Construction and Long Construction and Long- -Term Performance of - - PowerPoint PPT Presentation

construction and long construction and long term
SMART_READER_LITE
LIVE PREVIEW

Construction and Long Construction and Long- -Term Performance of - - PowerPoint PPT Presentation

Construction and Long Construction and Long- -Term Performance of Term Performance of Innovative Geotechnologies Innovative Geotechnologies Steven F. Bartlett Ph.D., P.E. Steven F. Bartlett Ph.D., P.E. Associate Professor University of Utah


slide-1
SLIDE 1

Construction and Long Construction and Long-

  • Term Performance of

Term Performance of Innovative Geotechnologies Innovative Geotechnologies

Steven F. Bartlett Ph.D., P.E. Steven F. Bartlett Ph.D., P.E. Associate Professor University of Utah

slide-2
SLIDE 2

I-

  • 15 Project Limits

15 Project Limits

  • Approx. 100,000 cubic meters of geofoam was placed
slide-3
SLIDE 3

I-

  • 15 Reconstruction

15 Reconstruction -

  • Quick Facts

Quick Facts

  • Single Largest Design-Build Highway Contract in U.S.
  • 17 Miles of Urban Interstate

17 Miles of Urban Interstate

  • $1.5 Billion (Project Cost)
  • Wasatch Constructors (Prime Contractor)
  • 4 Year Construction Duration (1997 - 2001)
  • 144 Bridges/Overpass Structures

144 Bridges/Overpass Structures

  • 160 Retaining Walls (mostly MSE Walls)
  • $350 K Embankment Study
slide-4
SLIDE 4

Geotechnical Issues Geotechnical Issues

  • Large Primary Consolidation Settlement (1 to 1.5 m)

g y ( )

  • Time Rate of Consolidation (2 years to end of primary)
  • Creep Settlement (Bump at Bridge)
  • Creep Settlement (Bump at Bridge)
  • Foundation Stability (Large Embankments on Soft Soils)
  • Schedule Constraints (two 2-year projects)
  • Maintenance of Traffic (Had to be maintained)
  • New Technologies and Development of Specifications
slide-5
SLIDE 5

Subsurface Profile in Salt Lake Valley Subsurface Profile in Salt Lake Valley

Upper Bonneville Clay Lower Bonneville Clay Interbeds

slide-6
SLIDE 6

Settlement of Soft Clays Settlement of Soft Clays in Salt Lake Valley in Salt Lake Valley

Approximate 2 years of primary settlement

slide-7
SLIDE 7

I-

  • 15 Embankment Construction

15 Embankment Construction 2-

  • stage MSE wall with surcharge

stage MSE wall with surcharge g g g g

slide-8
SLIDE 8

Prefabricated Vertical Drains Prefabricated Vertical Drains

Installed drain PV Drain Spacing 1.5 to 2.5 m Installed drain PV Drain Spacing 1.5 to 2.5 m triangular spacing PV drain pushed into ground Placement of anchor bar

slide-9
SLIDE 9

2-

  • Stage MSE Walls

Stage MSE Walls

Right-of-way constraints required many slopes to be built vertically. y p y Beginning of 2-stage MSE Wall

slide-10
SLIDE 10

2-

  • Stage MSE Wall Connections

Stage MSE Wall Connections

Female threaded rod coupler Attachment of Panels with threaded rod Concrete Fascia Panel

slide-11
SLIDE 11

2-

  • Stage MSE Wall with

Stage MSE Wall with Prefabricated Vertical Drains Prefabricated Vertical Drains Prefabricated Vertical Drains Prefabricated Vertical Drains Cost and Schedule Comparison Cost and Schedule Comparison

