December 3, 2019 DEQ Meeting 11/20/19 Preliminary Analysis Report - - PowerPoint PPT Presentation
December 3, 2019 DEQ Meeting 11/20/19 Preliminary Analysis Report - - PowerPoint PPT Presentation
PRELIMINARY ANALYSIS REPORT DAMS CONSTRUCTION/RECONSTRUCTION PROJECT CITY OF BOILING SPRING LAKES BOARD UPDATE December 3, 2019 DEQ Meeting 11/20/19 Preliminary Analysis Report (PAR) Agency Coordination Codes and Standards
DEQ Meeting 11/20/19
- Preliminary Analysis Report
(PAR)
- Agency Coordination
- Codes and Standards
- Preliminary H&H
- Geologic Conditions
- Design Considerations
- Recommendations
Alton Lennon Road (Sanford Dam) during Hurricane Florence
Preliminary Analysis Report
A meeting on June 3, 2019 with FEMA, NCDOT and NC Dam Safety Program revealed that additional tasks were necessary to fully define FEMA’s Disaster Recovery Scope of Work related to the BSL dams. These tasks are the primary focus of this Preliminary Analysis Report. They include:
- Coordination with agencies to determine the most suitable permitting
process
- Comprehensive hydrologic and hydraulic models
- Subsurface exploration program to fully address potential issues related to
sinkhole formation
- Utilizing East Boiling Spring Lake Road as an impounding structure for
North Lake and Pine Lake
Agency Coordination
McGill met onsite on 10.17.19 with:
- NC Wildlife Resources
Commission,
- NC Department of Environmental
Quality and
- US Army Corps of Engineers on
site
1.
Permit based on pre Florence conditions - impacts to open water. (anticipate NWP 3 for Maintenance Activities and Water Quality General Certification 4132).
UPPER LAKE MIDDLE LAKE PINE LAKE NORTH LAKE SPRING LAKE B O I L I N G S P R I N G L A K E ALLEN CREEK
³
1 0.5 Miles SANFORD DAM NORTH LAKE DAM PINE LAKE DAM MIDDLE LAKE DAM UPPER LAKE DAM SR 87
Boling Spring Lakes Site Map
5
Agency Coordination (cont.)
2.
WRC requested inclusion of data on the need to restore the lakes.
3.
Low flow conditions will be established in order to maintain downstream aquatic habitat within Allen Creek
4.
NCHPO found no historic impacts.
5.
Middle Dam (private) may be reconstructed under NRCS EWP grant.
Middle Dam post Hurricane Florence
Codes and Standards
- All dams predated NC Dam Safety regulations
- Pre Florence - all dams were functional and impounding
- Post Florence - all dams are now considered High Hazard
- NC Regulations require reconstructed all dams meet current design
standards per 15A NCAC 02K.0204(e)
- Hydrologic and Hydraulic Evaluation and Spillways Design
- Sanford spillway must provide overtopping protection up to ½ PMP storm
- North Lake, Pine Lake, and Upper Lake spillways must provide overtopping
protection up to ⅓ PMP storm
- Geotechnical Evaluation and Embankments Design
- Sanford - Sink holes, Seepage, Stability
- North Lake, Pine Lake, and Upper Lake – Seepage and Stability
Preliminary Hydrologic/Hydraulic Evaluation
- Hydrology – PMP analysis
- Hydraulics – Combined modeling approach
- Comparison to effective model
- Initial spillway sizing
- Preliminary breach conditions
Boiling Spring Lake Watershed 49.69 in 28047 ac-ft
Initial Spillway Sizing
Overtopping Storm Design Flow (SDF) Water Surface Elevation Elevation Event Flow Normal SDF Freeboard Upper Lake Dam 41.3 ⅓ PMP 943.1 38 40.4 0.9
- E. Boiling Spring at Pine Lake Dam
44 ⅓ PMP 335.9 35 38.6 5.4
- E. Boiling Spring at North Lake Dam
40 ⅓ PMP 888.2 35 38.3 1.7 Alton Lennon Road at Sanford Dam 39 ½ PMP 6477 30 35.3 3.7 Upper Dam Breach 35.5 Upper and Middle Dam Breach 35.7
Overview of NLD/PLD/ULD Explorations
- Intent of Exploration
- Confirm approximate height of the dams
- Characterize fill soils and foundation materials
- Exploration Method
- Auger Borings with Standard Penetration Tests (SPT)
- General Findings
- Dams are similar to design drawings.
- Foundation soils:
‐ poorly‐graded sands overlying clayey sands ‐ N < 10 blows per foot (bpf)
- Dam fill soils:
‐ poorly‐graded sands found in City vicinity ‐ 10 bpf < N < 30 bpf
- No core soils identified
- Pre‐construction natural debris, organic soils, and other materials
NLD/PLD/ULD Alternative 1 – Embedded Riser
NLD/PLD/ULD Alternative 2 – Riser in Lake
NLD/PLD Alternative 3 – Upgrade Existing
ULD Alternative 3 – Open Channel Spillway
Seepage Events at Sanford Dam (SD)
- Records available for four seepage events
- 1962
- 1976-1978
- 1986-1987
- 2001-2002
- Average of one event per decade in first 40 years
1986-1987 SD Seepage Event
Overview of SD Exploration
SD Design Goals
- Reduce risk to Dam Safety due to uncontrolled seepage
- Safely pass design flood
- Restore the lake to pre-breach condition
- Extend design life
- Facilitate ability to drain lake
- Promote public safety
- Meet additional current codes and standards
SD Common Design Modifications
- New Spillway
- Repair / regrade embankment
- Install positive seepage cutoff
- Remove existing spillway
Seepage Failure Mode
(taken from Best Practices in Dam and Levee Safety Risk Analysis, USBR / USACE, 2015)
SD Alt. 1A – Labyrinth in Existing Footprint
SD Alt. 1B – Labyrinth in Breach
SD Existing Spillway Removal
Example Labyrinth Spillway
SD Alt. 2A – Riser in Existing Spillway Footprint
SD Alt. 2B – Riser in Breach
Meeting Conclusions
- Any objections to the presented approach/alternatives?
- The most cost effective solution will be recommended for design.
- FEMA stated that it is important to move to the next step
- FEMA stated that there is still uncertainty on the responsibility split
between NCDOT and the City on North Lake and Pine Lake Dams
33
Schedule
34
Next Steps
- Complete PAR – due 1/14/20
- Complete FEMA Scope of Work for each dam
- Assist City in coordination with DPS and FEMA
- HMGP funding
- Eligibility concerns for EBSR at North Lake and Pine Lake Dams (quit
claim deeds from Reeves Telecom pending)
- City approval to proceed with Design Phase (including
Sanford Spillway)
MH1
Slide 34 MH1 include overall timeline
Michael Hanson, 12/2/2019