Customer Handoff & Final Project Documentation P18082 - - PowerPoint PPT Presentation

customer handoff final project documentation
SMART_READER_LITE
LIVE PREVIEW

Customer Handoff & Final Project Documentation P18082 - - PowerPoint PPT Presentation

Customer Handoff & Final Project Documentation P18082 Electrical Bioreactor Agenda 1. Team Vision Emily 6. 1. Functional Demo Materials 2. Test Results Summary Jon+Shena+Dillon a. Mechanical Luc b. Electrical Jon a. Test Plan 7:


slide-1
SLIDE 1

Customer Handoff & Final Project Documentation

P18082 Electrical Bioreactor

slide-2
SLIDE 2

Agenda

1. Team Vision Emily 2. Test Results Summary Jon+Shena+Dillon

a. Test Plan 7: Electrical Requirement Verification Test b. Test Plan 8: Full-Run Electrical Bioreactor Test

3. Problem Tracking Emily 4. Risk Assessment Dillon 5. Final Project Documentation

a. Design Schematics and Drawing Files Luc b. Bill of Materials Dillon c. Operators Manual All d. Software Jon e. Recommendations for Future Work Emily

1. Functional Demo Materials

a. Mechanical Luc b. Electrical Jon

2. Conclusion All 6. 7.

slide-3
SLIDE 3
  • 1. Team Vision

1. Rerun Test Plan 8 with corrected voltage values 2. Complete test plan result documentations 3. Finalize bioreactor unit redesign

a. Complete machining and assembly of bioreactor for Imagine b. Complete electrical wiring for Final Presentation

4. Complete all documentation and manual for customer handoff following finals 5. Have successful presentations

a. IAB Meeting b. Lighting Talks c. Imagine RIT

slide-4
SLIDE 4
  • 1. Team Vision - Schedule
slide-5
SLIDE 5
  • 1. Team Vision - Schedule Continued
slide-6
SLIDE 6
  • 1. Team Vision - Schedule Continued
  • All tasks outlined in the schedule were completed for phase 4 except for the following

○ 4.12 Customer Handoff ■ WIll occur following finals week with Prof Bailey ○ 4.16 Review with Guide Research Paper ■ Did not need to occur ○ 4.18 Complete Edge Website ■ Edge will be updated following final MSD review with guide and customer ○ 4.19 Clean Workspace ■ Workspace will be cleaned following manufacturing and assembly of additional carbon electrodes and 6-well plates

slide-7
SLIDE 7

Test Plan Summary

slide-8
SLIDE 8
  • 2. Test Plan 7: Electrical Requirement Verification

Test

slide-9
SLIDE 9
  • 2. Test Plan 7: Electrical Requirement Verification

Test

slide-10
SLIDE 10
  • 2. Test Plan 7: Electrical Requirement Verification

Test (Customer Requirements)

CR2.1 1 Apply a static or cyclic voltage across the culture for up to 3 weeks

50%

CR2.2 3 Controllable and adjustable stimulation during the experiment

Passed

CR3.1 2 Verification of correctly applied voltage

Passed

CR4.1 1 Safe for student population usage

Passed

slide-11
SLIDE 11
  • 2. Test Plan 7: Electrical Requirement Verification

Test (Engineering Requirements)

  • Engr. Requirement (metric)

Unit of Measure Marginal Value Ideal Value Actual Value Test Result Applies a voltage V 0 - 5 <5 +/- 0.05 0 - 0.5 0 - 0.5 +/- 0.05 Measures the applied voltage V +/- <0.015 +/- 0 +0.015V

  • 0.007V

Quickly adjustable applied voltage min 1 - 3 1 <0.5 <0.5 Software usage straightforward

  • Minimal Questions

No Questions

Passed

Shock hazard during normal operation including moving for media exchange or viewing on microscope

  • Passed
slide-12
SLIDE 12
  • 2. Test Plan 8: Full-Run Electrical Bioreactor Test
slide-13
SLIDE 13
  • 2. Test Plan 8: Full-Run Electrical Bioreactor Test

Test Well 1 on Day 2: Cells look healthy and thriving Test Well 2 on Day 2: Cells look healthy and thriving

slide-14
SLIDE 14
  • 2. Test Plan 8: Full-Run Electrical Bioreactor Test

Control Well 1 on Day 2: Cells look healthy and thriving Control Well 2 on Day 2: Cells look healthy and thriving

slide-15
SLIDE 15
  • 2. Test Plan 8: Full-Run Electrical Bioreactor Test
slide-16
SLIDE 16
  • 3. Problem Tracking
slide-17
SLIDE 17
  • 3. Problem Tracking - Continued
  • 3. Unknown reactor resistance
  • Wrote new code for LabVIEW and Arduino
  • Confirmed current output values were in desired range
  • 4. Unknown reactor current
  • Wrote new code for LabVIEW and Arduino
  • Confirmed current output values were in desired range
  • 9. Carbon electrode adhesion process is not sterile
  • Viability of cells was not affecting by carbon electrode adhesion and no further

actions needed to be taken

slide-18
SLIDE 18
  • 3. Problem Tracking - Continued
  • 10. Spring-latch holding in well-plate is inefficient
  • Redesigned spring-latch and reconfigured location
  • More ergonomic spring-latch implemented in redesign of bioreactor unit
  • 11. Arduino housing hinge is rigid
  • Research was conducted to find a hinge with better hinge properties
  • Less rigid hinge was implemented in the new design
  • 12. Electrical Bioreactor is heavy compared to other biological items
  • Lighter materials of Polycarbonate and Acetal Delrin replaced Aluminum in

redesign of bioreactor unit

slide-19
SLIDE 19
  • 3. Problem Tracking - Continued
  • 10. Voltage too high for first Test Plan 8 trials
  • Lower voltage values need to be considered
  • Recommended 0.2 - 0.5 V range following electrical tests
  • 11. Cells in Test Plan 8 were dying
  • Voltage ranges in 11 was not implemented in rerun of Test Plan 8
  • Recommended MAX voltage value of 0.5 V to sustain cell growth
slide-20
SLIDE 20
  • 4. Risk Assessment
  • Performed a final review of risk items
  • Determined whether the risks were avoided
  • Most risks were addressed and reduced

