Direct Examination of Patrick Bowman On behalf of the Manitoba - - PowerPoint PPT Presentation

direct examination of patrick bowman
SMART_READER_LITE
LIVE PREVIEW

Direct Examination of Patrick Bowman On behalf of the Manitoba - - PowerPoint PPT Presentation

Direct Examination of Patrick Bowman On behalf of the Manitoba Industrial Power Users Group (MIPUG) April 25, 2019 1 Outline Introduction Approach Testing application (February update) justification Assessment based on one-year


slide-1
SLIDE 1

Direct Examination of Patrick Bowman

On behalf of the Manitoba Industrial Power Users Group (MIPUG) April 25, 2019 1

slide-2
SLIDE 2

April 25, 2019

Outline

2

 Introduction  Approach  Testing application (February update) justification  Assessment based on one-year forecasts  Testing longer-term directional information  Other topics

Main Recommendation – across-the-board increase of 0% to 1.5% is justifiable based on: (a) reasonable customer expectations of annual rate increases; (b) no evidence rate increase above inflation is needed this year, and (c) benefit to smooth transition to higher rates to address Keeyask in-service (and eventual end of Bipole III deferral amortization). Consideration given to ensuring rate increase is deferred for Keeyask, similar to Bipole III account, to help ensure purpose is clear – not intended to fund growth in Hydro’s current costs.

slide-3
SLIDE 3

April 25, 2019

Introduction

3

 Evidence comprises MIPUG Exhibits:

 MIPUG-5 – Pre-filed Testimony  Responses to information requests from the Consumers Coalition (CC-9), PUB (PUB-

12) and Manitoba Hydro (MH-22).

 Comment on new issues arising from process.  Longstanding MIPUG Assignment – Review Hydro proposals and plans in

light of regulatory principles appropriate for Crown hydro utility – long-term perspective

 Fundamental view that interests of customers and Hydro should not be seen to be at

  • dds. Customers need financially sufficient Hydro, Hydro needs customer loads,

competitive rates, reliable service.

 Not like regulation of private sector utility, or a quasi-private utility with government investment

slide-4
SLIDE 4

April 25, 2019

Approach

4

 Proceeding led to challenges for analytical assessments as to whether rates are

sufficient, and are just and reasonable.

 Historically, Manitoba Hydro has always been regulated on basis of long-term

financial targets.

 Rates set to collect current period costs (O&M, interest on assets in service, taxes, etc.)  Testing if customers were sustainably funding (or drawing down) reserves to still

permit future rate stability

 In part reflects hydrology variability as discussed by MH earlier in hearing  Reserves are inherently longer-term concept

 Forecasts of one-year of finances is not sufficiently informative, on their own,

to draw conclusions on rate path. For this reason, concluded context was needed beyond just one-year information.

slide-5
SLIDE 5

April 25, 2019

Approach – looked at both one-year, and MH-93 path

5

 Relied on Exhibit MH-93

 Used by Hydro as a benchmark in the Application  Board found “with minor adjustments, this scenario is directionally consistent with the Board’s

decisions in this Order” (59/18, page 173)

 Defensible as a long-term trajectory

 Previously reviewed that MH-93 scenario showed 6 years of net losses.  Existence of losses was similar to each previous IFF (as summarized in MH-93):

 NFAT Scenarios for Keeyask – 8 years of losses totalling $638 million  IFF14 – 8 years of losses totalling $977 million  IFF15 – 3 years of losses totalling $58 million  Ex. MH-93 (based on IFF16) – 6 years of losses totalling $418 million  In each subsequent IFF, the start of net losses moved later, meaning higher retained earnings at

start of net loss period, better positioned to absorb losses.

 Overall – NFAT expansion era is unfolding very well.

slide-6
SLIDE 6

Context - Example of Bowman direct June 2015 re: IFF14

6  On surface, IFF14

showed challenges. But needed to recognize scale of hurdle.

 Still true for 5 impacts

being absorbed

 Still no Government

support; same pile-on effect.

