ELECTRICITY AND OUR FUTURE
INTEGRATED RESOURCE PLAN UPDATE
Public Utilities Committee Meeting December 11, 2019
1
ELECTRICITY AND OUR FUTURE INTEGRATED RESOURCE PLAN UPDATE Public - - PowerPoint PPT Presentation
ELECTRICITY AND OUR FUTURE INTEGRATED RESOURCE PLAN UPDATE Public Utilities Committee Meeting December 11, 2019 1 Agenda Mission Why An IRP TEA IRP Recommendations Public Comments Reliability, Financial & Environmental
1
2
3
Value
Service
Community
4
5
6
7
8
9
10
11
12
13
14
DALLMAN 31 COAL 61 MW 1968 DALLMAN 32 COAL 61 MW 1972 DALLMAN 33 COAL 172 MW 1978 UNIT 4 COAL 207 MW 2009 REYNOLDS FUEL OIL 14 MW 1970 FACTORY FUEL OIL 17 MW 1973 INTERSTATE FUEL OIL & NATURAL GAS 110 MW 1997
15
OR
CWLP Avg. Load = 195 MW
CWLP Load only over 350MW 0.5% of the year
Transmission upgrades will improve ability to import power thus increasing reliability
16
NET INCOME FROM ENERGY SALES NET INCOME FROM CAPACITY SALES TOTAL SALES INCOME FY19 $5,651,107 $2,800,350 $8,451,457 FY18 $7,807,930 $6,835,201 $14,643,131
*Excludes additional capital costs for environmental compliance and major repairs.
17
*Excludes additional capital costs for environmental compliance and major repairs.
18
19
February Dry Fly Ash Engineering (ordinance) April new FGD Waste Stream Treatment Engineering (ordinance) May 2020 deadline to certify retirement of Unit 31, 32 & 33 to
Ponds to October 2028.
November 2020 must cease sending water to Ash Ponds if no extension (to October 2023) granted
2020 2021
September 2021 Dry Fly Ash system constructed and
33 Begin construction of Filter
Press for WWTP, FGD WWTP
sludge handling and landfill leachate collection
316a, 316b and Biomonitoring
studies once new NPDES permit issued 2022-2024 ACE Rule for Heat Rate Improvements Complete construction of new
Lime Ponds.
Exhaust bank of seasonal NOx allowances if all Units running, Initiate purchase of additional allowances.
CCR alternatives analysis and
permitting expected under State rules
2022 2024
& Beyond
Summer 2023 complete construction
PSES rule as proposed October 2023 (if extension granted) complete Dry Bottom Ash system, WWTP sludge handling, FGD WWTP filter press and leachate relocation. Begin Closure of Ash Ponds if extension granted
2023
Future CO2 Limits
CEJA (if adopted) would
require all coal units shuttered by 2030. Complete closure of Ash
Ponds by October 2028 if
retirements option invoked in 2020
Dry Fly Ash by September 2021 Dry Bottom Ash by October 2023 Ash Ponds will stop receiving water by 2023
If retirement dates are set by May 2020, then ash pond closure date is extended to 2028
21
22
Upcoming slides do not include this project cost since rule just revised.
23
24
25
26
27
28
29
30
As of 11/13/19 Cal 20: $2.50 Cal 21: $2.47 Cal 22: $2.48 Cal 23: $2.53 Cal 24: $2.58 Cal 25: $2.62 Cal 26: $2.66 Cal 27: $2.75 Cal 28: $2.84 Cal 29: $2.94 Cal 30: $3.05 Cal 31: $3.16
The 2023-2031 strips hit new all- time lows earlier this week
(priorities, program needs, customer satisfaction)
31
February 2020 - Dry Ash Handling Engineering Ordinance April 2020 - New FGD Waste Stream Treatment Facility Engineering Ordinance
No sooner than Fall of 2021 No later than Fall of 2023
32
33
34