Total cost is for 10 m length of embankment

slide-12
SLIDE 12

I-

  • 15 Embankment Construction

15 Embankment Construction 1 stage MSE wall with lime cement columns stage MSE wall with lime cement columns 1-stage MSE wall with lime cement columns stage MSE wall with lime cement columns

slide-13
SLIDE 13

Lime Cement Stabilized Soil Lime Cement Stabilized Soil

Auger / Mixer for Lime and Cement Lime Cement Column Rig 125 kg/m3 15% lime 85% cement M = 30 Mpa (design); Su 300 to 400 kPa

slide-14
SLIDE 14

Lime Cement Column Installation Pattern Lime Cement Column Installation Pattern

slide-15
SLIDE 15

1-

  • Stage MSE Wall Construction

Stage MSE Wall Construction

Finished MSE wall 1-stage MSE placed over columns

slide-16
SLIDE 16

1-

  • Stage MSE Wall with

Stage MSE Wall with Lime Cement Stabilized Soil Lime Cement Stabilized Soil Lime Cement Stabilized Soil Lime Cement Stabilized Soil Cost and Schedule Comparison Cost and Schedule Comparison

Total cost is for 10 m length of embankment

slide-17
SLIDE 17

I-

  • 15 Reconstruction

15 Reconstruction Geofoam Embankment Geofoam Embankment Geofoam Embankment Geofoam Embankment

slide-18
SLIDE 18

I-

  • 15 Reconstruction

15 Reconstruction Geofoam Properties Geofoam Properties p

* I-15 used 1.25 pcf density exclusively (i.e., type VIII geofoam)

slide-19
SLIDE 19

Geofoam (I Geofoam (I-

  • 80 State Street to 200 West St.)

80 State Street to 200 West St.)

slide-20
SLIDE 20

Geofoam Embankment Construction Geofoam Embankment Construction

Base Sand Base Sand Footing for Panel Wall and Block Placement

slide-21
SLIDE 21

Geofoam Embankment Construction Geofoam Embankment Construction

Geofoam cut and placed around piling at bridge abutment Nearly Completed Geofoam Embankment with Vertical Face Transition Zone with MSE Wall

slide-22
SLIDE 22

Geofoam Embankment Construction Geofoam Embankment Construction

Completed Load Distribution Slab Reinforced Concrete Load Distribution Slab

slide-23
SLIDE 23

Geofoam Embankment Finished Geofoam Embankment Finished

slide-24
SLIDE 24

Geofoam Embankment with Geofoam Embankment with Tilt Tilt up Panel Wall up Panel Wall Tilt Tilt-up Panel Wall up Panel Wall Cost and Schedule Comparison Cost and Schedule Comparison

Total cost is for 10 m length of embankment

slide-25
SLIDE 25

Final Cost and Schedule Comparison Final Cost and Schedule Comparison p

140 160 100 120 140

Geofoam

60 80

LCC and Wall 2 St MSE

20 40

2-Stage MSE Wall

Cost $10 K Time (weeks) ( )

Cost represents total construction costs for each system for a 10-m long reach of interstate. Construction time is typical for embankments built on the I-15 Reconstruction Project.

slide-26
SLIDE 26

Performance Monitoring Performance Monitoring Objectives of Geofoam Arrays Objectives of Geofoam Arrays j y j y

M C S ttl t f G f M (10 )

  • Measure Creep Settlement of Geofoam Mass (10 yr.)
  • Measure the Pressure Distribution within Geofoam

M Diff i l S l i T i i Z

  • Measure Differential Settlement in Transition Zones
  • Measure Lateral Earth Pressure at Abutments
  • Monitor for Differential Icing at Geofoam /

Embankment Transition Zones

  • Model Stress / Strain Behavior

Model Stress / Strain Behavior

slide-27
SLIDE 27

Typical Geofoam Array Typical Geofoam Array

ROW OF SURVEY POINTS AT FACE OF WALL 25 MM - PVC STAND PIPE ROW OF SURVEY POINTS ALONG OUTSIDE EDGE OF EMERGENCY LANE ROW OF SURVEY POINTS ALONG INSIDE EDGE OF MOMENT SLAB CONCRETE PAVEMENT ROAD BASE LOAD DISTRIBUTION SLAB LEVEL 7.5 SQUARE PLATE WITH MAGNET RING LEVEL 6 6.5 TO 7.3 m GEOFOAM BLOCKS LEVEL 4 LEVEL 2 HEIGHT VARIES GRANULAR BACKFILL LEVEL 0 BEDDING SAND 2.5 m VIBRATING WIRE TOTAL PRESSURE CELL

