Corporate Presentation
June 2017
1
Corporate Presentation June 2017 1 Overview of Sahakol Equipment - - PowerPoint PPT Presentation
Corporate Presentation June 2017 1 Overview of Sahakol Equipment Public Company Limited (SQ) The leading mining contractor with well-established track record in Thailand and Laos The first Thai open-pit lignite mining contractor in 1983
1
Overview of Sahakol Equipment Public Company Limited (“SQ”)
The first Thai open-pit lignite mining contractor in 1983 Integrated mining service company focusing on mega mining projects including mine planning
and logistic solutions, open pit mining operation, heavy duty machine leasing, rental and maintenance services Our Business
Highly experienced management and operational team with over 30 years of
experiences
Over 1,000 staff including over 45 engineers
Our Team
Thailand: Mae Moh Phase 7 and 8 Laos: Hongsa Mine Phase D
Myanmar : Henda Tin Mine (Q4/2017) Our Operation
Secured backlog with remaining project value of THB 37,572 million for the next 10
years (as of March 2017) Our Backlog
Sirison Family (Management): 28.4% Areekul Family: 18.2% Others: 53.4%
Our Shareholders
The leading mining contractor with well-established track record in Thailand and Laos 2
Long-term prospect for coal mining for national power supply based on PDP 2015
Most Competitive Player in a Favorable Market
1
and Mining Specialists Teams
3
Stable Revenue via Long-Term Contract with Credible Sponsors
Long-term contract commitments with transparent price structure provide stable and recurring revenue for coming years
2
Stable Revenue Improving EBITDA Margin
613 648 557 683 1,169 34% 34% 34% 37% 40% 0% 10% 20% 30% 40% 50% 200 400 600 800 1,000 1,200 1,400 1,600 2012 2013 2014 2015 2016
EBITDA % EBITDA (RHS)
1,736 1,841 1,585 1,445 1,238 247 731 74 56 29 30 25
500 1,000 1,500 2,000 2,500 3,000 2012 2013 2014 2015 2016
2,891
THB mm THB mm %EBITDA
1,810 1,898 1,614 1,868
Hongsa MM8 MM7 & 7/1 Others
897
146
4
Stable Revenue via Long-Term Contract with Credible Sponsors
Highly Visible Backlog with over THB 37 bn for the Next 10Years
2 2,079 10,541 21,281 3,672 37,572
Y 2015-2026 Y 2016-2025 Y 2017-2024 Y 2009-2020 5
Stable Revenue via Long-Term Contract with Credible Sponsors
2
Credible Counterparties Supported by Respective Government Highly credible sponsor
Thailand Laos
State Owned Enterprise (SOE) that is responsible for national power generation
SOEs
S&P Hongsa Power shareholders are:
BANPU (Thai listed company)
Holding State Enterprise (LHSE) a state owned enterprise solely owned by Lao’s government, represented by Lao’s Ministry of Finance
SOE/ Government Related Entities
6
Highly Experienced Management and Operational Team with Proven Track Record
Management and Operational Team with Extensive Experiences in Mining Industry
3
Chairman of the Board
−EGAT Governor (1992-1995)
Chief Executive Officer
Chief Operation Officer
Chief supply chain manager
Chief Financial Officer
Ministry of Finance (2010-2012)
Chairman of Executive Committee
Controls Group Ltd (Present)
Property Co., Ltd. (Present)
Mae Moh Director
Hongsa Director
Executive Committee member
Executive Committee member
Project manager
Project manager
7
Promising Growth From Continuing Projects
4
