Demolition of the Cowley- Goettman Recreation Center Community - - PowerPoint PPT Presentation

demolition of the cowley goettman recreation center
SMART_READER_LITE
LIVE PREVIEW

Demolition of the Cowley- Goettman Recreation Center Community - - PowerPoint PPT Presentation

BUREAU OF FACILITIES, ARCHITECTURE DIVIS DEPARTMENT OF PUBLIC WORKS Demolition of the Cowley- Goettman Recreation Center Community Meeting #2 April 10, 2019 Mayor William Peduto Mike Gable, CPRP City of Pittsburgh Department of Public Works


slide-1
SLIDE 1
slide-2
SLIDE 2

DEPARTMENT OF PUBLIC WORKS BUREAU OF FACILITIES, ARCHITECTURE DIVIS

Demolition of the Cowley- Goettman Recreation Center

Community Meeting #2 April 10, 2019

slide-3
SLIDE 3

3 Mayor William Peduto City of Pittsburgh Councilwoman Darlene Harris Pittsburgh’s 1st District Molly Onufer Community Affairs Manager Leah Friedman Community Liaison Mike Gable, CPRP Department of Public Works (DPW) Director Chris Hornstein, RLA DPW Assistant Director – Bureau of Facilities Casimir Pellegrini III, AIA Senior Project Architect Andrea L. Ketzel, RLA Senior Project Landscape Architect Joe Adiutori, Jr., AIA Associate Project Manager Harvey Butts Associate Project Manager

slide-4
SLIDE 4

4

  • 1. INTRODUCTIONS
  • 2. REVIEW BUILDING CONDITION & THE FACILITIES OPTIMIZATION

PLAN

  • 3. DISCUSS WHAT SHOULD BE SALVAGED FROM THE BUILDING
  • 4. REVIEW DEMOLITION PROCESS
  • 5. REVIEW COST ANALYSIS
  • 6. Q&A
  • 7. CONCLUSIONS

Presentation Outline

slide-5
SLIDE 5

5

Cowley-Goettman Recreation Center

slide-6
SLIDE 6

6

slide-7
SLIDE 7

7

slide-8
SLIDE 8

8

slide-9
SLIDE 9

9

slide-10
SLIDE 10

10

slide-11
SLIDE 11

11

slide-12
SLIDE 12

12

slide-13
SLIDE 13

13

slide-14
SLIDE 14

14

Facilities Optimization Plan

slide-15
SLIDE 15

15

slide-16
SLIDE 16

16

slide-17
SLIDE 17

17

Architectural Salvage – Stone Work

slide-18
SLIDE 18

18

Architectural Salvage – Gym Flooring

slide-19
SLIDE 19

19

Architectural Salvage – Building Signage

slide-20
SLIDE 20

20

Architectural Salvage – Wall Mosaic

slide-21
SLIDE 21

21

  • Misc. Salvage – Basketball Standards & Banner
slide-22
SLIDE 22

22

  • Misc. Salvage – Warming Table & Billiard Table
slide-23
SLIDE 23

23

Miscellaneous Salvage – Frigidaire Fridge

slide-24
SLIDE 24

24

Miscellaneous Salvage – Westinghouse Fridge

slide-25
SLIDE 25

25

Demolition Process (4 to 6 months)

  • 1. Engineering (4 to 6 weeks); currently ongoing
  • 2. Permitting & Termination (4 to 8 weeks)
  • Will occur after the award, but prior to demolition.
  • Utilities to the building will be terminated.
  • 3. Building Demolition (12 to 18 weeks)
  • The City will work with the community to minimize impact to park usage.
  • 4. Mitigation Efforts:
  • Noise: Operation times to be specified in order to minimize disturbance.
  • Air Quality: Specify dust suppression & haul away all materials by contractors. Note: No

material processing (i.e. brick crushing) will be allowed on-site

  • Pest Control: Building to be exterminated prior to demolition.
  • Safety: Temporary perimeter fence will be installed around the building.
  • Post-Demolition Improvements: Engineered Slope will be required & the installation of a

railing along the sidewalk.

slide-26
SLIDE 26

26

Demolition Engineering Proposal

slide-27
SLIDE 27

27

slide-28
SLIDE 28

28

slide-29
SLIDE 29

29

Funding Sources

slide-30
SLIDE 30

DEPARTMENT OF PUBLIC WORKS BUREAU OF FACILITIES, ARCHITECTURE DIVIS

Question & Answer Session

slide-31
SLIDE 31

31

Next Steps