 Operating cash flow

now far ahead of this level (now debating if this can be met in each

  • f the worst years, not

just over the decade)

 Retained earnings now

far exceed last estimated cost of 5 year drought.

slide-7
SLIDE 7

April 25, 2019

Testing Hydro’s Updated Application (page 6-7 of MIPUG-5)

7

 Hydro’s update no longer needs 3.5% increase to avoid net losses.  Instead relies on 3 claims in support (Feb 14 Supplement, page 3):

  • 1. Waiting for low flow to give higher rates would result in increased debt:

 Mathematically true, but not the appropriate test for managing drought.  Implies net income is the tool to manage drought risk. Ignores retained earnings, and PUB

comments on reserves and regulatory action as the appropriate way to manage drought.

 If taken at face value, simply a directional support for perpetual large rate increases

  • 2. Keeyask and Bipole III cost increases could exacerbate losses in MH-93

 Noted as curious, given Bipole and Keeyask have good news compared to MH-93  Net losses in MH-93 (and each prior IFF) were well-known, and were part of rate transition

  • 3. Granting rate increase now reduces likelihood of future rate shock:

 Again, mathematically true, but not possible to test without long-term information  No information on how likely a rate shock is, how big it might be, how much a rate increase

  • f 3.5% reduces the likelihood – cannot be assessed without long-term forecasts
slide-8
SLIDE 8

April 25, 2019

One-Year Assessment - Comparison to MH-93, for 2019/20

8

Key Values:

 Long-term debt lower (by $0.580 billion)  Capital Investment cost control shows improvement (Plant in Service down by $0.543

billion)

 Retained earnings lower ($0.127 billion if no rate increase in 2019/20); one-year

drought risk for 2019/20 reduced due to known water in storage (max one-year adverse impact reduced from $432 million to $347 million)

 Basically same net income ($64 million) even without the annual rate increase

assumed in MH-93. One-year assessment – basically on track even before considering 2019/20 rate increase.

slide-9
SLIDE 9

April 25, 2019

One-year Assessment – Cash (and Capitalized Interest)

9

 Cash flow from Operations per MIPUG-MH-8c is positive. Exceeds Normal Capital Spending.  Two perspectives per MH Rebuttal : [note: this is transitory issue – IDC not typically this large]

 Issues with MH approach:

  • 1. Not consistent with ‘Used and Useful’ principles
  • 2. Not consistent with past PUB conclusions (59/18)
  • 3. Purports to show what happens when

Keeyask comes on-line – but ignores the added Revenue (approx. $360 million – PUB book, Page 76).

  • 4. No principled reason to treat interest different than
  • ther construction costs

More important - Hydro’s approach is not bad news – from cash perspective, this is close to a ‘post Keeyask’ picture, if you add $360 million export revenues and about $30 million extra water rentals and O&M – in short, we can cash flow a post-Keeyask year with today’s rates. (PUB/MH-I-9U)

Figure 6, Hydro Rebuttal, page 9

slide-10
SLIDE 10

April 25, 2019

Longer-Term Directional Assessment

10

 Compared to MH-93, key updated information:

 Bipole III lower cost  Keeyask earlier in-service (sooner revenues, ongoing savings).

 Hard to reconcile material schedule improvement with no improvement in cost ($8.7B) when IDC

is approaching $25 million a month and camp is $1 million per day to operate. But will accept evidence of no net cost reduction.

 Keeyask risks increasingly getting resolved – example of geotech  Added export contracts – SaskPower 215 MW. Potential renewals of Xcel Energy/NSP

 Last hearing (MH-93) evidence was no new contracts could arise or be assumed, has financial

impacts within important early years of Keeyask.

 Interest rates – average interest rate slightly higher in 2019/20 (0.18%), this is before

latest debt. But, this has been locked in for much longer, so MH-93 should show sustained benefits, with much lower refinancing impacts starting within a few years.

slide-11
SLIDE 11

April 25, 2019

Longer-Term Directional Assessment (cont’d)

11

 DSM future unknown, but hard to see case for more upward rate pressure from DSM. MH-93

included DSM programs that are now not likely to occur (most notably Fuel Choice).