High visibility of future project in existing territories There are continuing projects for sites that SQ currently operates in (i.e. Mae Moh mine and Hongsa mine) which are visible projects SQ targets to bid
Project Project Year Total Production
2019 – 2030 467 m BCM
2026 – 2037 Approx. 460 m BCM
Mae Moh Mine
Project Bidding Year Total Production
2019 190 m BCM
8
Mining Market Value
9
10
2,079 10,541 21,281 3,672 37,572
Y 2015-2026 Y 2016-2025 Y 2017-2024
11
Contract Counter Parties : EGAT / ITD-SQ Project Duration : November 2008 – April 2020
Mae Moh 7 Backlog
Scope of Works Contract Volume Contract Value (THB mm) SQ’s Backlog (end of 2016) SQ’s Backlog (end of Q1/2017) Volume Value (THB mm) Volume Value (THB mm) Job 1 Soil excavation and transportation Job 2 Coal excavation and transportation Job 3 Soil transportation (excavation by EGAT) 365.0 m.BCM 50.0 m.tons 40.0 m.BCM 18,602 2,463 842 42.7 m.BCM 5.0 m.tons
1,981 243 99 38.0m.BCM 5.0 m.tons
1,753 232 94 21,906 2,323 2,079
365 98 133.7
200 400 Total Performed prior to 2012 Joint Operation (Full scope)
Job 1: Soil excavation (m.BCM)
50 11 16.8
20 40 60 Total Performed prior to 2012 Joint Operation (Full scope)
Job 2: Coal excavation (m.tons)
40 5 8.3
20 40 60 Total Performed prior to 2012 Joint Operation (Full scope)
Job 3: Soil excavation by EGAT (m.BCM)
Mae Moh 7 Hongsa Project Mae Moh 8
13.7 27.0 41.4 69.2 91.0 95.7 95.7 38.0 50 100 150 2012 2013 2014 2015 2016 Q1/2017 Backlog
Cumulative Actual Backlog
0.4 3.6 7.1 8.3 8.3 0.0 5 10 15 2012 2013 2014 2015 2016 Backlog
Cumulative Actual Backlog
2.7 5.4 7.6 10.0 11.8 11.8 11.8 5.0 5 10 15 20 2012 2013 2014 2015 2016 Q1/2017 Backlog
Cumulative Actual Backlog
12
Mae Moh 8 Backlog
Scope of Works Contract Volume Contract Value (THB mm) SQ’s Backlog (end of 2016) SQ’s Backlog (end of Q1/2017) Volume Value (THB mm) Volume Value (THB mm) Job 1 Soil excavation and transportation Job 2 Coal excavation and transportation 375.0 m.BCM 31.0 m.tons 21,641 1,230 365.4 m.BCM 31.0 m.tons 20,598 1,230 361.0 m.BCM 31.0 m.tons 20,051 1,230 22,871 21,828 21,281
Job 1: Soil excavation (m.BCM) Job 2: Coal excavation (m.tons)
1.4 9.6 14.0 361.0
2015 2016 Q1/2017 2018 2019 2020 2021 2022 2023 2024 2025 Backlog
Cumulative Actual Cumulative Planned Backlog
31.0
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Backlog
Cumulative Planned Cumulative Actual / Backlog
Contract Counter Parties : EGAT / SQ Project Duration : January 2016 – December 2025
Mae Moh 7 Hongsa Project Mae Moh 8 13
Hongsa Project Overview
Total Coal Resource : Approx. 577.4 m.tons Potential Future Projects:
and coal of 1,250 m.BCM and 370.8 m.tons, respectively
Dumping Area Dumping Area
Mining Area
Hongsa Power Plant Hongsa Mine Planning Existing Capacity Coal Usage : approx. 14 m.tons/ year
Installed Capacity (MW) Utilized Capacity (MW) 1 626 551 2 626 551 3 626 551 Total 1,878 MW 1,653 MW
Mae Moh 7 Hongsa Project Mae Moh 8 14
Contract Counter Parties : HPC / SQ Project Duration : June 2015 – December 2026
Hongsa Project Backlog
Scope of Works Contract Volume Contract Value (THB mm) SQ’s Backlog (end of 2016) SQ’s Backlog (end of Q1/2017) Volume Value (THB mm) Volume Value (THB mm) Job 1 Soil excavation and transportation Job 2 Coal excavation and transportation 207.0 m.BCM 82.5 m.tons 8,481 3,262 186.5 m.BCM 79.6 m.tons 7,624 3,140 182.9 m.BCM 78.7 m.tons 7,447 3,094 11,743 10,764 10,541