○ Risk #7: Cell death due to lack of space -- Electrodes were cut so that they could be spaced at maximum effective distance, which would allow the maximum space for seeding cells. However, future users may be required to determine a means of slowing cell growth through adjustments in the cell media. ○ Risk #8: Screws/threaded holes become stripped -- The final product was fabricated out of polycarbonate and acetal delrin in order to reduce the system weight and avoid the possibility

  • f drops which result in stripping the fasteners. However, should accidents occur, a gluing or

bonding material is recommended to make fixes.

slide-21
SLIDE 21
  • 4. Risk Assessment
slide-22
SLIDE 22
  • 5a. Design Documentation

Arduino Housing Front Wall

slide-23
SLIDE 23
  • 5a. Design Documentation

Arduino Housing Side Walls

slide-24
SLIDE 24
  • 5a. Design Documentation

Arduino Housing Lid

slide-25
SLIDE 25
  • 5a. Design Documentation

Back Plate

slide-26
SLIDE 26
  • 5a. Design Documentation

Base Plate

slide-27
SLIDE 27
  • 5a. Design Documentation

Bracket

slide-28
SLIDE 28
  • 5a. Design Documentation

Electrical Connection Plate

slide-29
SLIDE 29
  • 5a. Design Documentation

Latch

slide-30
SLIDE 30
  • 5a. Design Documentation

Wire Plate

slide-31
SLIDE 31
  • 5a. Design Documentation

Lift Tab

slide-32
SLIDE 32
  • 5b. Bill of Materials
  • No items are planned for or awaiting

delivery.

  • We went over our original budget of

$500.00 by $52.02.

  • Biological items drove up the cost of the

project.

  • Should only the physical system be

required, then costs will be reduced by approximately half.

  • In addition, the final design requires fewer

components, which should drop the cost even more. Total Budget $1,000.00 Current Expenses $552.02 Current Budget $447.98 Projected Costs $0.00 Estimated Final Budget $447.98

slide-33
SLIDE 33
  • 5b. Bill of Materials
  • An example of some of the items we

recommend should Dr. Bailey desire to build another system.

  • Should be used in conjunction with

manufacturing and assembly instructions.

  • The plan is to drop off a list of materials

and where to purchase them at the customer hand-off.

Item Vendor Catalog # Individual Cost White Delrin Acetal Bar, 1-1/4" Thick, 4" Wide, 1' Long McMaster-Carr 8739K62 $44.32 Clear Polycarbonate Sheet, ½” Thick, 12” Wide, 12” Long McMaster-Carr 8574K32 $32.34 Off-White Nylon Pan Head Screws Phillips 1/4"-20 Thread, 3/4" Long McMaster-Carr 93135A454 $7.41 Off-White Nylon Pan Head Screws Phillips 1/4"-20 Thread, 1-1/2" Long McMaster-Carr 93135A456 $7.65 Adjustable-Fricti

  • n

Surface-Mount Hinge, Black Acetal Plastic, 7 in.-lbs. Torque McMaster-Carr 1791A44 $6.92

slide-34
SLIDE 34
  • 5c. Operators Manual

We would like to navigate to the GoogleDrive to open the Operators Manual for demonstration

slide-35
SLIDE 35
  • 5e. Recommendations for Future Work
  • Mechanical

○ Continue to look for ergonomic and system improvements of the bioreactor unit ■ Materials ■ Arduino housing hinge ■ Well plate spring-latch

  • Electrical

○ Addition of cyclic waveform to be included for student selection ■ With user variable frequency

  • Biological

○ Allow class to choose preferred cell line for electrical testing ○ Determine effective testing voltages based on cell line

slide-36
SLIDE 36
  • 7. Conclusion

The end product, following the senior design process from Problem Definition through Integrated System Build & Test, is a functional electrical bioreactor that the Advanced Cell Culture Techniques course can utilize as a tool to study the effects an electrical stimulus will have on tissue engineering cells.

We would like to personally thank Dr. Jennifer Bailey and Dr. Vinay Abhyankar for their guidance and insight of cell culture and tissue engineering. In addition, we appreciate the access to their research laboratories. The Kate Gleason College of Engineering, the Biomedical Engineering Department, Mechanical Engineering Machine Shop at RIT, and Robotics Lab are to be thanked: including Dr. Steven Day, Dr. Jason Kolodziej, and Mr. Jan Maneti. A special thank you to our guide, Michael Zona, for his patience, guidance, and knowledge on the multidisciplinary senior design process and engineering requirements.

slide-37
SLIDE 37
  • Misc. Info
slide-38
SLIDE 38
  • 2. Test Plan 8: Full-Run Electrical Bioreactor Test

Cell Viability Test (4/27/18) Initial Check Secondary Check Living Cells/uL Dead Cells/uL Living Cells/uL Dead Cells/uL Test 1 3 7.5 8 20 1 2.5 Test 2 3 7.5 1 2.5 2 5 2 5 Control 1 12 30 1 2.5 29 72.5 10 25 Control 2 114 285 1 2.5 257 642.5 Initial check was performed on Friday afternoon (4/27) and the secondary check was performed several hours later. The secondary check was performed to validate the numbers observed in the initial check.