slide-28
SLIDE 28

3300 South Geofoam Array Installation 3300 South Geofoam Array Installation

Magnet Extensometer and Pressure Cell Installation Pressure Cell Installation Hotwire Cut for Pressure Cell Pressure Cell Cast in Bridge Abutment Pressure Cell in Base Sand

slide-29
SLIDE 29

3300 South Array Settlement Data 3300 South Array Settlement Data

9 9 9 9 9 9 1 1 1 1 1 01/20/99 03/21/99 05/20/99 07/19/99 09/17/99 11/16/99 01/15/00 03/15/00 05/14/00 07/13/00 09/11/00 11/10/00 01/09/01 03/10/01 05/09/01 07/08/01 09/06/01

10 20 30

mm)

40 50 60

tlement (m

70 80 90

Sett

100

Level 0 Level 2 Level 4 Level 6 L l 8 Construction Completed (7/28/99) Level 8 Level 9 Load Distribution Slab placed Load Distribution Slab Curb placed Granular Borrow Open Graded Base PCCP Pavement

Approx. 1% Construction Strain

slide-30
SLIDE 30

3300 South Geofoam Array 3300 South Geofoam Array

Damage to Connections During Construction Damage to Connections During Construction g g g g Loading Loading

Damaged Connection

  • Approximately 1%

loading strain can be loading strain can be expected.

  • Strain due to seating of

untrimmed block and elastic compression.

  • Damaged connection

g was later repaired by dowels.

  • Rigid connect should be
  • Rigid connect should be

avoided.

slide-31
SLIDE 31

Settlement at Toe of Wall Settlement at Toe of Wall

slide-32
SLIDE 32

Geofoam Transition Zones Geofoam Transition Zones Post Post-

  • Construction Settlement

Construction Settlement

Transition slope 3.5 H : 1 V

25.0

ent

face of wall 5/30/00 face of wall 3/18/01

Transition zone

15.0 20.0

uction Settlem e (m m )

inside edge of moment slab 5/30/00 inside edge of moment slab 3/18/01

Geofoam MSE Wall

0.0 5.0 10.0

Post-Constru (

  • utside edge
  • f emergency

lane 5/30/00

  • utside edge
  • f emergency

lane 3/18/01 baseline survey completed on 11/10/99. 25340 25350 25360 25370 25380 25390 25400 25410 25420 25430 25440 25450 25460 25470 25480 25490

Mainline Stationing (m)

slide-33
SLIDE 33

Settlement Monitoring 100 South Street Settlement Monitoring 100 South Street

projected 0.5 % additional 50 yrs. 1% construction strain

slide-34
SLIDE 34

Pressure Cell Measurements in Geofoam Pressure Cell Measurements in Geofoam

Pressure Versus Time 3300 South Street Geofoam Array

60 0 70.0 80.0

a)

  • Sta. 25+315, Level 0
  • Sta. 25+347, Level 0
  • Sta. 25+315, Level 6
  • Sta. 25+347, Level 5
  • Sta. 25+315, Level 9

40.0 50.0 60.0

essure (kPa

,

  • Sta. 25+347, Level 8

10 0 20.0 30.0

Pre

0.0 10.0 /20/99 /21/99 /20/99 /19/99 /17/99 /16/99 /15/00 /15/00 /14/00 /13/00 /11/00 /10/00 1/9/01 /10/01 5/9/01 7/8/01 9/6/01 1/5/01 1/ 3/ 5/ 7/ 9/ 11/ 1/ 3/ 5/ 7/ 9/ 11/ 1 3/ 5 7 9 11

Date

slide-35
SLIDE 35

Geofoam Performance Summary Geofoam Performance Summary Geofoam Performance Summary Geofoam Performance Summary

