Discussion with the RCM Working Group 17 April Discussion outline - - PDF document

discussion with the rcm working group
SMART_READER_LITE
LIVE PREVIEW

Discussion with the RCM Working Group 17 April Discussion outline - - PDF document

Discussion with the RCM Working Group 17 April Discussion outline CAUSATION T HE RCM AND OTHER DRIVERS L OAD FORECAST UNCERTAINTY HOW THE RCM INFLUENCES CAPACITY INVESTMENT CHOICES T HE VALUE OF PURE CAPACITY T HE MRCP


slide-1
SLIDE 1

Discussion with the RCM Working Group

17 April

Discussion outline

  • CAUSATION

– THE RCM AND OTHER DRIVERS – LOAD FORECAST UNCERTAINTY

  • HOW THE RCM INFLUENCES CAPACITY INVESTMENT CHOICES

– THE VALUE OF PURE CAPACITY – THE MRCP REVIEW IN PERSPECTIVE

  • FURTHER DISCUSSION

– COMPLEXITY OF FULL MARKET-BASED APPROACH – RCP FORMULA-BASED APPROACH

  • The current RCP formulation and the option of a steeper “slope”

The Lantau Group

The current RCP formulation and the option of a steeper slope

  • The relationship between the RCP and the MRCP
  • Picking values

– Other Related Issues

1

slide-2
SLIDE 2

Trend in excess reserve capacity

14 6% 14.6%

The Lantau Group 2

Many “reasons”, but the RCM is always a factor

Capacity Year Attributed Factor 2008 2009 2010 2011 2012 2013 Total Schedule 7 536 536 Schedule 7 536 536 Displacement tender 256 256 MRET 1 1 90 5 19 116 Government policies 220 220 Market outcomes 331 109 10 112 562 Demand-side resources 47 71 87 181 45 431 Total Capacity Addition 583 587 181 187 518 64 2120 Excess Reserve Capacity 278 527 113 302 495 775

The Lantau Group 3

The specifics are interesting, but the general point that the RCM is a s factor attracting or supporting investment remains

slide-3
SLIDE 3

Demand uncertainty (1 of 2)

The Lantau Group 4

Just SIX “lumpy” loads – represent very significant uncertainty – what commitment should be expected of loads to be commensurate with other resources?

Demand uncertainty is inherent in the WEM (2 of 2)

DOWNWARD REVISIONS UPWARD REVISIONS

The Lantau Group 5

Probably any forecast can be made “better”, but you cannot eliminate fundamental uncertainty in a small, lumpy market – the RCM has to be sufficiently responsive so as not to ADD TO the problem

slide-4
SLIDE 4

A capacity credit value is the value of “pure capacity”

  • Consider the choice between

investing in an incremental MW of a pure peaking resource or an incremental MW from a unit with a

CC Levelized Cost = “Gross CONE” Energy and AS Margins Annual Fuel Savings CC Annual Carrying Cost

incremental MW from a unit with a lower marginal dispatch cost.

  • Both units would provide exactly the

same reliability benefit.

  • In addition, the unit with the lower

dispatch cost could displace higher- cost resources.

  • Accordingly, the unit with the lower

Peaker Levelized Cost = “Gross CONE” AS Margins Shortfall = Net CONE = Capacity Price Savings Capacity Value Peaker Annual Carrying Cost

The Lantau Group

dispatch cost has a second source

  • f value.

6

It is the role of the RCM to produce the “red” portion, which is the same “value” no matter what technology or side of the equation (demand or supply)

Combined Cycle Peaker

Before MRCP methodological and definitional adjustments, and after

40,000 60,000 80,000 100,000 120,000 140,000 160,000 180,000 200,000 RCP RCP (slope = -1) based on 85% OLD MRCP RCP (slope = 1) based on 85% NEW MRCP

23.4% ~9 %

The Lantau Group 7

20,000 0% 3% 5% 8% 10% 13% 15% 18% 20% 23% 25% Percentage of Excess Reserve Capacity RCP (slope = -1) based on 85% NEW MRCP

The MRCP has changed, but the RCP is no more sensitive to market conditions than before, and the lower MRCP has implications for longer-term investment incentives

slide-5
SLIDE 5

Reduced investment in the WEM has already (apparently) begun

50 100 150 200 250 300 350 MW Demand‐side resources Market outcomes

The Lantau Group 8

2008 2009 2010 2011 2012 2013 Capacity Year

This is to be expected, and is good, given the current level of excess reserve capacity…but

Market-based pricing of capacity credits is not simple

  • What is the value horizon (one year, multiple years)?
  • What is the reference point (today, next year, three year’s hence, longer term)?

