Combined License Application Review STP Units 3 and 4 Safety Panel - - PowerPoint PPT Presentation

combined license application review stp units 3 and 4
SMART_READER_LITE
LIVE PREVIEW

Combined License Application Review STP Units 3 and 4 Safety Panel - - PowerPoint PPT Presentation

NRC-012 Combined License Application Review STP Units 3 and 4 Safety Panel 1 November 19, 2015 Panelists Tom Tai Senior Project Manager Richard Turtil Senior Financial Analyst Dinesh Taneja Senior Electronics


slide-1
SLIDE 1

Combined License Application Review STP Units 3 and 4

Safety Panel 1 November 19, 2015

NRC-012

slide-2
SLIDE 2

2

Panelists

  • Tom Tai – Senior Project Manager
  • Richard Turtil – Senior Financial

Analyst

  • Dinesh Taneja – Senior

Electronics Engineer

slide-3
SLIDE 3

Departures Summary

  • Total departures – 275
  • Departures – Tier 1, Tier 2*, Tier 2

and Technical Specifications (TS)

  • Tier 1, Tier 2*, and TS departures

require NRC approval

  • Tier 2 departures generally do not

require NRC approval

3

slide-4
SLIDE 4

Tier 1 and TS Departures

  • Tier 1 departures – depart from

certified portion of design

  • TS departures – depart from

ABWR Technical Specifications

  • Exemptions are required for Tier

1 and TS departures

4

slide-5
SLIDE 5

Tier 2* and Tier 2 Departures

  • Tier 2* departures require NRC

approval but do not require an exemption

  • Tier 2 departures use 50.59-like

change process

  • One Tier 2 departure required

prior NRC approval

5

slide-6
SLIDE 6

Tier 2 Departures

  • Staff confirmed it was reasonable

that Tier 2 departures do not require NRC approval – Applied 50.59-like criteria – Examined applicant’s process – Some requests for additional information

6

slide-7
SLIDE 7

Exemptions

  • Exemption request for material

control and accounting

  • Exemption request for financial

qualifications

7

slide-8
SLIDE 8

Examples Covered In This Presentation

  • Exemption request – financial

qualifications

  • Tier 1 departure – STD DEP 3.4-1,

Safety Related I&C Architecture

8

slide-9
SLIDE 9

Current Regulatory Framework for Financial Qualifications

  • Current requirements in 10 CFR

50.33(f) and Part 50, Appendix C

  • COL applicants must possess or

have reasonable assurance of

  • btaining the funds to cover

construction and operation costs

9

slide-10
SLIDE 10

Challenges With Current Standard

  • Applicant could not meet current

requirements and requested a more flexible approach

  • SECY-13-0124 provided policy options

for Commission action

10

slide-11
SLIDE 11

SRM on SECY-13-0124

  • Change Part 50 by rulemaking to use

Part 70 standard

  • Applicants can rely on license

conditions

  • Consider granting exemptions during

pendency of rulemaking, but exemptions must anticipate the

  • utcome of the rulemaking

11

slide-12
SLIDE 12

Draft Regulatory Basis

  • Draft Regulatory Basis addressed

new Part 70 standard

  • Staff discussed draft proposed

requirements with public and solicited comment

  • Comments supported change in

financial qualification standard

12

slide-13
SLIDE 13

Financial Capacity

  • Reflects applicant’s understanding of

project size and scope

  • Is not a predictive finding that

applicant will obtain financing

  • Supports staff’s determination that

applicant appears to be financially qualified

13

slide-14
SLIDE 14

NINA Exemption Request

  • NINA provided:

– Reasonable cost estimates for construction and operation – Acceptable Financial Capacity Plan – License conditions ensuring adequate funding prior to construction and operation

14

slide-15
SLIDE 15

NINA Exemption Request

  • NINA meets the proposed

standards in the Draft Regulatory Basis

  • NINA satisfies the requirements

for an exemption

  • NINA’s exemption request should

be granted

15

slide-16
SLIDE 16

Tier 1 Departure On I&C Architecture

  • Selection of digital

instrumentation and control (I&C) platforms resulted in changes to I&C architecture

  • Data communication design

changed the most

16

slide-17
SLIDE 17

Tier 1 Departure On I&C Architecture

  • Diverse digital platforms are used

for the Engineered Safety Features System and the Reactor Trip System

  • Changes enhance protection

against failures

17

slide-18
SLIDE 18

Tier 1 Departure On I&C Architecture

  • Review based on current

regulations and staff guidance

  • Staff concluded the modified I&C

design conforms with current requirements

18

slide-19
SLIDE 19

19

Questions?

slide-20
SLIDE 20

20

Backup Slides

slide-21
SLIDE 21

Certified U.S. ABWR Ring Bus Design

21

Actuator 1 Sensor 1 Actuator N Sensor N

to to

Ring Bus RPS/MSIV ECCS SSLC/Trip Representation

  • f a Single Division
slide-22
SLIDE 22

STP Point-to-Point Data Communication Design

22

Actuator 1 Sensor 1 Actuator N Sensor N

to to

RPS/MSIV ECCS SSLC/Trip Representation

  • f a Single Division