 Note that just the change from the November application to February update is material – adds $30

million extra domestic revenue, offset by $12 million less export revenues, and reduced program spending $33 million in 2019/20 alone. (MIPUG/MH-2b)

 All of these updates are on top of assessments already noted by the Board about why MH-93

was conservative in 59/18.

 For example MH-93 did not consider export price benefits or import price reductions (2-5% in each

case) due to MMTP/GNTL (page 129 of 59/18). Also did not consider any dependability premium for uncontracted dependable export energy and had 7.9% price elasticities in load forecast.

 No apparent material or sustained negative developments compared to MH-93

 Not to confuse accounting detail regarding Keeyask earlier in-service with bad news.

 This is not an assessment based on “hope”. This reflects latest and best updated

information.

slide-12
SLIDE 12

Other Topics

12

slide-13
SLIDE 13

April 25, 2019

Is negative Net Income “OK”?

13

 Hydro rebuttal indicates it was intended to rebut Bowman evidence that negative Net

Income is OK. Not fair summary of Bowman evidence.

 Negative net income was part of each IFF since NFAT, including all Development

Plans at NFAT that included Keeyask.

 Negative net income was part of Order 25-92, when PUB directed a lower rate

increase than requested by Hydro despite net losses in the IFF at that time (1992).

 Negative net income was part of 2004 drought. Will always be part of droughts or

  • ther risks reliant on reserves.

 Also addressed by MIPUG & Coalition witnesses (Colaiacovo) at previous GRA.  Obviously, positive net income is better than negative, all other things being equal, so

long as it is not the primary purpose of otherwise unneeded rate increases.

 Zero or negative net income is simply a sign of reserves being sustained or drawn down, for

rate stability purposes.

slide-14
SLIDE 14

April 25, 2019

Are we “running out of time”? (transcript April 24)

14

 We are only running out of time if the intent is that rate increases will save Hydro

from all net losses from Keeyask and Bipole III in each year.

 That is not a reasonable standard

 For calculations that already include Capitalized Interest in financial calculations,

next few years will show massive improvement, not increased need for action.

 Keeyask debt (main Keeyask post-in-service cash impact) already in the expense side of these

calculations

 Keeyask revenue not yet in the benefits column (e.g. Cash receipts from customers).  This applies to Moody’s EBIT, Moody’s EBITDA cash ratio (not focus of Hydro’s evidence,

but currently 1.2 per Moody’s), and Hydro’s cash flow calculations per Rebuttal evidence.

 Similarly Bipole III deferral amortization, which will replace non-cash revenue with

cash revenue, as rates replace the deferral amortization. Increases cash flow over time

 If running out of time on anything, its how to start using Hydro’s uncertainty analysis

to determine appropriate reserve levels post-Keeyask (Minimum Retained Earnings) and communicate this to stakeholders (including customers, lenders, ratings agencies)

slide-15
SLIDE 15

April 25, 2019

Cost of Service (Coalition/MIPUG-I-5)

15

 Recommendation is to use across-the-board adjustments for any rate increase.  Reflects lack of PCOSS updated to the Test Year.  Revenue:Cost information available is not sufficient for class-specific rate changes.

 Reflects past fiscal year, with only Bipole III adjusted.  Does not reflect what is happening in other functions.  Outside of Major Capital, Hydro is spending relatively little on some functions:

 Generation (CEF averages $100 million/year for sustaining Generation, on an asset base of about $7.4 billion in

PCOSS18)

 Transmission (CEF averages less than $50 million/year for sustaining Transmission, on an asset base of about $2.2

billion in PCOSS18)

 Distribution spending however is very large. Averages $225 million/year on an asset base of about

$2.7 billion in PCOSS18. Plus this impact is magnified on the distribution-served classes (e.g., residential, GS Small) as:

 There is a smaller customer base to absorb these costs  The depreciation period for these assets tends to be somewhat shorter than for Generation and Transmission.

 None of this other spending is in the new PCOSS estimate. For this reason, the coarse PCOSS

revision provided is not considered reliable.