H bi i th k t (thi k l l f titi i /d i )?

  • How big is the market (thickness, level of competitive sourcing/dynamics)?
  • What is the starting point and how did it get there (transition, fairness, contracting, etc)
  • What is the role of forecasting and forecast uncertainty? (who bears?)
  • What is the level of accepted exposure to non-market risks?
  • The RCM currently bypasses or simplifies most of these, keeping it but imperfect

The Lantau Group 9

Changing the formula of the RCP can make a significant “pro-market” improvement, even if it does not address every imperfection immediately

slide-6
SLIDE 6

Current approach, varying slope

Steeper – more responsive to

40,000 60,000 80,000 100,000 120,000 140,000 160,000 180,000 200,000 RCP RCP (slope = -1) based on 85% OLD MRCP RCP (slope = -1) based on 85% NEW MRCP

p p market conditions Could be steeper still, as current market value of a single year credit is very very low The steeper and lower the Credit price can go, the more

  • ne has to worry about whether

the credit value can go “higher”

  • n the upside to create correct

The Lantau Group 10

20,000 0% 3% 5% 8% 10% 13% 15% 18% 20% 23% 25% Percentage of Excess Reserve Capacity RCP (slope = -3.25) based on 85% NEW MRCP

  • n the upside to create correct

expected values in the longer term

Capped by MRCP

Steeper – more responsive to

40,000 60,000 80,000 100,000 120,000 140,000 160,000 180,000 200,000 RCP RCP (slope = -1) based on 85% OLD MRCP RCP (slope = -1) based on 85% NEW MRCP

p p market conditions No 85% cap But still limited to MRCP What is the MRCP? It is the expected cost of pure peaking capacity provided by a 160MW OCGT

The Lantau Group 11

20,000 0% 3% 5% 8% 10% 13% 15% 18% 20% 23% 25% Percentage of Excess Reserve Capacity RCP (slope = -3.25) based on 100% NEW MRCP

It is not the estimated “maximum” cost of peaking capacity in economics, but a price cap in the WEM

slide-7
SLIDE 7

Capped by 110% of MRCP

Steeper – more responsive to

40,000 60,000 80,000 100,000 120,000 140,000 160,000 180,000 200,000 RCP RCP (slope = -1) based on 85% OLD MRCP RCP (slope = -1) based on 85% NEW MRCP

p p market conditions 110% of MRCP – is that enough? The higher the cap above MRCP, the more incentive to bilaterally contract around this exposure. An “uncapped” and “unbottomed” RCP would drive stakeholders into more contracting to manage risk

The Lantau Group 12

20,000 0% 3% 5% 8% 10% 13% 15% 18% 20% 23% 25% Percentage of Excess Reserve Capacity RCP (slope = -3.25) based on 110% NEW MRCP

more contracting to manage risk This principle is key to the bilateral contracting incentive in modern capacity markets

Comment

  • Currently, the RCP is adjusted downward in proportion to the amount of excess reserve capacity

that exists.

  • A straightforward change would focus on sharpening the administrative price adjustment

mechanism to be more responsive to the amount of excess reserve capacity in the WEM.

  • An alternative of “spigot control” would go against market-based provision of capacity by new

investors, though it would help protect existing generation investors from further potential reductions in CC value

  • Consequently, we favour a price-based adjustment either driven by more use of auctions

(complex implementation and more volatile value impacts), or a sharpened RCP price adjustment formula Th i k t b id d i i hi h th dj t t t th RCP ffi i tl d

The Lantau Group

  • The risk to be avoided is one in which the adjustments to the RCP are so sufficiently and

consistently downward without any chance of an offsetting upward adjustment that the expected value of a Capacity Credit over the life of a capacity investment is not sufficient to support that investment commercially.

13