Direct Testimony Presentation PUBLIC SESSION PREPARED BY: DAYMARK - - PowerPoint PPT Presentation

direct testimony presentation
SMART_READER_LITE
LIVE PREVIEW

Direct Testimony Presentation PUBLIC SESSION PREPARED BY: DAYMARK - - PowerPoint PPT Presentation

Direct Testimony Presentation PUBLIC SESSION PREPARED BY: DAYMARK ENERGY ADVISORS PREPARED FOR: MANITOBA PUBLIC UTILITIES BOARD DATE: JANUARY 2018 Presentation Objectives and Agenda Presentation Objectives Agenda 1. Understanding of


slide-1
SLIDE 1

PREPARED BY: PREPARED FOR: DATE:

Direct Testimony Presentation

PUBLIC SESSION

DAYMARK ENERGY ADVISORS MANITOBA PUBLIC UTILITIES BOARD JANUARY 2018

slide-2
SLIDE 2

Agenda

1.

Daymark Scope of Work

2.

Key Concepts

3.

Project History and Status

4.

2016 Economic Analysis

5.

2017 Updated Analysis

6.

Key Findings

Presentation Objectives and Agenda

2

Presentation Objectives

  • Understanding of the

general transaction and status

  • Understanding of general

evaluation methodology

  • Understanding of current

economics

slide-3
SLIDE 3
  • 1. Daymark Scope of Work

3

1 2 3 4 5 6

slide-4
SLIDE 4

“Review and assess the economic justification for the SaskPower 100 MW power sale and Manitoba- Saskatchewan Transmission Project and provide an

  • pinion on the merits of this project and whether it

is in Manitoba Hydro’s and ratepayers’ interests to proceed.”

Daymark Scope of Work

Our Charge

4

1 2 3 4 5 6

slide-5
SLIDE 5

Daymark Approach

  • Reviewed MH transmission documents (CSI*)
  • Reviewed MH economic evaluation documents and

workpapers (CSI)

  • Performed additional (limited) analysis

Daymark Materials Relevant to this Presentation

  • Produced public and CSI reports (already on record)
  • Responded to Information Requests (IR) related to reports

(already on record) Daymark Scope of Work

Our Approach and Relevant Materials

5

* “CSI” stands for “Commercially-Sensitive Information.”

1 2 3 4 5 6

slide-6
SLIDE 6
  • 2. Key Concepts

6

4 5 6 1 2 3

slide-7
SLIDE 7
  • MHEM – Manitoba Hydro Export Marketing
  • MHT – Manitoba Hydro Transmission
  • OATT – Open Access Transmission Tariff
  • CPJ – Capital Project Justification
  • FCA – Facilities Construction Agreement
  • GFS – Group Facilities Study
  • GSIS – Group System Impact Study
  • Transfer Capability – capacity, in MW, of a

transmission intertie

Key Concepts

A Few Key Terms

7

4 5 6 1 2 3

slide-8
SLIDE 8
  • 3. Project History and Status

8

4 5 6 1 2 3

slide-9
SLIDE 9

Transmission System, Pre-Agreement

  • 225 MW total transfer

capability

  • Various commitments against

that capability (CSI)

  • 45 MW available

Transmission System, with Project

  • 325 MW total transfer

capability

  • Retains capability to meet

existing commitments (CSI)

  • Allows for full amount of

power sale to SaskPower

Project History and Status

Existing System

9

4 5 6 1 2 3

slide-10
SLIDE 10
  • Power Sale Agreement (January 2016)
  • Facilities Construction Agreement (May 2017)
  • Transmission project in development
  • First monthly status report for transmission

reviewed (October 2017)

  • Limited transmission costs incurred to date

(roughly $1.6 million)

  • Further information in the CSI presentation

Project History and Status

Status

10

4 5 6 1 2 3

slide-11
SLIDE 11

Project History and Status

Key Timeline Elements

11

4 5 6 1 2 3

<-- TODAY

Q4 Q2 Q4 Q2 Q4 Q2 Q4 Q2 Q4 Q2 Q4 Q2 Q4

                                                                              

Transmission-related and energy sale-related events

<--2012 Facilities Study Term sheet negotations Transmission Service Requests (TSR) submitted by MHEM MH and SaskPower execute term sheet "Capital Project Justification for Manitoba - Saskatchewan Transmission Project" published GSIS MH and SaskPower execute PSA …energy sale contract duration, 2020 - 2040 to 2040 --> GFS …earliest in-service date for transmission, per GFS FCA 1st status report Licensing

 Provincal license decision

Station construction Transmission line construction

2018

Q3

2020 2021

Q1 Q3 Q1

2016 2015

“Saskatchewan Power 100/140 MW Sale Evaluation” study issued

2019

Q3 Q1 Q3 Q1 Q3 Q1 Q3 Q1 Q3

2017

slide-12
SLIDE 12
  • 4. 2016 Economic Analysis

12

4 5 6 1 2 3

slide-13
SLIDE 13
  • Evaluation considered 100 MW sale plus

potential for additional 40 MW

  • Evaluation used Manitoba Hydro’ long-term

planning model (SPLASH)

  • Base case assumed future Manitoba Hydro need

would be met with new gas fired generation

  • Results were expressed as net present value

(NPV) of sale plus transmission versus base case

  • Sensitivity analysis performed (Details in the CSI

presentation)

2016 Economic Analysis

Overview of the 2016 Sale Evaluation

13

4 5 6 1 2 3

slide-14
SLIDE 14
  • In general, late 2015 planning assumptions were used
  • Resource impacts of the sale were determined using

the July 2015 Resource Planning Assumptions and Analysis for 2015/16 Corporate Planning Report

  • Keeyask was assumed to be in-service in 2019
  • New 500-kV US connection assumed to be in-service

in 2020

  • Manitoba-Saskatchewan transmission project costs

sourced from the 2015 GSIS

2016 Economic Analysis

Review of Key Assumptions

14

4 5 6 1 2 3

slide-15
SLIDE 15
  • 5. 2017 Updated Analysis

15

5 6 1 2 3 4

slide-16
SLIDE 16
  • Based on a Daymark request, Manitoba Hydro

updated the analysis

  • Used Manitoba Hydro assumptions consistent with the

current General Rate Application

  • Updated transmission costs based on latest information
  • Served as the starting point for Daymark analysis of key input

assumptions

  • Daymark sensitivity analysis
  • Goal – test the current economics of the project
  • All information is commercially-sensitive

2017 Updated Analysis

16

5 6 1 2 3 4

slide-17
SLIDE 17
  • 6. Key Findings

17

6 1 2 3 4 5

slide-18
SLIDE 18
  • Transmission project is still in the early stages
  • f development
  • Any potential delays in the transmission

project do not present a significant risk to the near-term value of the power contract

  • The transaction, including the transmission

project, remains in the best interest of Manitoba Hydro and its ratepayers

  • Addition findings will be discussed in the CSI

portion of the presentation Key Findings

18

6 1 2 3 4 5

slide-19
SLIDE 19

Dan Peaco Daymark Energy Advisors 48 Free Street Portland, Maine 04101 Tel: (207) 347-3194 Email: dpeaco@daymarkea.com

End of Presentation

19

Doug Smith Daymark Energy Advisors 48 Free Street Portland, Maine 04101 Tel: (617) 778-2450 Email: dsmith@daymarkea.com

www.DaymarkEA.com