1. Geofoam fills are performing as expected 2 A i l 1 i l i d d i 2. Approximately 1 percent vertical strain occurred during construction. a. Strain due to seating and compression of geofoam. b. This strain can damage rigid connections. 3. Approximately 0.3 percent creep strain (15 mm) has occurred in the geofoam for an 8-year post construction period. This is acceptable and within the expected performance. 4. The vertical stress distribution that develops in a geofoam wedge p g g fill is complex, but generally diminishes with depth. 5. Pressure cell measurements suggest that approximately 45 kPa of vertical stress has developed in the center of the geofoam mass vertical stress has developed in the center of the geofoam mass. This is approximately 50 percent of the compressive strength of the geofoam.

slide-36
SLIDE 36

Settlement Comparison Settlement Comparison I-

  • 15 Geotechnologies

15 Geotechnologies g

slide-37
SLIDE 37

Settlement Conclusions Settlement Conclusions G I-

  • 15 Geotechnologies

15 Geotechnologies

  • Geofoam has met the 75 mm (3 inch) in 10-yr

settlement goal in all cases.

  • LCC Treated soil has met the 75 mm in 10-yr

settlement goal. 2 Stage MSE Walls ha e not met the 75 mm in

  • 2-Stage MSE Walls have not met the 75 mm in

10-yr settlement goal for the MSE wall and embankments monitored. The expected range

  • f settlement for these system is 100 (4 in) to

150 mm (6 in) for a 10-year post construction period. period.

slide-38
SLIDE 38

Principal Investigators Principal Investigators

bartlett@civil.utah.edu @

slide-39
SLIDE 39

Published Reports Published Reports

Farnsworth C. F., Bartlett S. F., Negussey, D. and Stuedlein A. 2008, “Construction and Post-Construction Settlement Performance of Innovative Embankment Systems, I-15 i j S l k Ci h ” l f G h i l d i l Reconstruction Project, Salt Lake City, Utah,” Journal of Geotechnical and Environmental Engineering, ASCE (Vol. 134 pp. 289-301). Bartlett, S. F. and Lawton E. C., 2008, “Evaluating the Seismic Stability and Performance of , , , g y Freestanding Geofoam Embankment,” 6th National Seismic Conference on Bridges and Highways, Charleston, S.C., July 27th –30th 2008, 17 p. N M P B tl tt S F L t E C “N i l M d li f G f Newman, M. P., Bartlett S. F., Lawton, E. C., “Numerical Modeling of Geofoam Embankments,” Journal of Geotechnical and Environmental Engineering, ASCE (final review). Bartlett S. F., Farnsworth, C., Negussey, D., and Stuedlein, A. W., 2001, “Instrumentation and Long-Term Monitoring of Geofoam Embankments, I-15 Reconstruction Project, Salt Lake City, Utah,” EPS Geofoam 2001, 3rd International Conference, Dec. 10th to 12th, 2001, Salt Lake City Utah 23 p Salt Lake City, Utah, 23 p.

slide-40
SLIDE 40

Published Reports Published Reports

Negussey, D., Stuedlin, A. W., Bartlett, S. F., Farnsworth, C., “Performance of Geofoam Embankment at 100 South, I-15 Reconstruction Project, Salt Lake City, Utah,” EPS G f 2001 3 d i l C f 10th 12th 2001 S l k Ci h Geofoam 2001, 3rd International Conference, Dec. 10th to 12th, 2001, Salt Lake City, Utah, 22 p. Bartlett, S. F., Negussey, D., Kimball, M., 2000, “Design and Use of Geofoam on the I-15 , , g y, , , , , g Reconstruction Project,” Transportation Research Board, January 9th to 13th, 2000, Washington, D.C., 20 p. B tl tt S F 2005 “Li ht i ht S l ti ” I f t t T h l S i 2005 Bartlett, S. F., 2005, “Lightweight Solution,” Infrastructure Technology, Spring 2005, pp. 36-40 (Chinese and English). Bartlett, S. F., Negussey, D. and Kimble, M., 2000, “Design of Geofoam Embankments for g y g the I-15 Reconstruction,” Conference on Application and Design of Expanded Polystrene, Sponsored by Taiwan Area National Expressway Engineering Bureau and China Engineering Consultants, Inc., March 3rd, 2000, Taipei, Taiwan, 20 p. (in Chinese).