connect 2020 update
play

Connect 2020 Update Citizens Oversight Panel March 5, 2020 Connect - PowerPoint PPT Presentation

Connect 2020 Update Citizens Oversight Panel March 5, 2020 Connect 2020 team members Marie Olson Sandee Ditt Executive Operations Director - Transit Expansion Customer Outreach Specialist Head of Connect 2020 Operations Head of Connect 2020


  1. Connect 2020 Update Citizens Oversight Panel March 5, 2020

  2. Connect 2020 team members Marie Olson Sandee Ditt Executive Operations Director - Transit Expansion Customer Outreach Specialist Head of Connect 2020 Operations Head of Connect 2020 Ambassador Program 2

  3. Behind the Scenes 3

  4. Connect 2020 Schedule WEEKEND WEEKEND WEEKEND CLOSURE CLOSURE CLOSURE PHASE PHASE Jan. 6 – Feb. 7 Feb. 10 – Mar. 13 1 2 Mar. Feb. Jan. 14 - 15 4 - 6 8 - 9 Single Tracking on NB – Working on SB Single Tracking on SB – Working on NB Regular service resumes March 16 4

  5. East Link / Blue Line Overview To Northgate 10 stations 14 miles Opens 2023 To Angle Lake 5

  6. Adjacent Construction 6

  7. Track-bed Preparation 7

  8. Track Installation 8

  9. Systems Work 9

  10. Testing and Safety Certification 10

  11. NB Single Track Operations Field video - Northbound 11

  12. 12

  13. 13

  14. Full weekend closures Capitol Hill - SODO 14

  15. Southbound platform closure February-March 15

  16. Center Platform Transfer 16

  17. Public Safety • Security operating 24/7, increased staffing from 6am – 10pm. • Bikes required to exit train prior to Pioneer Square Station. • No fares during weekend closures to speed transfers between Link and bus shuttles. • The overall passenger response has been supportive and positive. 17

  18. Temporary Signage: 18

  19. Ambassador Program • 930 staff have participated. • More than 11,000 staff hours of outreach. • Ambassadors answering questions and receiving feedback. 19

  20. Feedback Customer Service 169 total • Announcements (57) • Early/Late Operations (35) Social - Twitter 246 total • Neutral or positive (173) • Negative (73) 20

  21. Microsite 21

  22. Partner Agencies 22

  23. Thank you. soundtransit.org

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.