Job 1: Soil excavation (m.BCM) Job 2: Coal excavation (m.tons)
6.0 20.5 24.1 182.9
2015 2016 Q1/2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 Backlog
Cumulative Planned Cumulative Actual Backlog
2.9 3.8 78.7
2015 2016 Q1/2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 Backlog
Cumulative Planned Cumulative Actual Backlog
Mae Moh 7 Hongsa Project Mae Moh 8 15
16
Total Revenues (THB.m)
Key Financial Highlights – Stable Revenue with EBITDA Margin Growth
Stable revenue with promising growth from new project acquisition
1,736 1,841 1,585 1,445 1,238 342 245 247 731 178 223
897 154 547 74 56 29 30 25 7 4 500 1,000 1,500 2,000 2,500 3,000 3,500 2012 2013 2014 2015 2016 Q1/2016 Q1/2017
1,019 2,891
Hongsa MM8 MM7 & 7/1 Others
681 1,868 17
Profits (THB.m)
Key Financial Highlights – Stable Revenue with EBITDA Margin Growth
501 480 381 490 828 191 395 613 648 551 680 1,169 286 453 101 141 49 89 323 71 226
33.9% 34.1% 34.5% 36.6% 40.4% 42.0% 44.5% 6% 7% 3% 5% 11% 10% 22% 27.7% 25.3% 23.6% 26.2% 28.6% 28.1% 38.8% 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50%
175 375 575 775 975 1,175 1,375 2012 2013 2014 2015 2016 Q1/2016 Q1/2017
Gross Profit EBITDA NI
THB.m %GP %EBITDA %NI
18
18
Annual Operating Trends
Net Profit (THB.m) 2015 2016
Q1/2017
Net Profit before tax 121.18 422.48 280.20 Less : Extra ordinary items
26.00 22.87
16.10
18.33
23.88 Normalized Net Profit before tax 179.48 448.48 303.07 % of Revenue 9.61% 15.51% 29.74% Description
19
2,867 2,749 4,489 6,004 6,042 2,527 2,360 3,749 3,753 3,561 340 389 740 2,251 2,482
5.65 3.72 3.00 1.12 0.95 2.96 2.60 3.25 2.15 1.30 0.83 0.73 1.38 2.59 2.67 (14) (9) (4) 1 6 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000
2013 2014 2015 2016 Q1/2017
Assets Liabilities Shareholder's Equity IBD/Equity IBD/EBITDA DSCR 1.IBD/Equity ≤ 2 2.IBD/EBITDA ≤ 4 3.DSCR ≥ 1.2
Financial Covenant Assets, Liabilities and Shareholder’s Equity / Liquidity
times THB.m
Key Financial Highlights
20
Key Financial Highlights
4.6% 1.8% 2.5% 6.2% 15.0% 21.8% 20.8% 20.6% 26.2% 38.1%
0% 10% 20% 30% 40% 50%
2013 2014 2015 2016 2017
Return on Assets Return on Fixed Assets
Operating Performance
Note: * Annualized net profit to calculate key ratios for 1Q2017
21
22
23
Mae Moh Mine Planning Mae Moh Power Plant
Remaining Coal Resource : Approx. 300 million tons Potential Future Projects: Existing Capacity Coal Usage : approx. 15 mil. tons/ year
Units Installed Capacity 4 – 7 4 x 150 MW 8 – 13 6 x 300 MW Total 2,400 MW Project Description Bid Open Project Duration Phase 9
2017 2019 – 2030 Phase 10
2024 2026 – 2037 Phase 11
2027 2029 – 2045
Mae Moh Project Overview
Mae Moh 7 Hongsa Project Mae Moh 8
* Estimated
24
25
Potential Project Bidding Year Total Production Phase G 2019 190 MBCM
Total Coal Resource : Approx. 577.4 m.tons Potential Future Projects:
and coal of 1,250 m.BCM and 370.8 m.tons, respectively
Dumping Area Dumping Area
Mining Area
Existing Capacity Coal Usage : approx. 14 m.tons/ year
Installed Capacity (MW) Utilized Capacity (MW) 1 626 551 2 626 551 3 626 551 Total 1,878 MW 1,653 MW
26
SQ is No. 1 Mining Contractor with only one competitor
CLMV Market
Myanmar Cambodia Vietnam laos
Myanmar
Laos
Cambodia
Vietnam
Estimated Size : 100,000 MB.
27
Project Project Value Project Duration Phase 1: Tin Concentrate 3,672 THB mm 2017 - 2024
28
29