.e. any RA conflicts)?

  • Are there other product features that should be

considered?

Page 19

slide-20
SLIDE 20

CAISO Public

Measurement of behind the meter EVSE load curtailment

  • ESDER 1 implementation included the meter generator
  • utput (MGO) performance measurement

– Recognized a sub-metered storage device’s contribution to a facility’s overall load curtailment during a CAISO dispatch event

  • Received support from a majority of stakeholders to

extend the MGO concept to the sub-metered EVSE – provides an option for direct measurement of EVSE load curtailment, independent of its host customer, in response to a market dispatch

Page 20

slide-21
SLIDE 21

CAISO Public

Next steps and requested feedback under proposal

  • CAISO will establish a working group to develop

proposal details on EVSE – sub-metering requirements – performance measurement

  • Additional proposal details that should be considered

and addressed in the working group?

Page 21

slide-22
SLIDE 22

CAISO Public

MULTIPLE-USE APPLICATIONS PROPOSAL

slide-23
SLIDE 23

CAISO Public

  • The CAISO proposes to perform a comprehensive

review and analysis of what is needed to facilitate the rules and framework established in the MUA decision including – identifying all tariff and current participation model changes that would be needed – actively participating in all 2018 CPUC working group meeting and evaluate recommendations proposed that can be taken up in ESDER 3 or identified as a separate initiative – deliver an assessment report of potential tariff and market changes needed

Page 23

MUA proposal in scope for ESDER 3

slide-24
SLIDE 24

CAISO Public

NON-GENERATOR RESOURCE PROPOSAL

slide-25
SLIDE 25

CAISO Public

CAISO’s positions on the issue of throughput management

  • The CAISO maintains that the current NGR participation

model allows resources to reflect throughput limitations through bidding parameters – Supported from several stakeholders with market experience – Enhancements to the current NGR model are possible given FERC Order 841; under evaluation

  • Powin Energy’s claimed an issue with infeasible automatic

general control (AGC) dispatch – CAISO is in the process of addressing questions with Powin Energy – Internal review has not identified an issue with AGC signaling or NGR modeling

Page 25

slide-26
SLIDE 26

CAISO Public

CAISO’s positions on the issue of state-of-charge management

  • The CAISO will not consider proposals for request for

multi-segment AS bids or multiple bid offers – Stakeholders’ proposals are detailed in the paper – Both suggestions would require a fundamental market design change that would apply to all resources

  • Will need to be addressed through the stakeholder

catalog process

Page 26

slide-27
SLIDE 27

CAISO Public

The CAISO proposes to develop a process to define use-limited status for NGRs

  • Use-limited status will allow for NGRs to submit “use-

limit reached” outage cards

  • The Straw Proposal asks for the following:

– Potential use-limited qualifying factors – Types of documents a resource owner would provide to the CAISO – Commitment to show specific manufacturer contract provisions for cycling limitations

Page 27

slide-28
SLIDE 28

CAISO Public

Next steps and requested feedback under proposal

  • CAISO requests storage owners/operators reach out and

share any problematic market or operational experiences for CAISO evaluation – Will consider if participation model changes are needed based on evaluation and understanding of root causes

  • FERC Ruling on Order 841 (Storage Participation in

ISO/RTOs) – Ruling details are currently under review within the CAISO – Tariff and market design changes to align with ruling will be considered within ESDER 3

Page 28

slide-29
SLIDE 29

CAISO Public

NEXT STEPS

slide-30
SLIDE 30

CAISO Public

Next Steps

Page 30

Milestone Date

Straw Proposal Posted February 15, 2018 Stakeholder call February 21, 2018 Stakeholder comments due March 7, 2018

Written stakeholder comments on the issue paper are due by COB March 7 to InitiativeComments@caiso.com. Materials related to the ESDER Phase 3 initiative are available on the ISO website at http://www.caiso.com/informed/Pages/StakeholderProcesses/EnergyStora ge_DistributedEnergyResources.aspx

slide-31
SLIDE 31

CAISO Public

Stay connected

Page 31

Sign up for the Daily Briefing at www.caiso.com Download ISO Today mobile app @California_ISO

THANK YOU