Distributed Generation Customer Perspectives Focus on LV to 33kV - - PDF document

distributed generation customer perspectives focus on lv
SMART_READER_LITE
LIVE PREVIEW

Distributed Generation Customer Perspectives Focus on LV to 33kV - - PDF document

Distributed Generation Customer Perspectives Focus on LV to 33kV Connections sector (PV) James Hoare CEng MIET MEI BRE National Solar Centre - Associate Consultant LHW Partnership LLP - Owner 24 th September 2014 Part of the BRE Trust James


slide-1
SLIDE 1

1

Part of the BRE Trust

James Hoare CEng MIET MEI BRE National Solar Centre - Associate Consultant LHW Partnership LLP - Owner 24th September 2014

Distributed Generation – Customer Perspectives Focus on LV to 33kV Connections sector (PV)

James Hoare CEng MIET MEI - Bio

32 years Engineering in Power System & Renewable Energy Sector In Year 2000

  • big decision to leave HV power sector to join the fledgling PV Industry

(CEGB) (GEC)

(Ardenham Energy founder)

slide-2
SLIDE 2

2 Year 2000 – UK PV Industry

– Total PV Connected Capacity c1MWp – No FIT’s or ROC’s (nor in Germany) – A large project was typically 12kWp – G83 not in existence Largest UK PV programme at the time BP Solar Project Sunflower a 1098 kWp programme covering canopies on 76 UK petrol stations from 1996 to 2002

Year 2014 – UK PV Industry

– Total PV Connected Capacity c5GWp (5000 MWp) – Circa 750,000 DNO grid connected Installations – A large project is now 50-60 MWp – At peak PV output in July is c12.5% of UK weekend early PM national demand

(UK demand data - source gridwatch.templar.co.uk)

slide-3
SLIDE 3

3

slide-4
SLIDE 4

4 1. Quote + 2. Innovation 3. All DNOs Technical Forum Three examples of ✓✓✓✓✓ ✓✓✓✓✓ in Last year

  • Up to 3 options to be considered at a particular location
  • Estimate within 20 working days for each of the options_
  • If you choose to progress for one of the options within 5

working days, your place in the queue Three examples of ✓✓✓✓✓ ✓✓✓✓✓ in Last year

  • 1. Quote + for New Connection Enquiries
slide-5
SLIDE 5

5

  • Western Power Distribution have a strong focus on

innovation in future power systems covering a very broad range from energy storage, fault current limitation , active network management, demand side response, voltage control. Three examples of ✓✓✓✓✓ ✓✓✓✓✓ in Last year

  • 2. Innovation

The ENA facilitate a ¼ ly Technical Forum where DG connection issues are discussed and addressed and includes the sharing

  • f

best practice, a better understanding of technical constraints and the development

  • f agreed solutions

Participants

  • Hosted by ENA
  • Technical Representatives from all 6 DNOs
  • DG Industry Trade Association representation
  • National Grid
  • Industry technical representation

Three examples of ✓✓✓✓✓ ✓✓✓✓✓ in Last year

  • 3. ENA Technical Forum
slide-6
SLIDE 6

6 ENA Technical Forum Meeting minutes are published once approved on ENA web http://www.energynetworks.org - Technical Forum Advice to DG Customers - definitely worth viewing quarterly Located Here ENA Technical Forum – one very good link on ENA website

LV HV EHV Comments

ENW NPG SPEN SSE UKPN WPD

DNO’s requirement and position on some key connection aspects

  • DNO circuit breaker to protect a

customer installation

  • Composite Boards in

Substations

  • Fixed line telephony for SCADA
  • Harmonic Analysis
  • HV Interface Box standards
  • Load Control Devices
  • Tee’d & looped Connections

Full of really key & helpful information for DG Customers

slide-7
SLIDE 7

7 DG Customer Concerns As installed Capacity grows the following areas are increasingly becoming more of a challenge to DG connectivity. Time to Connect In some areas connections not possible till 2020’s – this is a obvious concern of DG Customers Harmonic Compliance A growing issue, with additional cost implications especially for Inverter baser technology Thermal constraints, Fault Level, Voltage Rise All challenges of evolving networks to accommodate DG that was designed and built over 60 years for demand customers. Advice to DG Customers To echo previous presentation - Engage with DNO’s and give them feedback

The surgeries and other initiative's are very good and there is the possibility for communication

  • Recent important Ofgem Consultation on I.C.E. Where

every DNO fed back on 2013/13 DG performance – Each DNO spent time & resource preparing responses for review – yet only 2 Responses from DG Community as a whole

slide-8
SLIDE 8

8 Advice to DG Customers To echo previous presentation - Engage with DNO’s and give them feedback

  • Current ENA Consultation on EREC G97 - Harmonic

Compliance and will affect DG customers– Very important issue, and important for DG customers - almost no response - yet all TA’s communicated details of this consultation to members.

Advice to DG Customers Gain an understanding of the cause & impact of the emerging connection constraint challenges. They may be technical but they are becoming increasingly important and in particular

  • Fault Currents
  • Harmonics

And also the importance of

  • Electrical Safety, Quality and Continuity Regulations (ESQCR)
slide-9
SLIDE 9

9 Feedback for DECC & Ofgem Capacity Hoarding, Sterile Networks & Reinforcement

There is a case example of a 250kW (£250k) Community project that wont progress as the network upgrade costs would be ££ several million as there is 75MW of consented but currently unused DG capacity on same network. , DNOs must enforce milestones for progression, & fairly redistribute relinquished capacity. Released capacity will be hugely helpful to industry as a major DG connection block is coming

Thank You